Risk Assessment for Solar Lighting System
Department Document Ref. No. Issue Date Revision
H&S HSE DOCS-RA-LFI-00 7-Jan-2024 00
Prepared &
Functional Area/SOW: Qiddiya Site Offices Lower Plateau R S Nassir H&S Manager
reviewed by:
Risk Rating
Very Low Low Medium High Very High
1-4 5 -9 10 - 15 16 - 20 20 - 25
Risk Rating = Severity (S) x Likelihood (L)
The risk assessment matrix below (TABLE 1) should be used to calculate the risk level (Likelihood x Severity). Consideration may also be given to
property damage or business risk; this can be added to the severity section as appropriate. Once the risk has been calculated the priority for action
can be set from TABLE 2.
Likelihood = L TABLE 2:
Risk Action
TABLE 1: Very May Unlikely Score
Certain (5) Likely (3) Rating
Likely (4) happen (2) (1)