EHSMSM/WORKS/446/4009 Rev No.

01 Effective Date: 16/10/2006


SAFE WORK PROCEDURE - FOR TENTATIVE JOB
(Performance Criteria – Perfection in job with no injury to persons or damage to property)
AIC Leader : PRATAP KR. SINHA
1. DEPARTMENT : ENGG. & PROJECT DOC. NO. : E&P/SAF-TSJ-LD#1&2 Long tom Area-Elect/EHSMS/SWP/4702
2. SECTION / LOCATION : LD-1, LD-2, Long tom Area NAME OF WORKING AGENCY : G.B. ENGINEERS
3. JOB TITLE : Misc. Electrical work D. O. NO. : 3700882605/109 dt. 09.06.2023
4. JOB DURATION : START DATE 09.06.2023 END DATE 30.06.2024 W. O. NO. : 4200001761/109 dt. 23.06.2021

Sl. Activities Hazards Safety Precautions Persons Condition of Tools/ Reference to document /
No. (Sequence of work) Responsible Tackles required criteria and remarks
Name & G P. No. OK / NOT OK
Unawareness of safety a) Written clearance to be taken before starting the job from concern authorities.
1) General Safety appliances may cause b) Safety induction training to be given to all workmen. TSL SS/GEN - 04
activities before damage loss or accident c) Brief description about hazards/safety measure to be given to all workmen at Mr. Anil Kumar SS/GEN - 05
starting the job every morning before starting of the job. Tool box talk (Mob-9204750502) SS/GEN - 06
d) First aid box to be kept at site. SS/GEN - 07
e) All traffic rules will be followed in site works. Mr. S.F Hussain SS/ENGG - 07
f) All workmen will be use safety helmet, safety boot, safety goggles and others safety (Mob-9234511429) SS/ENGG - 13
appliances properly (Manufacture as per standard) SS/ENGG - 27
g) Constant supervision will be there at site.
h) Always one safety sup and flagmen must be present at site.
i) Welding m/c and DB to be kept at protected area as per safety standard of TSL
j) LPG and Oxygen cylinder to be kept vertically separately (min. gap 3mtr) protected
and well mentioned area & bring in use with proper pressure gauge & safety devices
k) Use scrap bin for scrap dumping
l) Submit workmen list who will work at site. G. B. Engineers
m) Gas cylinder will be carried one site to another site by trolley (Bulk LPG and O2 P. Mandal
cylinder not carry together) (Mob- 8603401650)
n) Certified welder / electrician / rigger to be provided with copies of certificate of
Electrician / welder / rigger will be submitted before starting the job. S.K Paul
o) Tools & tackles certificate to be submitted before starting the job. (Mob- 7209336162)
p) Medical fitness certificate of all workmen for height work to be submitted before
starting the job.
q) Do not work in such places where another work is going in different level and
do not work in barricaded area of another agency.
r) Six direction hazard form to be filled up daily basis.
s) All Elect. equipt / lighting system should be kept in off position when not in use.

Dept. (E&P) TSL (Safety) G. B. ENGINEERS

Note : 1.This Safe Work procedure shall be prepared by owner department countersigned by Working agency / contractor’s representative and safety department.
2. Sequence of work shall involve step-by-step jobs. 3. All possible hazards including proximity hazards shall be identified
4. With the change of working conditions, the procedure shall be amended and persons shall be trained accordingly.
5. Review on status of implementation shall be done through task observation (Ref. Form # EHSMSM/WORKS/446/4008) and / or site severity audit
6. Before start of the job, induction shall be given to persons engaged at site by departmental and subsequent daily induction shall be given by Working agency /Contractor's representative