Tel No.

086-317735
Trader SINOHYDRO COPERATION (M) SDN BHD 吴琦 / 聂超
Person in charge Fax No. 086-317736
Clarification Sheet (1) 3/18/2015
Job No. SAKURA-FB-2014001 Project SAKURA Project - Earthwork Reply Deadline 3/22/2015
Item Quantity of Volume Cut and Fill SCC MR.No. SCC-MR-001
No. Description Vender Response Remarks
1 Attachment-1 and 1A
(1) we are feel uncertain which is the correct volume
(1) Back filling at Access road at platform 5.5 m near RC bridge, the
survey data and calculation from Your giving is amounting to
7,301.00 m3, but the calculation from surveyor Mr. Liu Zhi Hong is
13,937.80 m3
(2) The back filling volume at platfrom 7.0 m (Sino Storage Yard) as (2) we wish to know the volume of back filling (out side of
per mark at cloud our platfrom boundary)
(3) Back filiing works at platfrom 5.5 m near the existing guard house, (3) is Meaning to say from the Total of volume of back filling
Your giving calculation is 2,691.00 m3 was carry out by SINO work at platfrom 5.5m need to deduct of 2,691.00 m3 (carry
construction department & swee cheng work done is amounting to by SINO) form our contract, because all the back filling
1,601.00 m3 works at platfrom 5.5 m was carry by us

2 Attachment 2 and 2 A
Excavation works at the Tunnel foundation at platfrom 20.0 m, the we are feel uncertain which is the correct volume
calculation from Your giving is 2,072.00 m3, but the calculation from
Surveyor Mr. Liu Zhi Hong is 6,106.80 m3

3 Attachment 3
Excavation work at platfrom 5.5 m along the road side and river
diversion from CH 0+00 to CH 0+180 Please to confirm the Volume was calculation by your
Surveyor Mr. Liu Zhi Hong in amounting 8,541.20 m3
4 Attachment 4
Excavation and remove the unsuitable material at platfrom 20.0 m
slope failure No.2 Please to confirm the Volume was calculate by your
Surveyor Mr.Tang Jie in amounting 6,685.00 m3
5 Attachment 5
Excavation and remove the unsuitable material at platfrom 5.5 m
existing earth drain CH0+000 m to CH 0+539.8 m Please to review and calculate the unsuitable material
volume as per attached amounting 6,591.40 m3
6 Attachment 6
Excavation works at borrow pit out side platfrom 20.0 m Plaese to confirm the volume was calculate by your
Surveyor Mr. Tang Jie in amounting 17,687.00 m3
7 Attachemnt 7
Excavation works at borrow pit out side platfrom 5.5 m
Plaese to confirm the volume was calculate by your
Surveyor Mr. Tang Jie in amounting 41,820.00 m3
8 Attachemnt 8
River diversion from CH 0+100 to CH 0+380, Stripping of top soil is Please to confirm the valume was calculate as per your
amounting to 18,403 m2, Excavation works is amounting to Surveyor Mr. Tang Jie
37,698.00 m3

Date of Reply 3/22/2015


Mr. Raymond Tan @ Signature
Vendor SWEE CHENG CONSTRCUTION Contact Person
Mr. Chai KC
聂超