Ha0213 D1HPV MFF003 Mec P 00 A 279 J04 001
Ha0213 D1HPV MFF003 Mec P 00 A 279 J04 001
Permission to proceed does not constitute acceptance or approval of Design Detail, Calculations, Analysis, Test Methods or Materials developed OR selected by Vendor,
and does NOT relieve Vendor from FULL compliance with Contractual Obligations
Program No MRP Number Excluding Discipline & Type Unit No(Plant WBS) Cat. No Seq. No. Rev No
H26003 HA0213-D1HPV-MFF003-MEC-P-00-A - 2 7 9 - J 0 4 - 0 0 1 - 0 1
Page 1 of 1
SURFACE PREPARATION & PAINTING PROCEDURE
1.0 PURPOSE
This procedure establishes the minimum requirement for the surface preparation, coating
application for shop fabricated Strainers and Basket Filters and Inspection of painted / coated
surface of the same (Internal & External).
2.0 SCOPE:
This procedure covers the requirement of surface preparation, application of primer,
intermediate and finish painting for carbon steel made Strainer, filter etc.
3.0 REFERENCE
3.1) Approved Drawings.
3.2) Data sheets.
3.3) SSPC-SP10- Near White Blast Cleaning.
3.4) ISO 8501-1 – Visual assessment of surface cleanliness.
3.5) RIL Spec – RPMS-ENGG-SPC-PP-014
4.0 Responsibility:
Production Engineer/Painting Supervisor or his designee shall be responsible for surface
preparation & paint application work of vessels. QC Painting inspector shall monitor and verify
the surface preparation and painting work as per approved procedure.
Painting Inspector shall be certified by NACE \ SSPC, as required by RPMS spec.
7.1) Abrasive material shall meet the requirements of paint manufacturer material datasheet.
7.2) Abrasive material shall be Garnet or Grit or Shots.
7.3) All abrasive material shall be kept dry and covered when not in use.
7.4) Neither sand nor contaminated recycled abrasive shall be used under any circumstances for
blasting.
7.5) Pre cleaning:
a) All surface imperfections such as weld spatters, slags, sharp subjects etc., shall be removed by
wire brushing, cosmetic grinding or filling as applicable prior to blasting.
b) Oil and grease shall be removed by solvent cleaning in accordance with SSPC-SP1 or high
pressure washing or detergent cleaning. The washed surface shall be dry and free from trace
contaminants.
7.6) All external and internal surfaces shall be blasted to specification SA 2 ½ near white metal.
The surface profile shall comply with the requirement of relevant data sheet. Internal surfaces
shall be coated with Antirust coating after completion of blasting.
7.7) Operating pressure for shot blasting will be 100 psi. Shots shall be covered properly and it
shall be free from contamination.
7.8) Laps like surface defects and other surface defects revealed by blast cleaning shall be
dressed and shall be re blasted.
7.9) All blasting equipments shall be fitted with efficient oil and water traps. Dead man handle
shall be fixed as close as practical to the blast nozzle. Blasting equipment, hose and nozzle to be
earthed.
7.10) All surfaces shall be inspected for contamination free test prior to any coating.
7.11) Whole blasting & Painting job shall be supervised and all tests witnessed by NACE \ SSPC
certified personnel, as per RPMS spec.
8.1) All painting materials shall be stored in sealed dry area container under cover in accordance
with safety regulations and as per manufactures recommendations in the painting area. The
paint shall be protected from direct sun light, open flames. If required paint materials shall be
stored in air conditioned room.
8.2) The paint materials shall be in their original sealed containers, with manufacturers labels,
with batch nos, date of manufacturer and date of expiry.
8.3) Stock of paints and thinners shall be related regarding to ensure that only fresh materials are
issued.
The paint materials, first in shall be first out.
Doc. Number Rev.
PAINTING PROCEDURE FEIPL JOB NO.-5235 HA0213-D1HPV-MFF003-
MEC-P-00-A-279-J04-001 01
GENERAL
Sheet 2 of 6
FILTERATION ENGINEERS INDIA PVT. LTD. MUMBAI.
9.0 PAINTING PROCEDURE:
9.1.1) Clean paint nettles shall be used at all times. The use of miscellaneous tins shall not be
permitted.
9.1.2) All remnant abrasives shall be removed from surface by air before priming.
9.1.3) Application of all paints shall be spray technique for all surfaces.
Brush Shall be used only in case of inaccessible areas. The coating material shall be mixed and
applied in accordance with manufacture’s data sheets.
9.1.4) Each coat shall be free from pin holes, blisters detrimental runs, sags inadequate film build
& foreign inclusions.
Painting shall be done as per coating schedule to the required thickness as mentioned in this
procedure.
9.1.5) All painting appliances shall be cleaned simultaneously after use with cleaner
recommended by painting manufacturer.
9.1.6) Painting material shall be procured from reputed manufactures. Data sheets of proposed
paints from the manufactures shall be submitted to the Client for their review.
9.1.7) All bevelled edges ( if any) to be covered with masking tape of 4 inch wide before
application of primer.
9.2 PRIMER
9.2.1) The blasted surfaces shall be cleaned before priming by higher-pressure air. All the
surfaces shall be visually inspected and approved by QC Inspector prior to the primer being
applied.
9.2.2) No abrasive blasting operation shall be carried out to the detriment of painting work in
progress or freshly applied coating which has not dried thoroughly.
9.2.3) Blasted surface shall be coated within four hours to avoid oxidation/flash running. The
primer paint shall be thoroughly stirred to a homogeneous state using mechanical means. Apply
paint up to but not within four inches of joints to be field welded (if any).
9.2.4) Paint that exceeds its pot life shall not be used and shall be discarded. When thinning is
required in order to achieve the correct viscosity of the paint, only thinners recommended by
manufacturer’s shall be used.
9.2.5) At welds and at intricate locations, painting shall be patted on with the side of brush to
ensure that a full coating is obtained.
9.2.6) After drying the inspection has been carried out. Surface texture shall be visually examined
for defects like sagging, runs, missing, over sprays, foreign contamination, air pockets, drips, pin
holes and the DFT shall be measured and recorded.
9.4.1) Check the intermediate coat drying time and recoating interval as per data sheet.
9.4.2) Wet rub the previous coating with fine emery paper and flush with fresh water to remove
all loose dust, flake etc, before applying topcoat.
9.4.3) Apply subsequent coat and topcoat by airless spray to achieve dry film thickness as
specified.
9.4.4) If brushes are to be used the brush shall be of good quality and not more than 100 mm
wide.
9.4.5) After painting the equipment can placed at good environment so that any dust or dirt
particles shall not stick on the top paint coat.
9.4.6) The final colour of the paint coat shall be as per the schedule mentioned in this procedure.
9.4.7) After drying the inspection has been carried out. Surface texture shall be visually examined
for defects like sagging, runs, missing, over sprays, foreign contamination, air pockets, drips, pin
holes and the DFT shall be measured and recorded.
11.1) Inspection and testing shall be conducted as per requirement specified in datasheet,
drawing and technical specification if any.
11.2) All the blasting and painting materials shall meet the requirements of this procedure.
11.3) The inspection and testing equipments such as Surface Profile Gauges, DFT Gauges,
and Instruments to monitor ambient conditions shall be calibrated by external agencies
and the certificates shall be kept ready for inspection.
11.4) Prior to start of blasting/coating, during blasting / coating and upon completion of
blasting/coating the environmental conditions such as ambient temperature, metal surface
temperature and relative humidity (RH) shall be measured at every three hour intervals.
12.0 ACCEPTANCE
Paint Manufacturer as per Annexure B of RPMS spec: International, Asian Paints, Asian PPG or
Kansai Nerolac.
SURFACE PREPARATION:
13.0 ATTACHMENTS
With reference to the above P.O. we here by confirming that EQUIPMENT are Cleaned from outside, inside and remove
scale, rust dirt and other foreign material by abrasive cleaning and Blasting (using copper slag) as per Approved Procedure.
Environment Conditions
COATING WORK ACTIVITY Blasting Primer Intermediate Finish
TIME
DRY BULB TEMP. OC
WET BULB TEMP. OC
RELATIVE HUMIDITY %
DEW POINT OC
SURFACE TEMP. OC
Surface Preparations
METHOD:
ABRASIVE TYPE:
SURFACE PROFILE CHECK:
FINAL TESTING
Visual Inspection:- Free of over Spray, runs, sags, voids, blistering, peeling, rusting, and mud cracking.
DFT Film Thickness: Specified: Actual:
Salt Contamination Test:
Adhesion test:
Color shade: Specified Actual:
(QA/QC)-
CIN No U74899MH1994PTC192156