Professional Documents
Culture Documents
Appendix P Draft Construction Method Statement
Appendix P Draft Construction Method Statement
XXXX
XXXX
XXXX
Contents
1 Health and Safety Plan Error! Bookmark not defined.
1.1 Site Safety Induction Error! Bookmark not defined.
1.2 Company name Representatives Check List Error! Bookmark not defined.
1.3 Site Register (for personnel coming on/off-site during the day): Error! Bookmark
not defined.
1.4 Contacts Error! Bookmark not defined.
1.4.1 Site Contacts: (combination of named below to be on site) Error! Bookmark
not defined.
1.4.2 Company name Contacts Error! Bookmark not defined.
1.4.3 External Contacts (if applicable) Error! Bookmark not defined.
1.4.4 Emergency Contingency Plan Error! Bookmark not defined.
2 Project Proposal 3
2.1 Planned Start Date 3
2.2 Estimated Duration: 3
2.3 Location of Project 3
3 General Method Statement for the civils, mechanical and electrical installation of a
the ~185 MW Tauhei Solar Farm project 4
3.1 Site Induction 4
3.2 Site Setup 4
3.3 Working environment and restriction 5
3.4 Protection of others 5
3.5 Emergency Procedures & General Health and Safety 5
3.6 Operatives / Competence 5
3.7 PPE Requirements: Error! Bookmark not defined.
3.8 Materials handling and storage 6
3.9 Methodology for works: 7
3.10 Plant List: 13
3.11 General: 13
3.12 De-Mobilization of Site: 13
3.13 Health and Safety: Error! Bookmark not defined.
1 Project Proposal
Development of a ~185 MW solar photovoltaic (PV) plant, connected via electric cables to
Transformers, Inverters, Sub-stations and any other required auxiliary equipment units. The
proposed works on-site include installation of:
Add date
XX Weeks
NOTE: This Construction Method Statement is to be used in conjunction with the task-
specific RAMS and the Construction Phase Plan, which will be available at the pre-
construction phase.
2 General Method Statement for the civils, mechanical and electrical
installation of a the ~185 MW Tauhei Solar Farm project
• All personnel involved in the works will attend a site safety talk.
• All personnel involved must adhere strictly to site rules as defined by Company Name in the
induction.
• All supervisors will be required to attend safety briefings and toolbox talks when site
management deems appropriate. These will allow the dynamic changes to the site to be
communicated to the workforce and ensure that safe working is maintained.
• A Permit to Work (PTW) system will be implemented for works deemed applicable (i.e. hot
works). A PTW will be completed prior to any works commencing when applicable and
signed off daily.
• Perimeter Fencing:
o To be installed by Company name sub-contractor - XXXX
• The plant will be present on-site for the duration of the works. Appropriate routes to be
defined at the start of the works.
• Site signage, warning signs and pedestrian barriers will be set up. “Construction warning”
set up at site entrance. Warning signs to be erected along with netlon barrier at tree
protection area.
• Site welfare facilities will be a 20ft site offices, 20ft canteen, 20ft toilets (including separate
ladies) and drying room (when required)
• All personnel have Construction Skills Certification Scheme (CSCS), Construction Plant
Competence Scheme (CPCS) or relevant competency cards.
• The site Manager is Site Management Safety Training Scheme (SMSTS) or equivalent and 1st
Aid qualified.
• All electrical works will be undertaken by qualified electricians.
2.7 Materials handling and storage
• Deliveries to Site:
• Storage:
o PV modules, structure and other electrical equipment will be protected from the
elements and securely stored by Company name.
o Packaging should be kept dry to avoid collapse or compression of the packaging
which might lead to damage to the equipment.
All other equipment (electrical, ducting etc.) will be stored in a secure location (locked
container) until ready to be installed, location subject to site agreement (see proposed Layout
plan.
• Waste:
• Access:
o All routes will be kept free of obstacles and trip hazards during the period of works.
o Access to the site is to be via designated pedestrian and vehicle routes detailed on-
site plan. This will inevitably change throughout the works and will be
communicated to all site personnel via safety briefings with the site manager.
o Site management will provide designated access and egress routes to and from the
site.
o The site is exposed to the elements. All personnel will be required to wear
appropriate PPE to protect them from adverse weather conditions and encouraged
to use sunscreen as required.
o Works should cease in bad weather (persistent heavy rain, storm, high winds) as
instructed by the site manager.
o All cutting is to be carried out at the agreed location. Site management to take steps
to protect materials and other trades/personnel. Sub-contractor to provide a fire
extinguisher which will be present during all cutting works. A Hot works permit is to
be obtained each day as required.
o Cutting to be carried out on a firm surface and all cutting equipment to be secure
and stable.
o PPE to be worn includes gloves, face mask or approved safety goggles, ear
protectors, steel toe cap boots. (applicable to a specific task)
o All cutting equipment to be properly maintained and PAT tested.
o Instructions to be followed and guards to be used.
Note: Access track to have plate test done to assure it can handle the required crane loads
• 3rd Operation – Edge of park (customer substation) connection substation:
All lifting operations must be planned, supervised and carried out by competent people. This
does not mean it is necessary for an Appointed Person to be present during all lifting
operations.
2.10 General:
• Personnel have a responsibility to conduct work in a safe manner and must adhere to their
Method Statements and Risk Assessments and all working procedures.
• All-access equipment/plant used is certified, numbered, inspected, logged and maintained
as per the manufacturer’s requirements.
• All areas of work will be left in a clean and presentable condition on a daily basis.
• All items of equipment will be stored appropriately on site.
Name
Title
METHOD STATEMENT ACCEPTANCE FORM
This sheet is signed as confirmation that the individuals have read and understood the
above-named method statement and agree to carry out the works as stated, safely and
efficiently.