Professional Documents
Culture Documents
2-1 Load Flow IEEE 30 Bus - Summary
2-1 Load Flow IEEE 30 Bus - Summary
Project: Page: 1
12.6.0H
Location: Date: 12-27-2021
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: IEEE30Bus Config.: Normal
* Indicates operating load of a bus exceeds the bus critical limit ( 100.0% of the Continuous Ampere rating).
# Indicates operating load of a bus exceeds the bus marginal limit ( 95.0% of the Continuous Ampere rating).
ETAP
Project: Page: 2
12.6.0H
Location: Date: 12-27-2021
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: IEEE30Bus Config.: Normal
Transformer
CKT / Branch Cable & Reactor
Ampacity Loading Capability Loading (input) Loading (output)
Vd
CKT / Branch From-To Bus Flow To-From Bus Flow Losses % Bus Voltage
% Drop
ID MW Mvar MW Mvar kW kvar From To in Vmag
Line33 125.688 41.787 -116.560 -35.865 9128.0 5921.9 100.0 91.8 8.17
Line35 12.662 5.987 -12.335 -9.048 327.3 -3061.6 100.0 97.2 2.77
Line38 98.259 25.157 -97.943 -24.964 316.4 193.4 91.8 91.5 0.33
Line32 10.066 7.914 -10.062 -7.966 4.5 -52.5 97.2 97.2 0.04
Line40 19.072 9.072 -19.058 -9.111 13.8 -38.9 91.5 91.4 0.07
Line39 0.000 -0.052 0.000 0.000 0.0 -52.3 93.9 93.9 0.00
Line26 -22.696 -22.652 22.732 22.634 35.2 -17.8 87.0 87.1 0.12
Line41 0.000 -0.045 0.000 0.000 0.0 -44.8 87.0 87.0 0.00
Line42 9.259 13.339 -9.135 -13.247 124.0 92.1 93.9 93.1 0.86
Line8 14.990 9.605 -14.838 -9.492 151.8 113.5 93.1 92.1 1.00
Line11 1.904 0.604 -1.902 -0.605 1.9 -1.7 93.1 93.0 0.11
Line12 -12.783 1.471 12.862 -1.413 79.3 57.7 93.1 93.6 0.52
Line15 24.375 5.652 -24.093 -5.438 282.6 213.8 95.9 94.6 1.24
Line20 -24.616 -4.850 24.900 5.065 284.1 214.9 95.9 97.1 1.23
Line44 0.000 -0.003 0.000 0.000 0.0 -3.4 95.9 95.9 0.00
Line19 -30.747 -6.574 31.182 6.904 435.0 330.7 97.1 98.6 1.53
Line18 -12.009 -2.824 12.074 2.870 64.9 46.2 98.6 99.2 0.60
Line21 -27.153 -6.514 27.485 6.766 332.5 251.8 98.6 100.0 1.35
Line13 20.957 3.826 -20.747 -3.668 210.3 158.3 94.6 93.6 1.05
Line14 -15.226 -3.756 15.329 3.832 103.6 75.9 99.2 100.0 0.76
Line9 0.000 -0.003 0.000 0.000 0.0 -3.1 92.1 92.1 0.00
Line6 48.402 38.323 -46.820 -37.112 1581.7 1211.8 100.0 96.8 3.23
Line5 38.673 30.838 -37.588 -30.008 1084.2 829.7 96.8 94.1 2.67
Line4 34.497 27.979 -33.572 -27.271 924.7 707.4 94.1 91.6 2.47
Line22 3.092 2.029 -3.085 -2.028 6.4 1.7 94.1 93.9 0.21
Line1 10.790 2.377 -10.730 -2.334 60.4 43.3 91.6 91.1 0.57
Line2 8.740 1.588 -8.701 -1.560 39.5 27.3 91.1 90.6 0.45
15675.9 10985.8
ETAP
Project: Page: 4
12.6.0H
Location: Date: 12-27-2021
Contract: SN:
Engineer: Revision: Base
Study Case: LF
Filename: IEEE30Bus Config.: Normal
% Alert Settings
Critical Marginal
Loading
Bus 100.0 95.0
Bus Voltage
OverVoltage 105.0 102.0
Generator Excitation
OverExcited (Q Max.) 100.0 95.0
Critical Report
Critical Report
Marginal Report
MW Mvar MVA % PF
Number of Iterations: 4