Professional Documents
Culture Documents
Note For Maj - Br.543 Edited 01-01-2023
Note For Maj - Br.543 Edited 01-01-2023
(ii) Clarification required for Construction of One abutment (A1), one pier (P2)
leftover work proposed including pile foundation and allied works
pertains to the contract. proposed to undertake through instant open
tender.
(iii) The physical and financial As of now, the physical & Financial progress of
progress of the existing works is 55% and 63% respectively.
contract may be mentioned
for the better appraisal of
the proposal
(iv) The girder launching work is In quite a number of occasions tenders for
specialized job clubbed with composite works were invited and reasonable
civil works (execution of offers were received. There are Agencies available
foundation and substructure who have executed entire bridge works or even
may) may please be substructure and girder launching works
reviewed. separately. For Important /Major Bridges i.e.
Construction of major bridge/ROB/RUB with
foundation (Open/pile/well) and superstructure
(Steel/Composite) vide Sl No 17(a) & (b) of List of
approved Definitions of Similar Nature of Works
issued by the office of CAO/Con/BBS on
03.08.2022 and all tenders are being invited
accordingly except in exceptional cases, where the
girders are being procured from Railway
Workshop. However in the instant case, execution
of foundation /sub-structure also warranted as
submitted at (i) above.
In view of the above CAO/Con/BBS is requested to recommend the instant proposal for inviting open
tender in conventional method (Non-EPC) for the subject work with the above mentioned salient features
for approval of GM/ECoR.
Dy.CE/Con-I/VSKP
CE/C/JDB:
CAO/C/BBS:
GM/ECoR:
NS-1
NOTE: Date: 18.10.2023
2.0 Till now 10(Ten) block sections i.e. between Kottavalasa-Boddavara, Shimiliguda-Gorapur and
Padua-Suku stations (97.1Kms) out of 19 block sections have been commissioned and opened
for traffic. Work in progress in another 05 block sections i.e. between BDVR-SLPM, BGHU-
KVLS-SMLG and GPJ-DPC-PFU. Tenders invited for execution of works in the remaining section
i.e. between Shivalingapuram-Borraguhalu stations.
3.0 Moreover, some works are sanctioned in and around VSKP, which are to be executed.
Divisional Officers are required to frequently visit the construction sites as per the laid down
regulations. There is considerable movement of Headquarters officers to VSKP for various
inspections. Further they are required to stay at Araku for Inspection execution/
commissioning of ongoing doubling works. It is noticed that quite often, the accommodation
available at Visakhapatnam and Araku becoming very inadequate and it is becoming very
much difficult to accommodate higher officers leading to refusal of accommodation. The
existing ORH at Araku is insufficient to cater the present requirement as such officers are
forced to stay outside/ to opt for private accommodation. Similar is the situation at VSKP.
Hence availability of proper resting accommodation for inspecting officials at Araku and VSKP
is very much necessary. DRM/WAT vide letter dated 13.06.2023 & 04.07.2023 addressed to
CAO/Con/BBS has highlighted the persistent heavy demand for Rest House at Araku and
Visakhapatnam from Officers of Open line as well as Construction and requested to construct
additional accommodation in the existing campus of ORHs at Araku and Visakhapatnam. At
BGHU, the existing Rest House is to be dismantled to accommodate double line and hence it
is proposed to relocate the same on the station building side.
4.0 As such it is proposed to construct one ORH at Araku& Visakhapatnam to cater the present
requirement of Construction Organization as well as future requirement after commissioning
of double line. Further, at Borraguhalu, the existing ORH is to be dismantled and relocated for
accommodating additional lines in the yard. As such, new ORH building to be constructed at
Borraguhalu immediately. KTV-KRPU Doubling Estimate includes 150sqm (0.22 crores) towards
construction of ORH/SRH. The present scope of work is Construction of ORH at Araku (4 suits)
and Borraguhalu (2 suits) and at VSKP (6 suits). As construction of ORH at BGHU is obligatory
in view of the necessity to replace the existing ORH, the total cost of proposed works will be
included in revised estimate/ completion estimate as applicable.
5.0 The approximate cost of the proposed ORHs at Borraguhalu, Araku and Visakhapatnam has
been assessed as Rs 6.6 Crores.
In view of the above, CE/C/JDB is requested to forward the proposal to CAO/Con/BBS for
further forwarding the same approval of GM.
Dy CE/Con-I/VSKP
CE/C/JDB
CAO/Con
GM