Construction of Room for filteration water plant

S.NO NAME A/U QTY RATE/ UNIT QTY RATE REMARKS


1 CEMENT bags 48 1300 62400
2 CRUSH sqft 150 130 19500
3 SAND sqft 200 130 26000
4 STEEL 4mm kg 440 270 118800
5 BINDING WIRE KG 7 350 2450
6 DOOR 5’x7’ 1 ---- 10000
7 BRICKS nos 6000 10 60000
8 SOIL FILLING M3 300 ---- 5000
9 DISTEMPER bkt 2 --- 8000
10 WEATHER SHIELD GLN 2 --- 10000
11 ELECTRIC WORK 20000
12 VENT NO 2 250 500
13 CONTRACT 70,000
LABOUR
14 TRNPT CHARGES 20000
15 PLUMBER WORK 5000
16 TOTAL 437650

Initially the Transport charges of Bricks crush sand were not considered. In addition to this the
earth filling work was not included. Moreover the extra labour charges has been concluded due
to shifting of materials i.e bricks sand and crush etc. From outside of site due to no route for
tractor trolly