SATIP-W-014-01 Rev. 4
SATIP-W-014-01 Rev. 4
SATIP-W-014-01 Rev. 4
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
Recv Insp & Verification of Welding Use SATR-W-2020 SA shall verify and inspect first
2.1 Consumables-(Properties, Type, SAIC-W-2064 SAIC-W-2064 H W batch of delivered consumables, then random
Approved source, storage, etc.) inspection thereafter.
Receiving Inspection and Verification of
2.2 SAIC-W-2034 SAIC-W-2034 H W
Cladding materials
Verify Welding Equipment Calibration
2.3 SAIC-W-2065 SAIC-W-2065 H W Use SATR-W-2009 & SATR-W-2011
(Welding Machines, Electrode Ovens)
Positive Material Identification of Low Use SATR-A-2012 & SATR-A-2013 Refer to Note 1,
2.4 Alloy, Stainless Steel, Nickel & Copper SAIC-L-2010 SAIC-L-2010 H W General Notes for SA Inspection responsibility, after
Based Materials (If Required) which pre-arranged witness shall be agreed upon.
Page 1 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 4 COS 03/31/2010
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welding of Overlays & Cladding Restoration
SATIP-W-014-01 31-Aug-11 MECHANICAL
(Supplement of SAES-W-010 and SATIP-W-010-01)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
1.0
3.0 DOCUMENT REVIEW
INSTALLATION
Refer to SATIP-W-010-01 or SATIP-W-011-01
3.1 Welding Base Metal (vessel or piping)
whichever is applicable.
Control of Welding Consumables- Use SATR-W-2009 & SATR-W-2010 Use New Forms
3.2 SAIC-W-2066 SAIC-W-2066 H S
Storage, Handling, Issue, Conditioning (GTAW Consumable Controls)
Post Weld Heat Treatment Inspection (If Use SATR-W-2005, Refer to Note 1 of the General
3.10 SAIC-W-2004 SAIC-W-2004 H W/R
Required) Notes
4.0 PRE-COMMISSIONING
Final Inspection & review of Welding Use SATR-W-2017 & SATR-W-2008 Review &
4.1 SAIC-W-2028 SAIC-W-2028 H R
Summary Report / Record Approve All associated tests
Page 2 of 3
SAUDI ARAMCO ID/PID FORM REV 1 - 010109 REV 4 COS 03/31/2010
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Welding of Overlays & Cladding Restoration
SATIP-W-014-01 31-Aug-11 MECHANICAL
(Supplement of SAES-W-010 and SATIP-W-010-01)
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection
Page 3 of 3