HERITAGE INFRASPACE INDIA LTD

DAILY PROGRESS REPORT FOR DIAPHRAGM WALL & PILLING


Division : SOUTH DIVISION Date of Report: 03.01.2024
Name of the Project: BYPN DEPOT PHASE 2A Date of Starting Work as per Work Order

Place: BANGALORE Actual Date of Starting Work 25.10.2023

Date of Completion the Work as per Work Order

Name of the Client: J KUMAR-AICIPL JV Expected Date of Completion

DETAILS OF DIAPHRAGM WALL PANELS Hindrance if any


Sr. Reasons for Work
Date Thickness Previous Today Total Remarks
No. Length Depth in Scope in Balance in Hampered Reasons for
Number Type /Width in Shape Completed in Completed in Completed in NIL Progress
in RM RM Nos Nos.
mm Nos. Nos. Nos.

Dw-42 Grabbing Completed, Stop-end


1 02.01.2024 - 0 1000 Regular 5.50 20.00 46.00 27 0 27 19
Lowered, Cage Lowered

DETAILS OF GUIDE WALL Hindrance if any


Sr. Reasons for Work
Date Previous Today Total Remarks
No. Thickness/ Width in Balance in Hampered Reasons for
Type Length in RM Scope in RM Completed in Completed in Completed in
mm RM NIL Progress
RM RM RM

2 02.01.2024 - 1050 0 176 140.5 0 140.5 35.5

DETAILS OF PILE Hindrance if any


Sr. Reasons for Work
Date Previous Today Total Remarks
No. DIA in Scope in Balance in Hampered Reasons for
Number Location Type Depth in RM Completed in Completed in Completed in NIL Progress
mm Nos Nos.
Nos. Nos. Nos.

P-183 Concrete completed. Depth


3 02.01.2024 P-183 EDS-2 1000mm ROUTINE 0.00 25.4 80 26 1 27 53
From E.G.L

NOTE:
A. Resources available at Site like D Wall Rig B-200/ Pilling Rig, Crane 100T, Crane75T Crane40T, JCB, Compressor, DG etc.
B. Requirement of Manpower:
C. Manpower: Steel fabrication Manpower 65 Nos. Concrete Manpower 17 Nos & Anchor works Man Power 6 Nos. Total Manpower 88 Nos. Skilled 67 Nos & 21 Nos Unskilled.

Foreman Engineer Site In-charge Project Manager