Empire Hotel Subang TP Ver 1.0
Empire Hotel Subang TP Ver 1.0
A survey was carried out at EMPIRE HOTEL SUBANG by Jenexus Holding Sdn Bhd team on
infra structure sharing under Access Agreement for deployment of our Wireless services.
2. Objective
3. Site Details
Building 57m
1 EMPIRE HOTEL SUBANG 3.08261° 101.58348°
Monopole 1.5m
4. Rooftop Structure
5. Antenna Quantity
6. Cabling
7. Power Supply
Jenexus will apply power from EMPIRE HOTEL SUBANG existing source.
All wiring and civil works will be carried out by Jenexus appointed contractor.
8. Earthing
A separate grounding system will be installed for our antennas and equipment.
Standard Compliance – Power Rated Issue Standard Regulation
Grounding system will be determined during construction. All main grounding
system will be connected to Main Earth Chamber.
9. Site Accessibility
Frequent movement of staff and workers is expected at the initial stage of site
preparations and equipment installation, testing and commissioning.
While at the operational phase, the site may be visited by maintenance staff
periodically. Hence, it is required that the site be accessible 24 hours.
Cables run through horizontal & vertical with cable ladder and conduit pipe support
Feeders will run from rack to the antennas using these cable ladders. Jenexus will bear
the sole responsibility for all construction works and installation.
EQUIPMENT QTY
Radio Antenna 2
Radio POE 2
Astro Pole 2
Cat-6 Outdoor Cable Radio 01: 40m
Radio 02: 70m
Power Extension 1
Radio 01 location wall mount and Cable route Cable route to existing rack.
to existing rack. Green line: Cat6 outdoor cable
Location : Rooftop LVL Location : Rooftop LVL
Radio 02 location wall mount and Cable route Cable route to existing rack.
to existing rack Green line: Cat6 outdoor cable
Prepared by:
Syahid - 0126891952
Approved by: