Professional Documents
Culture Documents
INTERN PROJJJ Finall (Repairedddk)
INTERN PROJJJ Finall (Repairedddk)
INTERN PROJJJ Finall (Repairedddk)
INTERNSHIP REPORT
HOSTING CAMPANY: SEID AHMED NUR CONSTRUCTION (SANCON)
NAME ID No
1. KALEAB TESFAYE…………………………………..0421/18
2. DANIEL DESSU……………………………………....2003/18
3. ALI WORKU…………………………………….….…2894/18
4. WORKNEH DEMISE...………………………….……0967/16
MARCH, 11/3/2023G.C
DILLA, ETHIOPIA
DECELARATION
We, the students of Dilla University, declare that this report describes our four months stay in
Seid Ahmed Nur Construction and our working task within the company. We have done site and
office works by direct supervision of Mr. Wegayehu Mulugeta and Engineer Hawa Seman the
instructor at those areas of works and all source materials and pictures used while compiling this
report duly acknowledge. The contents in this report are not submitted to any other educational
institutions.
I approve the students that worked with in our organization for the four months and they done all
the tasks given by the company supervisor.
Signature: __________________
I approved the students that the main internship report contains the monthly internship report,
and the main internship reports.
Signature: __________________
ACKNOWLEDGMENT
First of all we would like to thank our Almighty God for giving us patience and strength from
beginning up to this Internship report and we would like to thank Dilla University Institute of
Technology specially CoTM department for facilitating and organizing such experiences. And
we also thankful for our Advisor AZEB.L and Inst. SAMUEL.G as coordinator, mentoring and
site coming, visiting and encouraging us. We would also like to thank Seid Ahmed Nur Con-
struction (SANCON) for accepting our request and assign us in a supervisor to whom our deep-
est gratitude is for sharing his experience, enlighten us the practical knowledge. Not forgetting
the staff members of the project for their help and corporation they have given us. At last we
would like to thank the site Supervisor Mr. WEGAYEHU MULUGETA and Engineer HAWA
SEMAN for giving all the time they had to help us with any problems we needed guidance with
and not being tired and always being so cooperative with anything we asked and also for being
encouraging. At last, we would like to say thanks our families, and all person who involved in
our academic success.
EXECUTIVE SUMMARY
It is a clear fact the knowledge of construction engineering cannot be upgraded without practical
experience in each field of the subject matter. This internship report paper represents our almost
three-months experience in Seid Ahmed Nur Construction Company, on B1 + G+12 Mixed Use
Building for a specific location Around Red cross in Adama City starting from its background as
it established in 1984 in Ethiopia context ,and its products mainly. For the last around three
months joining the company the report describe that we participate as working site engineer on
the office work as it’s a core base for overall construction in case of superstructure like column,
beams, lifts, stair, and slabs starting from all their office tasks that support the site physical im-
plementation assisted by the supervisor.
In other dimension we observe site work or building on its physical implementation area like as
listed above in office work in form of how they made, their bar arrangement, concrete casting
and equipment for the construction by asking question visualize the activity and capturing a pho-
to. In such a way the report is prepared by focusing up on the knowledge and skills that collected
from the internship visualization and practice mainly like; theoretical knowledge, interpersonal
communication skills, Team playing skills, leadership skills, and work ethics related issues gen-
erally more off management and real life experience. Again the report list out a conclusion for
all internship activities and give recommendation for the hosting company also for the university
as the company should follow the construction checklist and more off professional supervision
based works and for the sending university it will better to do more attention for about the practi-
cal based evaluation.
TABLE OF CONTENTS
DECELARATION ..................................................................................................................................................... I
ACKNOWLEDGMENT .......................................................................................................................................... II
EXECUTIVE SUMMARY ..................................................................................................................................... III
TABLE OF CONTENTS ....................................................................................................................................... IV
LIST OF FIGURE ................................................................................................................................................... VI
LIST OF TABLE .................................................................................................................................................... VII
LIST OF ACRONYMS .......................................................................................................................................... IX
CHAPTER ONE .........................................................................................................................................................1
INTRODUCTION ......................................................................................................................................................1
1. OVERVIEW OF THE COMPANY (HISTORY OF HOSTING COMPANY) ...........................................1
1.1 Background Of The Company ........................................................................................................... 1
1.2 Brief History Of The Company ......................................................................................................... 1
1.3 Vision Of The Company……………………………………………………………………...….....2
1.4 Mission Of TheCompany……………………………………………………………………………2
1.5 Goal Of The Company………………………………………………………………………………2
1.6 Main Products And Services Of The Company………………………..…………………….……..2
1.7 End Users Of The Company’s Products………………….………………………………….……..3
1.8 Overall Organizational Structure And Work Flow …………………………………………….…...4
CHAPTER FOUR……………………………………………………………………………………………..……36
4. CONCLUSION AND RECOMMENDATION ............................................................................................... 36
4.1 Conclusion…………………………………………………………………….……………...…….36
4.2 Recommendation For Hosting Company……………………………………………………….......37
4.2.1 Recommendation For University .............................................................................................. 37
REFERENCE ............................................................................................................................................................ 38
APPENDICE ............................................................................................................................................................. 39
LIST OF FIGURE
LIST OF TABLE
Table 1.1 Product / Service Delivered By Seid Ahmed Nur Construction .............................................3
Table 2.1 Mixing Ratio ........................................................................................................................................ 22
LIST OF ACRONYMS
SANCON Seid Ahmed Nur Construction
PLC Private Limited Company
B+G+”X” Basement Plus Ground Plus”X” Building
BOQ Bill of Quantity
DBB Design bid build
EBCS Ethiopian Building Code of Standard
GC General Contractor
MS Microsoft
& And
CHAPTER ONE
INTRODUCTION
Seid Ahmed Nur Construction PLC was established in 1984 to fulfill the construction needs of
the owner of the company. The company has got its title after the name of the owner Seid Ah-
med Nur. At that moment, the company could have built different buildings that belong to the
owner Ato Seid Ahmed Nur the owner of the company, has started to construct buildings and
civil works for himself with an Italian engineer named Fikadu Bantuma. The dedication of the
company’s founder and staffs, aided by the conductive economic and political environment cre-
ated has helped to facilitate to keep a steady growth of the company within a short period of time
and continues to do so. Now they are constructed B1+G+ 12 mixed uses building in Adama.
Figure1.1 Heading
1.2 Brief History of the Company
At the beginning, company-built Palace Hotel, in Adama city (Kebele09). After that, the com-
pany continued to build four projects like “Nur Gebeya” (Keble19), “Wulesh Gibi” in (kebele20)
and others since 1986 E.C. Thus, the company had stayed on constructing its own projects for
more than 9 years. During this time, the contractor had increased its capital in a great rate. Start-
ing from 1994E.C, for about seven years, the company had passed a remarkable time to support
governmental institution and it come an experienced company’s within decades.
Seid Ahmed Nur general contractor company has been contracting different construction in var-
ious parts of the country and a lot of products and services those are important to the country. Its
core values are quality service, customer satisfaction, transparence and accountability, teamwork,
learning and continuous improvement, and social responsibility. Seid Ahmed Nur construction is
a privet contractors company committed to high & excelling quality of construction work.
Take an active part in the nation’s real estate development thus ensuring maximum
customer satisfaction.
Multipurpose buildings,
Institutional buildings,
Apartments,
Commercial building,
Hotels and
Offices.
Multipurpose
2. Nur gebeya Kebele19 commercial
building
Multipurpose hall
4. Hall building MebratHayl
building
CHAPTER TWO
In our site there are various profession/position which undertaken their role and responsibility to
perform the work smoothly and to meet the project goals and objectives and interest of the own-
er. The professional or different stake holder performs in various project positions. These posi-
Project manager: Plans, arranges and leads the site and office engineer team activities.
Site engineer: Site engineer in construction has a responsibility to make sure that the work is
implemented based on the design and based on specifications used by the company. Control all
the construction activities on the site starting from the very beginning. In construction sites, de-
pending on the schedule given by the project manager, the site engineer;
Check the excavation and earth works according to specification and drawings,
Check the construction of all structural and finishing works,
Make all necessary reports to the Project Engineer.
Office Engineer: Collect data on the site from data collector or surveyor and compile these
data and make report to the Project manager and make detail drawings to be easy.
Foreman: Acts as an agent’s right hand man for the execution of the work in the field, his duty
being to keep the work moving ahead daily as the agent has planned it.
Cabo: - Cabo controls the distribution of labors throughout the site. He also controls the number
of labors at each work place, transfer of labors from one place to another as labor general con-
troller.
Administrator: Administer the workers (employees), takes care of the employment of new
workers and checks the working performance and punctuality of the workers with the time
keeper.
Finance: Takes care of monthly salary (fee) of the employees, finance the purchasing of
requested materials by receiving a commands and directions of the clients and the project con-
tractor.
Store keepers: Controls the amount and type of material of the construction Entering and
leaving from the store by preparing some forms and sometimes act as a general keeper of sites.
2.3 Project description and Section of the project we have worked in the
Company
Site and
Office works.
Columns are usually considered as vertical structural elements, but they can be positioned in any
orientation (e.g. diagonal and horizontal compression elements in a truss). The loads applied to a
column are only axial loads. In our site there are about 42 columns with size or diameter of
90*40,85*85,80*80,70*70,75*75,65*65,60*60,55*55,50*50,50*40,45*45,40*40,and30*30 with
circular, rectangular, and square shapes. The height of a column can be measured from floor to
bottom part of a beam. Every reinforced concrete (RC) has a process so that a column is one of
reinforced concrete structure and has also a process that should be followed appropriately for ef-
fective end product of a column. The first step is making a base point or a starter to erect the
formwork accurately as per designed size of the column. They called it on site crachary. It has
been done by calculating the size of the column and formwork material. After constructing the
starter or crachary reinforcement of bar will prepared.
Reinforcement of column
Ø8 for stirrups
Ø16,ø20,ø24 For column
Ø20 for beam & Ø14, ø10, ø12 for slabs.
Longitudinal (main) steel bar:-To starter bars are projecting from the column or foundation
below.
Stirrups (Staffa): Serve as shear reinforcement and tied on longitudinal reinforcements to pro-
vide resistance against out ward buckling.
To resist shear.
To restrict the growth of diagonal tension cracks.
To tie longitudinal bars.
To improve ductility.
It’s a small shaped concrete cover with 2.5-5cm thickness which used to provide space between
the steel reinforcement and the form work this space will be filled with concrete. Again it used
for fire resistance steel bar reinforcement and prevents visualization of the bars after removal of
formwork. It’s made of 1:3 ratio proportions of cement and sand mixing with water
Crachery
(Starter)
Formwork
Formwork is temporary support construction designed. It can be constructed from timber or met-
al and should be capable of withstanding the live and dead loads imposed on it during the time of
construction. Also it is an open box into which a freshly mixed concrete poured & compact. It is
used to mold any structural member to the desired shape & support the reinforced concrete until
it achieves its strength. To do a formwork, we measure the structural member dimension then we
will cut the ply wood including the thickness of ply wood. We will attach on the concrete cover
tied on the reinforcement bar after that we will attach using nail.
Formwork
Gaucho
Cravat Stanga
Plumb bob
The curing time may depend on concrete type, the type of the structural element and environ-
ment of the working station. There are two setting times of concrete namely, initial setting time
and final setting time. The former one is setting time from placing of concrete up to dismantling
of the formwork. It is 24 hrs for columns, slabs and beams. The final setting time is the time
from dismantling of formwork to the final setting of concrete. It is 7 days for columns and beams
and 21 days for slabs. In our site curing is by spraying and covering method.
In our working site most circular columns short in height compared to other rectangular means
that casted by plywood formwork, this circular columns casted by panel metal formwork and this
panel is not equal in height with intended height of circular column which is 4m but the panel
heights 3.50 m so, to fill this remain 0.5m height of a column our site or the engineer decide to
Sit the panel on the increased height, and fit properly with the casted column,
Mix concrete by adding chemical construction/bonding agent for good connection with
the precast column.
Both sides of form work called sponda and the bottoms called fondo by site language
and the standing that use to carry beams are cristy (fonte).
There are three main different reinforcements on beam. Which are positive bar, negative bar, and
stirrup (site name as Staffa).
1. Positive bar: these kinds of bars are manly used to resist the positive moments. These mo-
ments developed at the mid span on the beams and these positive bars are placed t the mid span.
2. Negative bar: these are bars used to resist negative moment. Negative bar are provided at one
third of the total length (L/3) because most of the time negative bending acts at that position.
3. Stirrups: they are placed to provide diagonal shear resistance. Therefore, stirrups are provided
to take the shear stress.
- Beam work procedure;
A. Before casting
B. During casting
C. After casting
- Before casting
1. Alignment of reinforcement.
2. Reinforcement diameter, number and overlap length (50 times diameter of the reinforcement)
4. Stirrup spacing.
5. Provision of spacer (type, shape, dimension, spacing, and method of fixing it to maintain the
7. Conformity with the approved formwork design i.e. Dimension, shape, strength, method of
fixing, rigidity, bracing detail and method of removing the formwork.
9. Volume of the required material for the required concrete volume during casting.
- During casting
3. Way of The execution of the work (way of mixing, way of placing, distance the concrete trav-
el).
- After casting
C. SLAB
Slab is the flat member of the structure which form floor and roof which carries uniformly
distributed loads. The type of slab used in our site is solid the whole up to 12th story but we can’t
arrive at the slabs casting even reinforcement but we can observe the overall formwork construc-
tion.
- It is sound insulator.
- Have higher strength.
Disadvantage of the solid slab:-
D. Shear wall
Shear wall is a structural member in a reinforced concrete framed structure to resist vibration
load which comes from lift, stair and lateral forces such as wind forces and Shear wall is im-
portant for constructing bridge which connects one block with another i.e. block A with block B.
shear wall has its own footing, transferring its load directly to the ground and it is like another
structural member subjected to both flexure and shear.
The procedures used in site to construct shear wall:-
1. First the masons construct internal formwork.
2. The re-bars are placed properly and are tied together.
3. After they finish tying the bars, the carpenters start to construct external formworks and scaf-
foldings.
4. The mixer operator starts to mix the concrete.
5. Then the concrete mix is poured in to the formwork.
6. They vibrate the mix in order to blow out the air bubbles.
7. The form work will be removed after the concrete curing for 16 hour.
Stairs are set of steps leading from one floor to another or it’s a mode of vertical transportation in
the building. Steps arranged in series and placed in an enclosure are called Staircase. In our site
there are 2 lifts and stares with dog leg shapes structured. There are few calculations in order to
get height of riser, length of flight and total tread length that is more about its construction. In
order to get height from GF up to landing we divide the length from GF up to FF to two. The
first thing in stair construction is dividing the floor height in to two, then by using string we get
Lifts are like stair its mode of vertical transportation from one to other story that assisted by elec-
tric. In our site like stairs there are two lifts with thickness of 20 and 25cm with 4m height that
attached to stair as alternative way.
Casting of concrete: - Casting involves placing and compacting concrete in its final position to
have the desired shape and thickness.
Lift shaft
Lift house
In concrete cement is used to bind sand and aggregates and the binding properties of cement is
affected by type of cement used and the amount of water added.
Sand is used as a fill between aggregates and this avoids presence of voids between aggregate
materials. Also the presence of sand in concrete mix with a certain ratio is needed to reduce the
quantity of cement to be used. But excess sand will also result in consumption of much cement.
Concrete batching
In our site concrete material proportion or measuring is performed by loader with known and
well designed which is indicated in figure; in the bucket of loader there are 3 bar welded along
longitudinal direction which are full, half and quarter in three lines. In such way batching is car-
ried out with various mix ratios and in most mix even in our site the gauge box used is 50*40*16
for concrete grade C30 and ratio of 1:2:3 the full loader contain 22 box of coarse and fine aggre-
gate, at half line 11 and 52 bags of cement with 7 min water inserting. Full truck mixer can able
to mix concrete about 7m3 at once if there is no longer transportation rate.
The concrete mix shall be designed to have the minimum cement content and the grading be-
tween the limits shown for course and fine aggregate shall be such as to produce a workable and
dense concrete with appropriate water-cement ratio.
Mixing of concrete
In our site the company has its own batching site which is located at Unity University. The con-
crete shall be mixed in an efficient automatic mechanical mixer of an approved type and of suffi-
cient capacity. The mixing operation shall continue until the cement is thoroughly distributed
throughout the mass and shall last at least 2 minutes or forty turns of the drum after the whole of
the water has been added total water about 7min.
Additives to Concrete
In our site there are owned Batching site at Unity University and are transported to Red Cross. If
there is long distance of traffic jam between the batching plant and the construction site, special
admixtures (retarders) should be used up on approval by the engineer.
Transportation of concrete
Concrete is to be transferred from the place of mixing to the place of final deposit as rapidly as
possible to avoid re-handling and flowing of segregation.
Placing of concrete
Concrete shall be placed before setting has commenced and in any case within 30 minutes from
the time that the water is added in the mixer. Concrete shall not be discharged during placing
from a height in excess of 2.5m according to EBCS.
Supervision
Before Casting
the vertical and the horizontal alignment should be checked (with ligna and Tumby)
spacing between bar should be checked
reinforcement diameter overlap length 50 times diameter (50D )of the reinforcement
should be checked
stirrup spacing should be checked
During Casting
proper curing
check if there is segregation
Slump test
From the above common tests of concrete we investigate the cube compressive strength of a
concrete test. Before starting any concrete works of the project physical and chemical tests will
be carried out on sand and aggregate to be used for the works at a laboratory. The test results will
be submitted to the Engineer for approval.
Compressive strength test
The compressive strength of the concrete is continuously tested whenever a concrete mix is made
for the structure. Eight test cubes of each (15cm*15cm*15cm) are taken for each test. Out of the
six cubes, three will be tested for 7 days’ strength which should be greater than 70% of the
compressive strength of the 28th day strength, and the rest will be tested for the 28days
compressive strength which should fulfill the required strength and at the end the concrete should
be load resistant that applied on it.
- Finally we will deduct the advance payment plus previous payment including their 15% VAT
& retention from the executed amount then we will prepare the net service payment & certify
the payment by the concerned people through their signature.
- The format to perform this payment for execution of the project seems like this,
|||||||||||||||||||||
Task dependence is use to establish relationship b/n tasks, which reflect how successor task de-
pend on the predecessor. There are four types of task dependence.
In addition to the four types of dependence there are some concepts to adjust the dependence,
which is called lag & lead. Lag means addition of day or delay b/n two tasks that share depend-
ency & we will use a positive sign. Lead means overlapping works on its predecessor.
As an internship Student we performed different works during our apparent time on the project
we have tried to do on thus basic topics particular.
- Checking bars that are installed in structure like ground floor lift, stair, and Column
by referring the drawing plan and their overlaps,
- Checking the placement and position of bars at different task,
- Work on concrete work from its batching and transporting the ready concrete in to
the casting area,
- More about office tasks preparing and observe like take off, BOQ, bar schedule and
ms-task scheduling, and oiling the formwork for easy removal after casted concrete
dried and checks the spacer in any task that has reinforcement in it and need form-
works.
During our internship time it was good means we can gather many knowledge that we want to
know in practice aspects. We attend on the job training in a good way and actively take im-
portant notes and photos and more of asking from all professions about the work being done
moreover; we ask the site engineer, and the foreman and the workers if there is anything we can’t
understand. Furthermore, we work each task ordered by the supervisor diligently and interesting-
ly so that we can improve our practical and theoretical skills at large. Also, we see the time in
good perspectives which help us to know basic machineries in construction.
The company have so many owned machineris starting from small to huge, from those we can
able to observe the following , when they ar at working.
Crane truck: Are vehicles with a machine designed to help them lift, lower or move heavy ob-
jects.
There are many challenges we faced during our internship in the past four months. From those:
The main challenge that we have faced during the internship time is to understand the
site language and terminologies applied by different work groups, as we are new for site
works,
Lack of safety wears i.e. safety shoe, helmets and other personal protection equipments,
Site clearing from unwanted nail inside wood and it’s not safe for leg at the end flexi-
ble work flow,
The ladder that made in the site is not sloppy or its 900 to the ground, and it’s not safe
and comfortable for us even for worker,
Improper bar handling , it close all the working site and it’s not easy to move in the site
We can’t get office work easily at the first time because of engineer perform at d/t sites.
Asking and try to search about new words from daily labors, engineer that are work in the
company.
Try to keep our safety as much as possible starting from wearing proper working shoes ,
keep other measures like don’t walking along unsuitable and crowd areas.
As, engineer we try to recommend or by saying it’s better to do on that proper and check-
list based ladder standing, and other things.
By recommend , as the bar for working will corrode and minimize its overall perfor-
mance if it take with improper handling and keep it at the same place, even it need shade
and wooden made bed like structure.
In case of office work, contact with engineer with is free time with his permission.
CHAPTER THREE
During our internship experience, we have been able to gain a lot of practical knowledge .such
as;
Since the practice depends first on theory, it was easy to correspond with each other. It is not
very challenging to change the theory into practice. Theoretical knowledge is dependable on
principles, logic and calculations. In somehow in the site it’s more about practical in both site
and office work but we can obtain theoretical knowledge like; able to know our strength weak-
ness, in different dimensions and correct and improve our theory based knowledge, improving
which type of construction material should be used.
Improve better communication skills on construction site languages with worker since it
gave us an opportunity to work with different persons having different responsibility like
site engineers, office engineers, foreman, and labors.
those are: -
Good speaking ability.
To have the ability to listen to other.
To be decisive.
Good management skills.
Punctuality
Accountability
Respecting each other
Responsibility
In general we improve or gain the two main ethics; personal ethics like honesty and pro-
fessional ethics like accountability, cooperation.
CHAPTER FOUR
4.1 Conclusion
This report, the whole internship mainly presented the practical skills gained such as communi-
cation skills, work ethics skills, and team playing skills, leadership skills and general theoretical
knowledge developed through the program. The major relevant structural work activities of the
project have been discussed, the program is very crucial and important for students to develop
good knowledge and skills needed for their future career. It gives the mental image of their work-
ing environment and greatly motivated how to execute the imposed responsibilities.
This internship program enabled us know what a construction manager should know and do. As
we observe from the task and duties to be done in the company, we can say that the project was
interesting to realize the practical skill with the theoretical aspect that we had learned. Moreover
working on both at site and office work made us learn different things, even though that was new for us.
For the last Four month of our internship experience has been a very useful experience for us;
however the internship was not free from challenges. The most challenge was every office work-
ers were busy so it take effort to get what we want& difficult to saw a tangible construction
work. Generally, as a conclusion we can say the following:
Internship is the best program for us to know what the working principle is.
It helps in what way we solve the problem facing in the site during work.
It also helps us to know the coordinative work between the site engineer and the foreman
and other workers.
Based on the internship program interns will try to grasp what things to know for the
coming time of our class.
As a recommendation the company should prepare its own quality and safety engineer and su-
pervision activities for that to control or based on standard checklist and rules like;
First material handling like fine and coarse aggregate, bars even their working
Fulfillment of personal protective equipment.
Site clearing even during on working means before completion of project to minimize work
crowd.
In case of preparation concrete spacer for aligning on the reinforcement bars, as we observe their
ratio is not quality based .when they attach on bars, during formwork making they simply
crushed or remove from their site, so for this we recommend for the company to do qualified and
right proportion of cement and sands without negligence.
Also we observe harshly segregated column and column, then they demolish the whole one
column, this is because of proper vibration at the filling height of 1.5m.
In case of concrete casting, they fill the lift out of its height means out of slab height, then after
they prepare labors that demolish the over casted lift. For this we recommend to batch a quanti-
fied amount of concrete for lifts to cast at the required height.
We also observe dampness on at the bottom ground slab, this is because of excess amount of cur-
ing of column and again improper compaction of slab that create hole that pass water.
Practical learning should give great attention rather than the theoretical learning before internship
semester by preparing trip that student can practice is selected site and evaluating the student’s
activity in marks.
It’s really better to give a great attention for a Compulsory courses like; MS project, procurement
and contract management, planning and schedule, again courses that aligned with contract doc-
ument.
REFERENCE
APPENDICE
Staffa/ stirrup: used to tie reinforcement bar. And shear resistant bar of column, beam
and shear wall.
Wehalik/sprit level: is an instrument used to check the horizontal level.
Tumby (plumb-bob): is an apparatus used to check the vertical alignment of the column.
Sibago/ligna/mason line/string: is string used to maintain alignments.
Berga: 12m reinforcement bar.
Tape: used to measure distance & height between columns.
Ferayo: is a person who works with reinforcement.
Cravat /yokes/prop: eucalyptus material used to fix the column formwork in their posi-
tion.
Segeto: steel saw, used to cut steel.
Bega: an instrument used to bend bars.
Crachery: wooden piece relay around the column to stand the column formwork.
Gaucho: anchorage of bar.
Stanga: inclined wooden material that used to support column.
Morale: a long rectangular wood that used join column formwork.
Sponda: a vertical side formwork for beam and slab.
Fondo: bottom formwork of beam.
Penci: is panel but is small in size which is used to fill the small opening in formwork.
Fonte: is the standing that uses to carry beams.