04 - Land Development Report, Nanded
04 - Land Development Report, Nanded
OF DPR FOR
DISCLAIMER
This document (the “Document”) has been prepared by ARINEM Consultancy Services Pvt. Ltd.
ARINEM has relied upon the information collected from the client (‘Client Inputs’) for the purpose of
inferences presented in this report.
The information, statements, statistics, and commentary (together the ‘information’) contained in
this Document have been prepared by ARINEM from primary and secondary research, ARINEM’s
internal database and to large degree, from Client Inputs and details collected from the competent
authorities. ARINEM does not express an opinion as to the accuracy or completeness of the
information provided, the assumptions made by the parties that provided the information, or any
conclusions reached by those parties. The facts quoted and inferences drawn in this Document have
been prepared based on the information received or obtained, on the basis that such information is
accurate and, where it is represented to ARINEM as such, complete.
Neither ARINEM or any of its associates, nor any of their respective Directors, employees or advisors
make any expressed or implied representation or warranty and no responsibility or liability is
accepted by any of them with respect to the accuracy, completeness or reasonableness of the facts,
opinions, estimates, forecasts, based and nothing contained herein is, or shall be relied upon as
promise or representation regarding the performance of the project. This Document is divided into
chapters and sub- sections only for the purpose of reading convenience. Any partial reading of this
Document may lead to inferences, which may be at divergence with the conclusions and opinions
based on the entirety of this Document.
The information set forth in this Document is intended solely for the use of the Client and its potential
partners to whom it has been delivered and the recipients must undertake such investigations as they
see fir before making any commitment to entering a contract. The inferences made may not cover the
opinions and views of stakeholders exhaustively.
This Document is furnished on a strictly confidential basis. Neither this Document nor the information
contained herein, may be reproduced, or passed to any person or used for any purposes other than
that stated above. By accepting a copy of this Report, the recipient accepts the terms of this Notice,
which forms an integral part of this Document.
i
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Table of Contents
CHAPTER 1- INTRODUCTION .............................................................................................1
1.1 Background ...............................................................................................................2
1.2 Purpose of this report .............................................................................................. 2
1.3 Structure of the report ............................................................................................. 2
List of Figures
Figure 1 Existing Land Use ......................................................................................................................5
Figure 2 : Site zoning for further assessment of Land use .........................................................................7
Figure 3 : Detail Plan of Zone 1 ................................................................. 7
Figure 4 : Detail Plan of Zone-2 ................................................................... 8
Figure 5 : Detail Plan of Zone-3 ......................................................................... 9
Figure 6 : Detail Plan of Zone-4 ................................................................................. 9
Figure 8 Master plan 2021 of Nanded ............................................................... 12
Figure 9 Land use around Nanded Railway Station ............................. 13
Figure 10 Land Parcels for mandatory development ........................................................................... 15
Figure 11 Proposed Relocations ........................................................................................................... 18
Figure 12 Revenue Map ........................................................................................................................20
ii
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
List of Tables
Table 1 Report Coverage........................................................................................................................3
Table 2 : Existing Building Condition ................................................................... 6
Table 3 : Detail Components of Zone-1 ..................................................................................................... 7
Table 4 : Detail Components of Zone-2 ..................................................................................................... 8
Table 5 : Detail Components of Zone-3 ..................................................................................................... 9
Table 6 : Detail Component of Zone-4 .....................................................................................................10
iii
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
CHAPTER 1- INTRODUCTION
1
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
1.1 Background
The project aims for re-development and construction of the railway station building and
supporting Facilities, including its surroundings, on the entire Railway land along with
commercial exploitation of land parcels.
The Consultants have already submitted the Inception Report, the Situation Analysis
report, & the Preliminary Land Due Diligence Report of the first deliverable KD1 of the
Mandate. This document, the Land Redevelopment Report, is a part of the second
deliverable KD2. This document refers to Infrastructure Development Report (also a part of
the second deliverable KD2) at some instances and should be read along with it.
The purpose of this report is to document and furnish the project requirements regarding
Land, based on the analysis of existing Land Use of Railway Land, conditions of assets,
need of replacement, and the permissible land use in the area. Data collected and surveys
done for the initial studies, like:
• Topographical Surveys,
• Building condition assessment,
• Land ownership and registry records
are studied. Based on the same improvements, relocations, rebuilding, improvement in
overall circulation etc. are envisaged.
This report determines availability of land for mandatory and commercial development
along with any additional land which can be taken for joint development where required.
Review the existing land use (such as buildings, structures, access Existing Land Use and the
roads, trees, green areas etc.) on the railway land surrounding the condition of Structures & assets
1 station. has been discussed in Chapter 2.
The review shall include permissible land use in the area. Permissible Land Use has been
2 discussed in Chapter 3.
Suggest improvements, relocation, rebuilding, additional civic The improvement and relocation
3 amenities and the possibility of release of space for improvement in requirements have been
circulation network and commercial development. discussed in Chapter 4 –
Improvement & Relocation
Plan of the Project site showing the existing Railway land ownership The Land ownerships has been
4 based on Land Registry Records (along with all the existing assets discussed in Chapter 5 – Land
within the boundary) and encroachments, if any, together with a Plan Schedule.
list of such encroachments along with their brief description.
2
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Land plan schedules for acquisition of additional land and/or No additional land required for
5 additional land which can be taken up for joint development where the project.
required.
Table 1 Report Coverage Source: Author
The land redevelopment report for the Project Site containing existing land use,
improvement & relocation, permissible land uses etc. has been carried out based on data
collected from the topographical survey and Urban local bodies followed by assessment of
need of improvement, rebuilding and relocation of assets. The report is structured into the
following chapters –
Chapter 1: Introduction
Chapter 2: Existing Land Use – This chapter assesses the land use within the site based on
the findings of the topographical survey.
Chapter 3: Permissible Land Use – This chapter studies the regulatory norms that defines
the permissible land use on the existing site.
Chapter 4: Improvement and Relocation – This chapter discusses on the need of
improvement, relocation, rebuilding, additional civic amenities and the possibility of
releasing space based on the assessment of existing land use and the conceptual master
plan.
Chapter 5: Land Plan Schedule – This chapter discusses the ownership of land within the
Site based on the land due diligence and also provides the land plan schedule for
requirement of additional land.
3
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
4
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Block No. TYPE OF BUILDING NO. OF BUA (Sq.M.) Current Status Boundary wall
(Survey FLOORS
Drawing)
1 MAIN STATION BUILDING G+2 2558.021 GOOD CONDITION None Load bearing
2 office of inspector railway protection force G 348.259 GOOD CONDITION None Load bearing
3 Loha maarge police station G 290.3556 GOOD CONDITION None Load bearing
4 execotive test house G+1 422.8521 GOOD CONDITION None Load bearing
5
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
6
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
2.3.1 Zone-1
Item Description
Overview This area is on the West of site and consists of North side Station building,
offices, ancillary structures, sub stations,
Station Building Entrance through north side of station.
Total Zone 1 Area ~ 29,503 Sq.m
Ground Coverage Ground Coverage ~ 10%
Built up area of existing buildings (including service structures) ~ 2982
Sqm
Access Road Main Access to this zone is via Railway Station Road.
Open/ Green Area RPF SPORTS GROUND is the main green patch
Open space is allotted to parking in this zone.
Trees There are 7 full grown trees in this zone.
Table 3: Detail Components of Zone-1
7
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
2.3.2 Zone-2
Item Description
Overview This area is on the Eastern side of site and consists of offices, utilities and
ancillary structures.
Total Zone 2 Area ~ 34,358 Sqm
Ground Ground Coverage ~ 16%
Coverage Built up of existing buildings (including service structures) ~ 5563 Sqm
Access Road It is connected via internal station road.
Main Access to this zone is station front road.
Open/ Green There are no open spaces/greens allotted in this zone
Area
Trees This area has only 1 full grown tree.
8
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
2.3.3 Zone-3
Item Description
Overview This area is on the South western side and consists of residential quarters,
reservation office and main station building
Abuts main access road of the station
Total Zone 3 Area ~ 28593 Sqm
Ground Coverage ~ 21 %
Built up of existing buildings ~ 6207 Sqm
Access Road Main Access to this zone is via Main Station Road.
Open/Green Two parking areas are yhe only open space
Area
Trees This area is covered with green covers and bushes and trees .
There are10 full grown trees in this zone.
Table 5: Detail Components of Zone-3
2.3.4 Zone-4
Item Description
Overview This zone lies in the Eastern land of the Railway estate.
This area consists mainly of Railway quarters, one Hospital, some SSE
offices and ancillary structures.
Total Zone 4 Area ~ 45,798 Sqm
Ground Coverage Ground Coverage ~ 13 %
Built up of existing buildings ~ 6273 Sqm
Access Road Main Access to this zone is via Station Road.
Open/ Green Area One small parking for Hospital
9
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Most of the area in the zone is covered with bushes, small trees and big
trees.
Trees There are 8 small and medium grown trees in this zone.
Table 6: Detail Component of Zone-4
10
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
CHAPTER 3- PERMISSIBLE
LANDUSE
11
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
12
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Figure 9 Land use around Nanded Railway Station Source: Nanded Development Plan 2031
The site is surrounded by residential, mixed use and commercial land. Highlighted Circle
demarcates 1 Km influence zone around the station which has majorly Residential area,
commercial area, industrial area, and mixed use area.Nanded Bus stand is next to railway
station which is 0.8 kms.
13
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
14
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
Accordingly, all the utilities present in the identified land parcels like power grid, DG shed,
parking etc has to be relocated within the site.
For betterment of vehicular circulation around the station, realignment and widening of
roads are proposed along-with station redevelopment. Vehicular movement is proposed to
be unidirectional to ease the Entries and Exits in the railway estate.Provisions for heightened
parking load will also require additional land.
15
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
16
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
17
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
BUILDING
18
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
19
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
5.1 Ownership Records within the Project Site Boundary (Refer Annexure 2)
20
LAND REDEVELOPMENT REPORT
Part-3 of KD2 REPORT For Redevelopment of Nanded Railway Station
ANNEXURES
21
Anne
xur
e1
Annexure - 2
Annexure - 3