GNB-CPD Guidance from the Group of Notified Bodies Issued: 22 October 2003
for the Construction Products Directive
AG 89/106/EEC
APPROVED –
INFORMATIVE
- are for general use and should be reviewed by SGs and elaborated further, amended or adapted to the
special product under consideration,
- should be considered as measures to be taken into account when undertaking inspection body duties when
carrying out initial inspection and continuous surveillance,
- may be taken by CEN/EOTA for consideration when specifying the respective methods of control of
conformity.
Check List for Initial Inspection of Factory and of Factory Production Control
In the course of the initial inspection the following criteria should be considered:
I. GENERAL QUESTIONS
10 Do the findings of these tests correlate with the requirements laid down in
the technical specification for initial type testing, and for testing for
surveillance purposes of the FPC?
12 Does the producer apply an adequate documented system that allows the
detection of defects and deviations quickly enough to identify
unambiguously those products that are not in accordance with the product
specification so that they are removed prior to delivery?
In which way is the marking of such products performed?
14 Summary of the results by the inspection body and the specification of the
measures to be taken for correction if necessary
Page 2 of 4
Check list for the continuous surveillance
I. GENERAL QUESTIONS
Page 4 of 4