Cantilever Loading Platform Dismantling
Cantilever Loading Platform Dismantling
Project Phase 1
Signature:
Name:
Date:
Time:
1.0 Introduction
The purpose of this Method statement to explain how the cantilever loading platform installation at
level 3 K5 CUB Building will be carried out in safely manner and to follow the standard lifting
procedure being implemented.
All materials used on site must be approved type and they are as follows: -
Trades Anticipated
Numbers
Mobile crane operator 1
Semi-trailer truck operator 1
Flagman / signalman/ 4
banksman
Skill workers/ Installer/fitter 5
Rigger 2
Lifting supervisor 1
Safety coordinator 1
General workers 6
Forklift Operator 1
4.1 Access
Access will indicate in the Lifting plan and get the approval from Exyte 1 day before
site is ready to move in
All worker, project management team, material or equipment and machinery delivery
must be entering from the site entrance and transporter detail must be provided to
security team 1 day in advance.
All visitor and vendor which are entering the site should apply permit for temporary
badge from the security team.
Lifting plan will incorporate the traffic control plan during lifting activity.
Adequate protection will be provided for the material/access route to ensure that
there is no damage during the transportation process.
Latest construction drawing shall be prepared and ready onsite upon receiving of
materials.
During the loading and unloading the driver of the trailer shall switch off the engine
and move to a safe area.
4.3 Handling
Lifting activity will be conducted as per approved Lifting Plan and construction
drawing.
Task lighting will be provided by ZSCECM if the activity will extend beyond 1800
hours/ when is necessary, subject to the environment.
Read labels and Material Safety Data Sheets (MSDS) before storing chemicals or
flammable materials. Smoking is strictly prohibited on site. Non-compatible materials
must be segregated in storage.
Work will be carried out in compliance with safety requirements and legal regulations.
Lifting activity and mobilization shall be done by trained person and use correct tools/
equipment as per agreed by Exyte management.
Carry out site inspections and plan approval from Exyte officer 2-3 working days
earlier before start any erection at site
The application for road occupation for hoisting must be made 1-2 days in advance.
During hoisting, barricades shall be set up in the hoisting area and maintained.
Personnel shall not pass during hoisting
The crane must be accepted by Exyte, and enter the work site only after getting
approval. Crane operators and signalmen must have relevant certificates, and non-
professionals are not allowed to operate
Check logistics plan, access road, ground condition for unit delivery and mobile crane
parking/hoisting task
- All the material should be stored in a proper manner with barricading and appropriate
signages.
- All the materials stored shall be covered up with no direct contact with ground.
- All the material shall not block emergency access or equipment and all the
passageways must be kept clear of obstructions and slip, trip and fall hazards. A 36-
inch clearance shall be maintained around emergency equipment and the emergency
equipment shall be clearly marked.
- Keep storage area free from accumulated material that may causes slips, trips, falls
or fires or that may contribute to harboring pests.
- Stack material no more than 1.5m if handled manually and no more than 2m fi using
a forklift and remove all nail from the used lumber fore stacking it.
Job Safety & Health Analysis (HIRARC) shall be conducted on all hazardous activities at
project site. The hazards in a particular activity and the control measures n implemented in
the HIRARC shall be briefed to the workers during safety induction and toolbox meeting
All workers employed in the project site must have valid CIDB green card.
All new workers and staff must attend the Safety Training or Safety Induction Course before
commencing works at site and attendances shall be recorded in an induction checklist.
All site personnel shall wear proper Personnel Protective Equipment (PPE):
Safety helmets, google, glove, safety vest, safety boots and Wellington Boots with steel toe.
Monthly safety meetings shall be held with all the contractors’ related-to-works.
All workers must attend the daily toolbox meetings held at site and attendances shall be
recorded.
Traffic signal man to execute the traffic management plan & control the traffic flow during
the execution works on affected areas.
Driver or operator should follow the safe operating instruction laid out in the operation
manuals of the respective transport vehicles or machineries.
All the trailer or lorry entering the site shall be guided by a banksman with a speed limit of
15 km/h and switch on the hazard lights whilst escorting the incoming or outgoing vehicles.
During unloading a tire stopper must be in place, barricade the area and put up signage.
All the trucks and trailers should pass through the wheel washing bay before leaving the
site and workers will be assigned to carry out road cleaning with water if necessary.
Cranes must not be left unattended whilst suspending a load. When not in used and left
unattended, crane cabs and compartment must be kept closed with controls or power pack
locked off and the vehicles parked without obstructing access.
Site access and external road to maintain in clean condition at all time.
Area should be barricade adequately with warning barriers prior to any lift.
All equipment shall be checked for good conditions before commencing the
work
Unauthorized persons shall be excluded from the area.
When lifting the personnel shall not remain in the lifting equipment work area.
Adequate caution boards and waring sign shall be provided
Only trained and authorized personnel shall operate the hydraulic lifting
device
Observance of the lifting equipment capacity.
lectrical installation and equipment shall confirm to standards.
Application, maintenance, storage, of electric and oxygen cutting welding
units shall confirm to applicable standards.
Do not stand under suspended loads
On completion of job, the area shall be cleared of any materials and kept
clean and tidy.
Hazard analysis for hazardous operation shall be carried out prior to
commencing the works.
- To identify all the factors that may cause harm to employees and other (the
hazards).
- To consider what the chances are of that harm actually be falling anyone in
the circumstances of a particular case and the possible severity that could
come from it (the risk).
This value is based on the likelihood of an event occurring. You may ask the question “How many
times has this event happened in the past?”. Accessing likelihood is based worker experience,
analysis or measurement. Likelihood level range from “most likely” to “inconceivable”
incidents / issues;
3) Quantified high exposure to the risk without any controls
in place.
3 Conceivable 1) May occur or known to occur; 3
2) Infrequent number and regularity of reported incidents /
issues;
3) Quantified moderate exposure to the risk without any
controls in place.
4 Remote 1) Could occur at some but not expected; 2
2) One or two reported incidents / issues to date;
3) Quantified low exposure to the risk without any controls
in place.
5 inconceivable 1) Highly unlikely to occur; 1
2) No evidence of reported incidents / issues in the past;
3) No quantified and known exposure to the risk without
controls in place
L x S = Relative Risk
L = Likelihood
S = Severity
Consequence Table
Negligible - 1 Minor - 2 Serious - 3 Fatal - 4 Catastrophic - 5
Minor abrasion, Disabling but non- Non-fatal injury, Approximately Numerous
first aid type injury permanently permanent one single fatality fatalities,
SEVERITY (S) injury. disability. major property irrecoverable
damage if hazard property damaged
LIKELIHOOD is realized and productivity
To use this Risk Matrix table first find the severity column that best describes the outcome of risk. Then
follow the likelihood row to find the description what best suits the likelihood that severity will occur. The
risk level is given in box where the row and column meet. The relative risk value can be used to prioritize necessary
action to effectively manage workplace hazard.
Further risk reduction required where possible; remedial action to be taken immediately; 7 day (max) review needed
MEDIUM
to ensure risk level assigned is accurate and does not increase over time; management attention required.
This hazard assessed, as HIGH RISK must have immediate actions. To resolve risk to life safety and or the
environment. Individual responsible for required action, including follow up must be clearly identified. A
further detail risk assessment method may require such as quantitative risk assessment as mean of
determine suitable control measures.
Check weather
forecast prior to work
activities.
that use to work on the Extension - back pain establish below work
Service Platform during the - blister area according to
dismantling work. approved work plan.
Damage tools Use correct PPE (anti-
and equipment cut hand glove) if
necessary.
4
Flatbed Loader delivers for Mechanical
standby to carry the Hazard. Ensure the ESP is in
dismantling extension service a safe condition on
Falling Objects the low loader
platform out from EXYTE
project site.
Physical Driver to ensure that
Hazard slings and shackles
Use provided route to K5 building
are properly
area. Moving plant
secured.
and equipment
- Vehicle impact
Driver must ensure
use proper
equipment for
securing the ESP.
Trained banksman
shall be deployed to
guide
vehicles/cranes from
Confirm routing
provided.
Pay attention to
reverse and road
bedding on steep
slopes or unstable
roads.
5
Secure ESP tie rod and
disengage it from building
structure Working at Lifting supervisor to
height established lifting plan
-Fall of person prior start work.
Active, swing and extend crane
- Fall of material
boom and position the boom on To ensure Rigger,
top of the Extension service Manual Signalman is
platform tie rod. handling designated to carry out
- Physical injury the job.
Slowly lower the hoist and hook
- back pain
up the shackles/slings to the ESP Use an inspected step
- blister
tie rod. ladder to climb up and
down on the trailer.
Lifting supervisor will conduct Moving plant
survey and confirm that it is in and equipment Ensure to not
Use of two-way
communication device
for guiding the crane
operator
With using scissor lift Rigger/skill Sharp points Ensure all trip hazards
workers will reach the ESP material / on truck bed are
support column anchor area and equipment or removed.
install pad eye with anchor bolt. cutting edges.
- Cut injury Ensure material
- possible damage securely attached to
Continue with attached chain
to lifting gears the lifting gear before
block to the installed pad eye and start lifting process.
Use of two-way
communication device
for guiding the crane
operator
boom and position the boom on -Fall of person prior start work.
top of the Extension service - Fall of material
platform. To ensure Rigger,
Manual Signalman is
Slowly lower the hoist and hook handling designated to carry out
- Physical injury the job.
up the shackles/slings to the 4
point of ESP lifting lug. - back pain
Use an inspected step
- blister
ladder to climb up and
Lifting supervisor will conduct down on the trailer.
survey and confirm that it is in Moving plant
order before signalman instruct and equipment Ensure to not
the crane operator to proceed with - Vehicle impact dismantle trailer
the lifting. stanchion as protection
Damage tools fence for additional
Slowly hoist up the crane jib until and equipment protection.
the attached shackle and sling belt
give a vertical tension force to the Physical injury Ensure sufficient
- cut, blister, lighting for all work at
ESP structure.
electric shock height activities.
- After the ESP structure safely Ensure all trip hazards
Sharp points
receives a vertical force from on truck bed are
material /
crane, rigger/skill workers start equipment or removed.
loosen up and disengage it from cutting edges.
building structure. - Cut injury Ensure material
- possible damage securely attached to
- continue with slowly lift up the to lifting gears the lifting gear before
ESP structure and slide it out from start lifting process.
level 3 area. Limited distance
of sight – no / Ensure did not
limited lighting dismantle trailer
- After all ESP structure out of
facilities or protection fence.
level three space slowly swing the
obstruction from
crane boom until it reaches on the All tools equip with
other object
top of standby flat bad trailer and (wall) at work lanyards.
slowly lower down the ESP zone
structure until it safely land on top - Knock and hit Use proper inspected
of the flat bad trailer. workers and approved lifting
gear.
- Secure the ESP structure with off shape and
strap or any chain block to the flat over size and Do not exceed safe
bad trailer hook point. overweight working load of the
material machine.
-flat bad trailer drive out from site - sharp edges
Use of two-way
communication device
for guiding the crane
operator
7
Housekeeping & Demobilization
Poor Stack and arrange
At the end of the operations, housekeeping item not exceeding
housekeeping will be carried out. 2.0m
Slip trip and fall
Crane, forklift etc. will be demobilized. All loose materials
Physical hazard should be properly
Barricade will be removed. secured on pallets
Housekeeping to be
done periodically
To establish exclusion
zone / hoarding as per
proposed and approve
work plan with rigid
barrier
Set up signage /
warning signs to alert
others
To ensure floor is
sufficiently protected
(floor protection)
Supervisor to reinspect
the whole flooring to
ensure no slip trip and
fall hazards.
Mark / put up
warnings for area with
uneven floors / steps
or scuppers
Complete and append the Inspection and Test Plan (ITP) for the work, to include:
1. Receiving of materials / machinery
2. In-process inspection during installation and positioning
3. Final stage prior
ITP shall also address the “Hold Point”, where approval on the work activity is required.
Attachment 4 - HIRRAC