January 4, 2024
Your Reference
To File : AECOM-Lombardi’s Mock NP-UAHEL-336951-CS-QCBS
Evaluation of selected sections of its own (formally known as
Technical Proposal for “Tender Design, PSRSHDP/UAHEL/S/QCBS-1).
Preparation of Bidding Document, Project No: P178722
Construction Supervision and Post
Construction Services for the Upper Arun Our Reference
Hydroelectric Project” OPP-1182298
a. AK-1 Team Leader (Maximum Score 70, Secured Score – 53.90 (77%))
Mr. Rakesh Mahajan, a highly accomplished professional with master's in Civil Engineering, an impressive 41 years of
experience in project management, planning, design, and supervision of hydropower projects in Asian countries. He has
extensive knowledge and understanding of international contract conditions and possesses excellent oral and written
communication skills in English. Through his exceptional leadership skills, as an overall in charge leading a team of 150
personnel and has successfully delivered the design and planning of 10 large projects, with his involvement exceeding 8
months in each project. Mr. Mahajan's expertise and leadership have made him a highly respected professional in the
industry. Considering the above, our anticipated scores are as follows:
Clarification about the man-month on the CV
Name of Project: Nyamjang Chhu Hydroelectric Project (780 MW) – Preparation of Detailed Project
Report (DPR) and Assistance to Client in Obtaining Techno-Economic Clearance
(TEC)
Year: 2011: January 2011 to December 2011 - 12-month duration
Name of Project: Indira Sagar Polavaram Multipurpose Irrigation Project (960 MW) –Detailed Design and
Engineering
Year: 2016: January 2016 to December 2016 - 12-month duration
Name of Project: Malana Hydroelectric Project (86 MW) – DPR, Tender Preparation, Detailed Design and
Construction Supervision
Year: 2001: January 2001 to December 2001 - 12-month duration
Name of Project: Regional Rusumo Falls Hydroelectric Project (80 MW) – Owner’s Engineer
Year: 2015: January 2015 to December 2015 - 12-month duration
Name of Project: Sechi Hydroelectric Project (4.5 MW) – Detailed Design and Engineering and
Construction Supervision
Year: 2012: January 2012 to December 2012 - 12-month duration
Name of Project: Bara Bangahal Hydroelectric Project (92 MW) – Preparation of Detailed Project Report
Year: 2013: January 2013 to December 2013 - 12-month duration
b. BK-2 Chief Resident Engineer | (Maximum Score 30, Secured Score – 23.30 (77.6%))
Mr. Dusko Pavic is an accomplished professional with 31 years of experience in civil engineering, structural engineering,
dams and powerhouses, site and team supervision. Specifically, he brings 25+ years of experience in planning and design
and construction supervision of hydroelectric plants. He brings international experience and design/supervision project
management on numerous projects. His expertise includes design of
spillway tunnels, preparation of site instruction for instrumentation, preparing concrete mix design, testing of concrete
quality, planning and site organization, of client staff, and review of detail design. His CV presents at least 6 projects of
similar natures/scale such as RCC Dam/dam height/ Installed capacity/HRT Ø/Cavern width, with his involvement
exceeding 12 months in each project, out of which 4 projects as a Chief Design Engineer or Design Coordinator.
Considering the above, our anticipated scores are as follows:
c. BK-3-1 Resident Engineers for Headworks (Maximum Score 30, Secured Score – 13.20 (44%)
Mr. Vijay Kumar Singh is a highly experienced civil engineer specializing in the construction supervision of hydraulic
structures for hydroelectric projects particularly the intricate process of roller compacted dam construction. With an
impressive experience of 25 years as resident engineer, out of which 17 years of
experience in the field of construction supervision of hydraulics structures of HEP, Mr. Singh possesses a
comprehensive knowledge of international acceptable contract conditions. His expertise in managing and
overseeing projects in Asian countries has been demonstrated through his continuous involvement for durations
exceeding 24 months. This extended engagement has allowed him to develop a profound understanding of the
complexities associated with the construction of such structures. Mr. Singh’s notable achievements include the
successful completion of two projects. Considering the above, our anticipated scores are as follows:
Relevant experience in 28 years of experience in working in India (Kiru Exceeds the Maximum
Asian countries would be Hydroelectric Project, Tidong-1 Power Generation, minimum i.e., 100%
an added advantage. Chuzachen Hydroelectric Project, and Pinapuram PSP requirement
Project)
The experience of IBN Hammad Dam Project - Involved till successful Exceeds the Maximum
involvement of the expert completion of project. minimum i.e., 100%
up to the successful Chuzachen Hydroelectric Project (110 MW) - requirement
completion of the project Involved in project from its start until its
will be an added commissioning and post commissioning works.
advantage.
d. BK-3-3 Resident Engineers for Powerhouse (Maximum Score 30, Secured Score – 25.2 (84%)
Mr. Mukesh Kumar, a highly skilled civil engineer with a Master's degree in Structural & Construction Techniques, with
25 years of professional experience, Mr. Kumar has dedicated 20 years of experience as a resident engineer in the field
of construction supervision of hydraulic structures of hydroelectric projects. Mr. Kumar's expertise extends beyond
construction techniques and possesses a wealth of experience in reviewing construction designs submitted by EPC
contractors, ensuring their compliance with project requirements and international contracts. Notably, Mr. Kumar has
been involved in 3 projects for durations exceeding 24 months, demonstrating his commitment and dedication to
delivering successful outcomes. He has played a pivotal role in the successful completion of one project, with his active
involvement throughout the process. Considering the above, our anticipated scores are as follows.
e. BK-4-1 Senior Mechanical Engineers (HSS) (Maximum Score 20, Secured Score – 15.7 (78.5%)
Mr. Horia Babau is a highly skilled hydro-mechanical engineer with 31 years of design and construction supervision of
hydro-mechanical and powerhouse mechanical design of large hydropower projects, with 25+ years of extensive
experience in planning, erection, and troubleshooting hydropower systems. Mr. Babau is a specialist in hydraulic and
pneumatic system supervision, troubleshooting and maintenance for hydropower projects and power hydraulic
installations including significant experience in planning and troubleshooting hydropower systems. He has experience with
World Bank projects such as the Kainji HPP (760 MW) and INGA1 and INGA2 hydroelectric complex. His expertise in
managing and overseeing projects in has been demonstrated through his continuous involvement for durations exceeding
24 months in at least 5 projects of similar nature and scale, out of which 3 as a Senior Mechanical Engineer and 2 as
Resident engineer.
Considering the above, our anticipated scores are as follows.
RFP Expert qualifications
Anticipated
and competence for the Expert Qualification & Experience Comments
Scores
assignment
The Senior Mechanical Bachelor of Science, Mechanical Engineering, Meets the Qualifying
Engineers should have Technical University of Timisoara, Faculty of minimum i.e 80%
minimum a Bachelor’s Hydraulic Machines, Romania, 1992 requirement
degree in the field of
Mechanical Engineering
and preferably a Master's
degree in Mechanical
Engineering or any
relevant discipline.
They should have at least 31 years of design and construction supervision of Exceeds the Maximum i.e.,
15 years of experience in hydro-mechanical and powerhouse mechanical design minimum 100%
the field of design and of large hydropower projects requirement
construction supervision
of hydro-mechanical and
powerhouse mechanical
design of large
hydropower projects.
S/he should preferably 5 projects of similar natures/scale such as RCC Exceeds the Maximum i.e.,
have an experience as a Dam/dam height/ Installed capacity/HRT Ø/Cavern minimum 100%
Senior Mechanical width, with his involvement exceeding 12 months in requirement
Engineer in detailed each project, out of which 3 as a Senior Mechanical
design and construction Engineer and all based on international contracts.
supervision of hydropower
projects of similar nature INGA-1 (360 MW) & INGA-2 (1424 MW)
and complexity. Hydroelectric Complex – Rehabilitation -
The Senior Mechanical Democratic Republic of the Congo
Engineers shall be the key 36 man-month
member of the Senior Mechanical Engineer/Resident
consultancy team, and as Engineer (Assigned in DR Congo)
such are expected to have 1424 MW
been involved in at least Monitored all project developments (construction
two (2) projects of a similar supervision)
nature based on
Optimization of Shipshaw HEPP (1145 MW) –
international contracts.
Canada
The Experts' involvement
2011 - 2012: January 2011 to March 2012 - 14-
in the previous assignment
month duration
as the Senior Mechanical
Senior Mechanical/Resident Engineer
Engineers in the individual
1145 MW
hydropower projects need
Monitored all project developments (construction
to be equal or more than
supervision)
twelve (12) man-months.
Kainji Hydropower Plant (760 MW) – Nigeria
48 man-month
Senior Mechanical Engineer/Resident Project
Manager (Upgraded from Chief Resident Engineer),
assigned in Nigeria
760 MW
65-m high earth and concrete dam
Monitored all project developments (construction
supervision)
Chamera II HEPP in India (300 MW) – India
2003 - 2004: January 2003 to May 2004 - 16-
month duration
Field Project Supervisor (Assigned in India)
Designed, led testing and the successful
commissioning of Hydraulic Pressure Greasing
System
Technical site supervision
Nurek Hydropower Plant (3375 MW) - Republic of
Tajikistan
24 man-month (and ongoing)
Chief Resident Engineer (Assigned in
Tajikistan)/Team Leader of a Multi-disciplinary
international Team (seven expat engineers)
3375 MW
Monitored all project developments (construction
supervision)
f. BK5 – Senior Electrical Engineer (Maximum Score 20, Secured Score – 9.70 (48.50%))
Mr. Leonardo Nieto, a highly skilled electrical engineer with 40 years of professional experience, performing as field
resident engineer, design engineer, project engineer, supervision engineer, project coordination and managing. Mr. Nieto
has dedicated more than 25 years of experience in different kind of hydroelectric electric projects concentrated in main
activities such construction, detail engineering, preparation of technical specifications for bidding documents, follow-up
of planning, technical supervision, testing, assistance to factory acceptance tests and commissioning. Mr. Nieto as well
has actively participated in contract negotiations for manufacturing and supplying of electromechanical equipment for
hydropower plants and substations comprising turbines, generators, switchgears, power transformers, control and
protection devices, gates, bridge cranes, penstocks, etc. Notably, Mr. Nieto has been involved in few projects for
durations exceeding 44 months, demonstrating his commitment and dedication to delivering successful outcomes. He has
a remarkable experience in international projects, particularly in Canada, Colombia, Dominican Republic, Guatemala,
India, Rwanda, Senegal, Guinea, and others. Considering the above, our anticipated scores are as follows: