HSE Corrective and Preventative Measure Handling Sheet

Department CONSORTIUM HSE DEPARTMENT


Form No. Nº1
Nonconformance:□Occurred□PotentialType:□Serious□General
Non Conformance Description
The COMPANY STAM is doing maintenance without any kind of control. There are chemical product
and oil placed without retention trays; the containers are open without roof. There are leakages of oil
over the ground. All the area is contaminated. They have to follow all the environmental procedures
and mitigation measures

Issuer:Date: 12/09/16
Cause analysis:
Lack of supervision
Lack of information (check if they have receive the CESMP and procedures, act of adherence)
Lack of training
Responsible Department Manager Signature: MATIAS BAÑOS(HSE CONSORTIUM CONSULTANT)
Date12/09/16
Measure:□Corrective Measure □Preventative Measure

ALL CHEMICAL PRODUCTS HAVE TO BE IDENTIFY AND BE OVER A RETENTION TRAY.


ALL HYDROCARBONS (OIL ANG GASOIL) HAVE TO BE IDENTIFY, BE SET IN CLOSE
CONTAINERS, WITH A RETENTION TRAY AND UNDER A ROOF.
THE AREA OF THE OIL HAS A CONCRETE WALL BUT IT IS OPEN, SO THE LEAKS WILL GO OUT
OF THERE. CLOSE IT OR CREATE A STEP.
ALL MATERIAL SAFETY DATA SHEET HAS TO BE AVAILABLE FOR WORKERS AND ALL THE
REQUIREMENTS HAS TO BE FOLLOWED
STAM HAS TO DO A TRAINING ABOUT HOW TO HANDLING HAZARDOUS MATERIAL (SEND
THE ATTENDANCE SHEET)
ALL THE CONTAMINATED SOIL HAS TO BE REMOVED FROM GROUND, STORAGE AS
HAZARDOUS WASTE AND BE GIVEN TO A HAZARDOUS WASTE COMPANY
THE MAINTENANCE IS FORBIDEN BUT IN PROPER AREAS, STAM HASN’T GOT ANY PROPER
AREA

Responsible Department Manager Signature: Close-out date:


Approved by: Date:
Completed situation:

Responsible Department Manager Signature: Date:


Verified results: Measure is effective □Measure is invalid,□Implement and verify again

Verifier: Date:
Remarks:
After _______ (department or subcontractor) receives this sheet, please organize with the relevant
department to analyze the reason, submit feedback within ____ days, and implement it after
approval by HSE Department. And check and verify the implementation and results.