The document provides a summary of items, descriptions, units, quantities, and rates for piling work. It includes the provision of piling equipment, maintenance and handling of equipment on site, supply and delivery of initial and extension concrete piles up to specified lengths, driving of initial piles to a maximum depth, joining of pile extensions with steel plates, and cutting pile heads to required levels. The total cost of the piling work is not provided in the 3 sentence summary.
The document provides a summary of items, descriptions, units, quantities, and rates for piling work. It includes the provision of piling equipment, maintenance and handling of equipment on site, supply and delivery of initial and extension concrete piles up to specified lengths, driving of initial piles to a maximum depth, joining of pile extensions with steel plates, and cutting pile heads to required levels. The total cost of the piling work is not provided in the 3 sentence summary.
The document provides a summary of items, descriptions, units, quantities, and rates for piling work. It includes the provision of piling equipment, maintenance and handling of equipment on site, supply and delivery of initial and extension concrete piles up to specified lengths, driving of initial piles to a maximum depth, joining of pile extensions with steel plates, and cutting pile heads to required levels. The total cost of the piling work is not provided in the 3 sentence summary.
Allow for the provision of all necessary piling equipment
plant, tools and anciallary equipment for their transport 1 to the site, handling, assembling erecting, dismanting item item and removal off site after completion of piling operation.
Allow for maintaining, moving and handling piling
equipment on site as often and whenever necessary for 2 item item the whole operation including all maintenance and idling time.
175mm x 175mm 'Hume' or approved equivalent
square reinforced concrete Grade 45 piles to M.S ISO 9002 as described
Supply, deliver an unload 6.00m long initial piles with
3 NO. 43 175mm x 175mm x 1.25 kg wild steel shoe.
Supply, deliver and unload extension piles not
4 m 129 exceeding 3.00m.
Supply, deliver and unload extension piles exceeding
5 3.00m.
Driven length vertical initial piles to the maximum depth
6 m 774 of 26 meters.
Piles extension joint fixed with 16mm thick mild steel
plate 175mm x 175mm overall with splayed corners 7 N0. 172 with 50mm x 50mm mild steel plate and filled welded around the joint perimeter.
Cut off pile heads to the required levels including
cutting back, dressing for key and exposing 8 NO. 43 reinforcement bars for connecting to pile caps (measured seperately) and remove all debris from site.