TUNNLES PROJECT EET-ELECTRICAL EXPRESS TRAIN STATION -RAS EL-HEKMA CONSULTANT SYSTRA CONTRACTOR KASED KHAIR for General Supplies & Contracting
Prepared by: Quality manager Eng. SAMER AMER
Project manager Eng. SHERIF HASAN
1-scope The scope of this method statement covers the Damp proofing for foundation. 2-Purpose: Purpose of this method is to address the requirement of ECP- 203- 2007, including the inspection, fabrication order to verify compliance to the code and the required project specifications for concrete water proofing. 3- DEFINITION: 3.1 MS: METHOD STATEMENT 3.2 ECP: EGYPTION CODE FOR PRACTICE. 3.3 ITP: INSPECTION AND TEST PLAN. 3.4 QR. QUALITY RECORD. 4-RESPONSIBILITIES: 4.1 project manager: Shall be responsible for the overall implementation. 4.2 Quality manager: shall be coordinates with technical manager for materials suitable time approval and available, commitment to the project time schedule, receive the work from the site engineer by the Q.C engineer to submit it to the consultant, and attending the concrete pours and acceleration the critical areas for the best time schedule. 4.3 The Construction Manager In-Charge Shall Be Responsible for The Work Procedure to ensure the construction is carried out as per project specification. he shall see that work is ready for inspection and prepare inspection request. he shall inform all parties concerned for any kind of inspection or test for time schedule. 4.4 Technical office manager. Technical and engineering documents management, and getting the approval for the all-shop drawings, RFI, RFP, BBS and all approval for all the technical documents. 4.5 The site engineer: he shall be responsible for implementing the required work procedures report any deficiencies to the construction manager, prepare the work for inspection by addressing the quality control remarks, and attending the concrete pours. 4.6 Surveyors: Shall be responsible for all work levels and the coordinates of all the elements as per approved shop drawings and time schedule and the work requirements. 5-References: 5.1 project's specification. 5.2 Approved project's shop drawings. 5.3 ECP 203-2007. 5.4 Approved Materials, Technical Data sheet. 5.5 Project's B.O.Q. 6-Equipment: 6.1 brush or roller and squeegee. 6.2 blower to removing the dust/sand to clean the concrete. 6.3 hammer to remove any cement spot residues. 6.4Hot air generator or propane torch. 6.5Manpower: 2Technicl worker, 2 helpers. 7-Materials: 7.1 TECHNOBIT PRIMER WB TS3 7.2 SBS Bitumen Membrane (Quartz). 7.3Fresh Clear water. 7.4Screed concrete or Fine Sand Quartz-S/E or Mineral Slate. 8-Procedure: 8.1 Surface Preparation: 8.1.1 The concrete surface must be free from dirt, debris, and scale. 8.1.2 Defective concrete spots and honey comps must be repair by approved material prior to commencement of water proofing works. 8.1.3 the surface must be saturated with water. 8.1.4 IR to be raised to consultant engineer for preparations inspection. 8.2 Application of Priming coat (TECHNOBIT PRIMER WB TS3): 8.2.1 The coat applied as per manufacture recommendations (T.D.S) and as per consultant engineer instructions. 8.2.2The priming coat can be diluted up to 1:1 in fresh clear water 8.2.3Allow 2 to 4 hours for drying before applying the membrane. 8.3 Application of membranes: 8.3.1After 2-4 hours 8.3.2By using a propane torch or a hot air generator by mechanical fastening or by special adhesives in cold or hot applications. 8.3.3Quartz HD25 can be applied to the substrate fully bonded, semi bonded or loose laid and the method of adhesion to the substrate shall be decided according to the waterproofing system design. 8.3.4Side laps should be from 8-10 cm, while end laps should be from 12-15 cm. 8.3.5Storage& Handling: Quartz HD25 rolls should be kept in an upright position in flat, properly ventilated and sheltered storage area. 8.3.6Laying the screed concrete as protective layer. 8.3.7 IR to be raised to consultant engineer for first coat inspection. 9-SAFETY: 9.1 Ensure safe working environment. 9.2 Safety instructions to be given by the HSE supervisor. 9.3 Hardhats, safety shoes, long pants, visibility vests, long sleeve shirts to be worn. 9.4 Ensure trained workmen use masks and gloves 9.5 Ensure that any skin splashes from any materials to be removed with hand cleaner, soap and water. 9.6 All employees shall be informed as to the necessity for protective clothing particularly when carrying potentially dangerous operations (i.e., welding). 9.7 Materials shall be stored so as not to be considered a hazard i.e. 9.8 Cranes, hoists and other plant items shall be well maintained and operators trained in their use. No personnel will be permitted to ride on loads or use the equipment in a manner which could be constructed as dangerous (i.e., passengers). 9.9 Scaffolding shall have all adequate working boards Scaffolding shall be will not be permitted to ride on vehicles on bumpers inspected regularly to assess its safe state. 9.91 Scaffolding shall be wide enough to allow employees to walk safely and shall be provided with handrails fixed properly to the scaffolding.
9.92 Ladders shall be secure at a permitted inclination.
4 meters without platforms. 9.93 Ladders shall be provided where stairs are not available. 9.94 Emergency exit paths shall be maintained clear of all obstruction. INSPECTION AND TEST PLAN Contractor: KASED KHAIR for General Supplies & Contracting Description of work: Dump proofing Date:15/03/2023 NO Work phase Project Test method / type Acceptance criteria Frequency Record Inspection parties (description of specification of inspection (ICL, test /type of inspection inspection/ report) (Internal checking testing) witness or hold point) Contractor SC QC 1 Submittal: 1.1 Approval of ECP 203/ 207- Compliance with Conforms to Prior to Approved R H methods of BOQ project BOQ specifications starting submittal statement activity 1.2 Approval of ECP 203/ 207- Compliance with Conforms to Prior to Approved R H repair materials BOQ project BOQ specifications starting submittal activity 2 Materials: 2.1 Quartz ECP 203/207 Check manufacture T.D. S For deep MSR W W HD25(TECHNO BOQ date cracks bit CO) 2.2 SIKA ECP 203/207 Check manufacture T.D. S For small MSR W W BOQ date and hair cracks 3 Inspection; 3.1 Preparations Approved M.O.S Compliance with Review on honey combs. After curing Inspection W H for R.C & Ecp m.o.s & Ecp 203/ Voids. Concrete surface. finish request 203/2007 2010 Cracks. Concrete pockets 3.2 Dump proofing Approved M.O.S Compliance with Review on the coverage After Inspection W H first coat for R.C & Ecp m.o.s & Ecp 203/ all the area preparations request 203/2007 2010 3.3 Dump proofing Approved M.O.S Compliance with Review on the thickness 2 hours Inspection H H second coat for R.C & Ecp m.o.s & Ecp 203/ after first request 203/2007 2010 coat ✘ Construction ✘ Consultan ✘ Other Abbreviation: Verification Codes manager t s C- Contractor I- Inspection W- Witness Point RA- Regulatory C-Internal Checking H- Hold Point Authority point T- Test R- Review