Plot No. W-62 B & W-38 B, TTC Industrial Area, Road No.

3
MIDC Rabale, Navi Mumbai, India- 400 701
Tel: +91 22 2760 8501/ 27693111
Fax: +91 22 27608510. E-mail: sales@feipl.com; www.feipl.com

REF: FE/REL/PAINT/FR- /01 DATE:

SURFACE PREPARATION & PAINTING REPORT


CLIENT:.
PROJECT:
DESCRIPTION: SIZE :-
PO.NO :- QTY:
DRAWING NO: TAG NO:

With reference to the above P.O. we here by confirming that EQUIPMENT are Cleaned from outside, inside and remove
scale, rust dirt and other foreign material by abrasive cleaning and Blasting (using copper slag) as per Approved Procedure.

Environment Conditions
COATING WORK ACTIVITY Blasting Primer Intermediate Finish
TIME
DRY BULB TEMP. OC
WET BULB TEMP. OC
RELATIVE HUMIDITY %
DEW POINT OC
SURFACE TEMP. OC
Surface Preparations
METHOD:
ABRASIVE TYPE:
SURFACE PROFILE CHECK:

Painting done on Carbon Steel surfaces as follows:


A. Primer- (DFT found: MICRON).
Manufacturer: Batch No:
B. Tie coat- (DFT Found: MICRON)
Manufacturer: Batch No:
C. Intermediate – (DFT found: MICRON)
Manufacturer: Batch No:
D. Finish- (DFT found: MICRON).
Manufacturer: Batch No:

FINAL TESTING

Visual Inspection:- Free of over Spray, runs, sags, voids, blistering, peeling, rusting, and mud cracking.
DFT Film Thickness: Specified: Actual:
Salt Contamination Test:
Adhesion test:
Color shade: Specified Actual: