Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

Skender-Blackwood Joint Venture Project: 22-03-30 Albany Terrace - JV

1330 W. Fulton St 3030 W. 21st Place


Chicago, Illinois 60607 Chicago, Illinois 60623
P: (312) 781-0265

RFI #128: Penthouse Elevator A/C Feeds


Status Open

To Irma Ayala (Canopy-Chicago) From Preston Collins (Skender Construction LLC)


Ismael Vela (Canopy-Chicago) 1330 W. Fulton St.
Temitayo Odunlami (Canopy-Chicago) Chicago, Illinois 60607
Armando Tobias (Canopy-Chicago)

Date Initiated Oct 30, 2023 Due Date Nov 6, 2023

Location Project Stage Construction

Cost Impact Schedule Impact

Drawing Number

Linked Drawings

Received From Ryan Dostal (Jolen Electric/Communications) Sub Job

Copies To Frank Alfano (Skender Construction LLC), Preston Collins (Skender Construction LLC), Jake Dohm (Michaels Development),
Kaustubh Kridutta (Skender Construction LLC), Christina Martinez-Sahagun (Chicago Housing Authority), Brian O'Neal (Chicago
Housing Authority), Joe Pecoraro (Skender Construction LLC), David Ruzich (Skender Construction LLC), Justin Skender
(Skender Construction LLC), Edmund Steele (Chicago Housing Authority), Jacob Wilhoit (Michaels Development)

Priority

Activity

Question Question from Preston Collins Skender Construction LLC on Monday, Oct 30, 2023 at 08:25 AM CDT
In the elevator machine room there are 2 - A/C Split Units that cool the elevator machine room. These units were installed
during the elevator modernization project and currently are fed from the Penthouse panel that is scheduled to be demoed.

These units will need to be re-fed, but they are not accounted for in new panel schedule.

Is it acceptable to feed these 2 units that will require (2) 2 pole 30amp breakers to be installed in panel PHELP1. See
attached for A/C name plate.

Attachments
IMG_E1439.JPG

Official Response Response from Irma Ayala Canopy-Chicago on Wednesday, Nov 15, 2023 at 12:01 PM CST
Refer to the attached file for submittal AT RFI 128_Penthouse Elevator AC Feeds_11.15.23
response
Irma Ayala/ Canopy A+D
Attachments
AT RFI 128_Penthouse Elevator AC Feeds_11.15.23 response.pdf

All Replies Response from Kaustubh Kridutta Skender Construction LLC on Thursday, Dec 14, 2023 at 03:21 PM CST
The UH-09 has a 27.1 MBH capacity, roughly 8 KW. Per the updated PHELP1 panel schedule, the amperage and voltage
won't be enough to get the required capacity of 8 KW. See the attached schedule and select the heater that will work with the
new panel. These heaters are available with minimum lead time.

FYI, the transformer has been released.

Attachments
Electric Heater Schedule.pdf

Skender-Blackwood Joint Venture Page 1 of 2 Printed On: Dec 14, 2023 03:21 PM CST
RFI #128 - Penthouse Elevator A/C Feeds Project: 22-03-30 Albany Terrace - JV

Response from Irma Ayala Canopy-Chicago on Wednesday, Nov 15, 2023 at 12:01 PM CST
Refer to the attached file for submittal AT RFI 128_Penthouse Elevator AC Feeds_11.15.23
response
Irma Ayala/ Canopy A+D
Attachments
AT RFI 128_Penthouse Elevator AC Feeds_11.15.23 response.pdf

Response from Kaustubh Kridutta Skender Construction LLC on Wednesday, Nov 1, 2023 at 08:07 AM CDT
Since we are changing the panel board and transformer to accommodate the split A/Cs, can we also accommodate the
change of the UH-09 gas heater to an electric heater per the RFI #121 (see attached) so that we don't have to build a soffit
and make changes on the 17th floor?

Attachments
AT_RFI 121_UH-09 Pipe Routing Issue_response 10.17.23 (1).pdf

Response from Ismael Vela Canopy-Chicago on Tuesday, Oct 31, 2023 at 02:49 PM CDT
Refer to the attached file for AT RFI 128_Penthouse Elevator AC Feeds response
Ismael Vela/ Canopy A+D

Attachments
AT RFI 128_Penthouse Elevator AC Feeds_response.pdf

TES response:

In the penthouse P-01, in place of the specified UH-09 gas unit heater, use
a 7.5KW, 208V, 3 phase electric unit heater similar to model MUH-07-8 in
the attached selection chart. Provide a 30A/3P CB in panelboard PHELP1
and 3#10, 1#10G, 3/4"C to serve the new electric unit heater via a 30A/3P
non-fused disconnect switch.

Regarding the existing heat pump split systems serving the elevator
machine room, the Contractor shall confirm that the requested 30A/2P CB
will be adequate ampacity to serve each existing system, noting that this
existing equipment nameplate indicates 35A MOCP.

Canopy remarks | 01.03.24:

1. Comply with the engineers response.

Skender-Blackwood Joint Venture Page 2 of 2 Printed On: Dec 14, 2023 03:21 PM CST
32'-0" 0'-0" 16'-0" 32'-0" 64'-0" 16'-0" 0'-0" 8'-0" 16'-0" 64'-0" 8'-0" 0'-0" 4'-0" 8'-0" 16'-0" 4'-0" 0'-0" 2'-0" 4'-0" 8'-0" 2'-0" 0'-0" 1'-0" 2'-0" 4'-0" 1'-0" 0'-0" 0'-6" 1'-0" 2'-0" 0'-0" 0'-6" 1'-0" 2'-0" 0'-0" 0'-3" 0'-6" 0'-9" 1'-0"

1/32" = 1'-0" 1/16" = 1'-0" 1/8" = 1'-0" 1/4" = 1'-0" 1/2" = 1'-0" 1" = 1'-0" 1-1/2" = 1'-0" 3" = 1'-0"

KEYED NOTES - FLOOR PLANS

01 NEW SBS ROOFING SYSTEM: SBS MODIFIED


BITUMEN ROOFING CAP PLY, WITH BASEPLY, COVER
BOARD, INSULATION (MIN. R-30 OR MAX ALLOWED
PER EXISTING EDGE CONDITION) TAPERED TO DRAIN,
AND VAPOR RETARDER OVER SUBSTRATE.
02 METAL ROOF SYSTEM: STANDING SEAM METAL ROOF
1 2 3 4 5 6 7 8 9 PANELS, (2) LAYERS OF BUILDING FELT, RIGID
INSULATION (MIN R-30), VAPOR BARRIER, ROOF DECK
03 NOT USED

1 / A1.18
21'-0" 21'-0" 21'-0" 21'-0" 21'-0" 21'-0" 21'-0" 21'-0" 04 NEW PERMANENT SAFETY ANCHOR POINTS
FASTENED TO EXISTING CONCRETE ROOF
STRUCTURE – 2 PER BAY. REFER TO STRUCTURAL.
05 NEW SLAB ON GRADE WITH FOUNDATION WALL -
REFER TO STRUCTURAL.
06 NEW ALUMINUM STOREFRONT GLAZING SYSTEM AT
EXISTING EXTERIOR WALL. REFER TO SHEET A3.4a
FOR STOREFRONT TYPE. COORDINATE LINTEL W/
A STRUCTURAL
08 NEW SUPPORT COLUMNS FOR CANOPY, TYP.
SLOPE TO DRAIN SLOPE TO DRAIN 09 NEW WOOD HANDRAIL. PROVIDE BLOCKING AS
1/4":12" 1/4":12"
REQUIRED
11 STAINLESS STEEL 48" HEIGHT CORNER GUARD
14'-0"

SLOPE TO DRAIN

SLOPE TO DRAIN
12 NEW STOREFRONT. REFER TO SHEET A3.4a
13 BUILT-IN BENCH

1/4":12"

1/4":12"
04 7 14 ELECTRICAL ROOM ONLY AT EVEN FLOORS
ELEVATOR SHAFT P-01
TYP 15 STORAGE ROOM ONLY AT ODD FLOORS
A6.3 16 LOUNGE ROOM ONLY AT EVEN FLOORS, LAUNDRY
B M ROOM ONLY AT ODD FLOORS

SLOPE TO DRAIN
OPEN TO 17 DOOR PUSH PLATE

1/4":12"
SLOPE TO DRAIN

25 ABOVE 18 2-WAY COMMUNICATOR DEVICE


PENTHOUSE
1/4":12"

19 PROVIDE NEW WALL DOOR ACCESS FOR CLEAN


P-01 OUTS AT EXISTING LOCATIONS. REFER TO PLUMBING
14'-0"

DRAWINGS FOR MORE INFORMATION


20 ROLLER SHADES LOCATIONS. REFER TO FINISH
SCHEDULE FOR SPECS
SLOPE TO DRAIN SLOPE TO DRAIN RD 21 PATCH WITH NEW PARTITION ASSEMBLY WHERE
1/4":12" 1/4":12"
LOUVERS WERE DEMOLISHED
RD ORD 01 SLOPE TO DRAIN SLOPE TO DRAIN
C 1/4":12" 1/4":12" 22 NEW LOUVER LOCATION. REFER TO MECHANICAL
DRAWINGS

ALBANY TERRACE
ORD

3030 W. 21ST PLACE, CHICAGO, IL


23 G.C. TO MODIFY EXISTING PARTITION AS REQUIRED

SLOPE TO DRAIN
TO MEET 2HR FIRE RATING AND TO MATCH
PARTITION TYPE C2 ASSEMBLY

1/4":12"
04
14'-0"

24 G.C. TO MODIFY EXISTING PARTITION AS REQUIRED

APARTMENTS
RENOVATION
TYP TO MEET 1HR FIRE RATING AND TO MATCH
PARTITION TYPE A2 ASSEMBLY
25 ROOF EQUIPMENT RAIL, VERIFY SPACING WITH
MECH. CONTRACTOR, TYP.
26 NEW WALL MTD MTL LADDER FOR ROOF HATCH
D 27 NEW PREFABRICATED ROOF ACCESS HATCH
8 29 LINE OF FURRING PARTITION AT 16TH FLOOR.

1 / A1.18
ADJUST MILLWORK, FAN COIL, CLOSET SIZE, ETC. AS

60623
----------------------------------------------------------------------------------------------------------------------------------

HIGH POINT: +1'-6" ABOVE A6.2


REQUIRED
CONC. DECK, TYP.
30 (5) WIRESHEVES SPACED 12" APART. B/SHELF
STARTS AT 18" A.F.F.
31 (1) WIRESHELF MOUNTED AT 5'-8" A.F.F.

CONSTRUCTION PLAN LEGEND

ROOF & PENTHOUSE NORTH EXISTING TO REMAIN XX KEYNOTE


2 1/8" = 1'-0" NEW PARTITION
XX DOOR TAG
7 8 MILLWORK
XX PARTITION TAG
A NEW CONCRETE
Indoor units stacked SLAB GL-X GLAZING TAG
on each other (see CR CARD READER
photo)
10 11 12 13 14 CONSTRUCTION GENERAL NOTES ARCHITECT OF RECORD:
CANOPY ARCHITECTURE + DESIGN, LLC
1. ALL WORK SHALL CONFORM TO APPLICABLE CODES 180 W WASHINGTON ST,200, CHICAGO, IL 60602
AND COMPLY WITH ALL LAWS, ORDINANCES, RULES, PHONE: (312) 763-8005/ canopy-chicago.com
21'-0" 21'-0" 21'-0" 21'-0"
REGULATIONS, AND LAWFUL ORDERS OF ANY
2 / A1.18

PUBLIC AUTHORITY BEARING ON THE PERFORMANCE DEVELOPER:


THE MICHAELS ORGANIZATION
OF THE WORK.
B HIGH POINT: +1'-6"
2. CONTRACTOR TO COMPLY WITH OWNER AND/OR
542 S DEARBORN ST, 800, CHICAGO, IL 60605
PHONE: (856) 596-0500
OPEN TO ABOVE CONC. DECK, LANDLORD REQUIREMENTS FOR WORK ONSITE.
TYP. CONTRACTOR SHALL PERFORM ALL WORK IN CO-DEVELOPER:
BELOW
COMPLIANCE W/ ALL BUILDING RULES AND THE CHICAGO HOUSING AUTHORITY
REGULATIONS. 60 E VAN BUREN, CHICAGO, IL 60605
A 3. ALL EXISTING CONDITIONS AND DIMENSIONS SHALL PHONE: (312) 742-8500
BE FIELD VERIFIED BY THE CONTRACTOR. NOTIFY CIVIL ENGINEER:
IMMEDIATELY THE ARCHITECT OF ANY ERIKSSON ENGINEERING
DISCREPANCIES, COMMISSIONS, OR CONFLICTS 135 S JEFFERSON ST, 135, CHICAGO, IL 60661
BEFORE PROCEEEDING WITH THE WORK. PHONE: (312) 463-0551

14'-0"
4. THE CONTRACTOR SHALL PROVIDE AND MAINTAIN
Outdoor Units LANDSCAPE ARCHITECT:
C REQUIRED DUST BARRIERS, CANOPIES,
BARRICADES, PROTECTION, AND/OR WARNING
MCKAY LANDSCAPE ARCHITECTS
5215 N RAVENSWOOD AVE, CHICAGO, IL 60640
04 LIGHTS IN GOOD CONDITION UNTIL THE COMPLETION PHONE: (773) 561-1227
MACHINE ROOM TYP
OF THE WORK REQUIRING SUCH PROTECTION.
4 PROVIDE EGRESS PATHWAYS AS REQ'D FOR STRUCTURAL ENGINEER:
1/8" = 1'-0"
B SPACES TO REMAIN OCCUPIED DURING
CONSTRUCTION.
CARSELLO ENGINEERING
2656 WILD TIMOTHY RD, NAPERVILLE, IL 60564

SLOPE TO DRAIN
PHONE: (630) 854-9567
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR

1/4":12"
25 DAILY CLEANING AND REMOVAL OF ALL DEBRIS, MEPF ENGINEER:
DUST, AND EQUIPMENT RELATED TO THE
7 8 THE ENGINEERING STUDIO

SLOPE TO DRAIN
DEMOLITION AND THROUGH CLEAN-UP UPON 701 LEE ST #510, DES PLAINES, IL 60016

14'-0"
COMPLETION OF THE PROJECT. PHONE: (847) 795-8810

1/4":12"
A 6. PROTECT EXISTING EXTERIOR WALLS AND OTHER
ELEMENTS TO REMAIN THROUGHOUT WARNING: ASBESTOS CONTAINING BUILDING
CONSTRUCTION. MATERIALS ARE OR MAY BE PRESENT IN THIS
43'-4" V.I.F SLOPE TO DRAIN SLOPE TO DRAIN
7. THE DRAWINGS ISSUED HEREWITH ARE SCOPE BUILDING. AN ASBESTOS MANAGEMENT PLAN IS
01 1/4":12" 1/4":12"
AVAILABLE IN THE BUILDING FOR REVIEW UPON
ORD RD DOCUMENTS, AND AS SUCH SHOW THE GENERAL
C EXTENT OF THE PROJECT AND DO NOT
REQUEST. NO PERSON MAY DISTURB
ASBESTOS CONTAINING MATERIALS UNLESS
NECESSARILY INDICATE OR DESCRIBE ALL WORK THAT PERSON IS A LICENSED ASBESTOS
REQUIRED FOR FULL PERFORMANCE AND WORKER OR CONDUCTS SUCH WORK IN
SLOPE TO DRAIN

COMPLETION OF THE WORK, NOR DO THEY SHOW ACCORDANCE WITH SPECIFICATION(S)


1/4":12"

CONTAINED IN THE PROJECT DOCUMENTS AND


16'-2 1/2" V.I.F

04 ALL OF THE CONDITIONS WHICH MAY BE


01 IN COMPLIANCE WITH ILLINOIS DEPARTMENT

14'-0"
TYP ENCOUNTERED TO PROPERLY EXECUTE THE WORK.
OF HEALTH RULES AND REGULATIONS.
8. DO NOT SCALE DRAWINGS - DIMENSIONS GOVERN.
B LARGE SCALE DETAILS GOVERN OVER SMALL. ISSUANCE
9. WHERE DISCREPANCIES OCCUR BETWEEN THE
VARIOUS DISCIPLINES/TRADES, CONSULT THE MARK DESCRIPTION DATE
ORD RD ARCHITECT BEFORE PROCEEDING WITH THE WORK. SCHEMATIC DESIGN 06.19.20
D 10. PROVIDE FIRE RETARDANT BLOCKING AT ALL ITEMS
WALL-MOUNTED TO STEEL STUD AND GYPSUM
DESIGN DEVELOPMENT
80% CD
04.30.21
08.13.21
BOARD PARTITIONS.
2 / A1.18

PERMIT/ BID 10.01.21


LOW POINT: +5" 11. ALL ACCESSIBLE DOOR HARDWARE SHALL BE
HIGH POINT: +10 1/2" PROVIDED IN COMPLIANCE WITH CHICAGO BUILDING 1 PERMIT CORRECTIONS 04.22.22
ABOVE CONC. DECK, LOW POINT: +5"
ABOVE CONC. DECK, TYP. CODE AND ANSI. 2 RE-BID 04.22.22
TYP. AT DRAINS ABOVE CONC. DECK,
TYP. AT DRAINS 12. ALL DOORS REQUIRED FOR ACCESSIBLE ACCESS 3 IFC 12.22.22
C SHALL HAVE MANEUVERING CLEARANCES PROVIDED
PER CHICAGO BUILDING CODE.
13. REFER TO SHEET A9-01 FOR PARTITIONS TYPE.
PROJECT NUMBER: P2001
14. EXISTING FLOOR TO REMAIN TO BE LEVELED AS
REQUIRED TO RECEIVE NEW FLOOR FINISHES. TITLE
PENTHOUSE ROOF PLAN ROOF & PENTHOUSE - SOUTH 15. REFER TO RESIDENTIAL UNIT CALLOUT PLANS FOR
3 1/8" = 1'-0"
1 1/8" = 1'-0"
UNIT-SPECIFIC NEW WORK, TYPICAL FOR ALL UNITS
OF EACH TYPE, AS NOTED
ROOF AND PENTHOUSE
12/22/2022 2:49:16 PM

16. G.C TO VERIFY EXISTING PARTITION LOCATIONS AND PLANS


1 PROVIDE NEW AS REQUIRED TO MEET THE UNIT
LAYOUTS.
17. ROOFING SYSTEM SHALL HAVE AN INITIAL SOLAR SHEET
REFLCTANCE OF NOT LESS THAN 0.9 AND THREE

18.
YEARS INSTALLED SOLAR REFLECTANCE OF NOT
LESS THAN 0.88.
LOW SLOPE ROOF COVERINGS SHALL BE CLASS A.
A1.18
© 2022 CANOPY ARCHITECTURE + DESIGN, LLC

You might also like