Professional Documents
Culture Documents
Functional Stability Pile
Functional Stability Pile
2013). Adapting these for working platforms usually requires unreinforced and reinforced platform depths have been
assuming a load spread angle (β) to reduce the imposed rig load considered for the following methods BR470, SP123 and
pressure throughout the platform. With little guidance on Okamura et al. (1998), for a granular platform on a cohesive
suitable partial factors, these are often designed in line with subgrade. A range of subsoil strengths were compared for a
permanent foundations and as a consequence can be typical working platform case, detailed in Table 1.
excessively conservative.
Table 1. Input Parameters for Design Comparison
Okamura et al. (1998) enhanced this model by analysis and Loading Conditions
formulating the bearing capacity of a granular fill overlying an Rig Loading Pressure ws 200 kN/m2
undrained soil. This provided a more realistic bearing capacity Track Width W 0.5 m
but included no option to consider geosynthetic reinforcement. Track Length L 2.4 m
Platform Fill Properties
2.4 Numerical Analysis Frictional Shear Strength ' 40°
Unit Weight 20 kN/m3
In addition to analytical and empirical models, it is possible to
Subgrade Properties
use numerical tools to analyse the complex failure planes and Undrained Shear Strength cu 20-50 kN/m2
bearing capacity. This can be undertaken typically using Unit Weight γ 19 kN/m3
bearing capacity or limit equilibrium software. Increasingly In each comparison the strength of geosynthetic reinforcement
Discontinuity Layout Optimisation (DLO) modelling is being was increased until there was no conceivable benefit to the
used to check bearing capacity. The indiscriminate nature of reduction of platform thickness.
the check allows realistic bearing shear failure planes to be
found for complex problems (Figure 4). More information on Figure 5 highlights the wide range of calculated platform
the study of working platforms using this tool can be found in thicknesses required by each approach with varying subgrade
Smith and Tatari who concluded that the DLO method was strength. For unreinforced platforms the Okamura et. al.
better at determining a greater number of failure mechanisms methodology generally results in the thinnest platform. There
including a formerly unreported rotational snapping of a thin is some cross over with the BRE 470 method below a subgrade
embankment (2016). strength in the order of 23kPa and equalling the SP123
thickness at 50kPa. For the BRE 470 and SP123 methods, as
expected, the reinforced platforms calculated are thinner than
unreinforced platforms.
345
Proceedings of the XVI ECSMGE
Geotechnical Engineering for Infrastructure and Development
ISBN 978-0-7277-6067-8
RÉSUMÉ Plates-formes de travail temporaires sont essentielles pour la stabilité de l'installation, l'efficacité et la sécurité de fonctionne-
ment. Le guide de bonnes pratiques (BR 470), «les plates-formes de travail pour l'usine de camions» a été préparé par le BRE en Juin 2004
Le premier objectif de ce guide est d'atteindre un niveau de sécurité acceptable pour empilage et d'autres opérations de l'usine à chenilles.
Le guide inclut l'option d'utiliser des produits géosynthétiques comme renfort structurel. Conceptions basées sur cette directive se traduit
souvent par une plate-forme de travail trop épaisse. Des recherches approfondies ont été réalisées sur des couches d'agrégats non liés méca-
niquement stabilisé avec une structure de géogrille hexagonale avec des ouvertures triangulaires. Sur la base de cette recherche avec une
expérience sur le terrain, une méthode de charge de propagation a été conçue comme une approche alternative au guide de BR470 qui four-
nit une conception économique sûr, mais plus avec une empreinte carbone plus faible. Cette approche a été largement utilisée dans de nom-
breux projets au Royaume-Uni pour les plates-formes de travail sur des sols de fondation plus faibles, parfois inclus, conditions de charge
extrêmes. Ce document met en évidence l'application de plates-formes de travail stabilisées mécaniquement sur deux projets avec des con-
ditions géotechniques et de chargement difficiles; Crossrail, contrat C310 à North Woolwich et de développement commercial à Ipswich.
Les plates-formes de travail stabilisées non seulement permis l'utilisation de matériaux recyclés, mais aussi de réduire l'épaisseur de la
plate-forme de travail pouvant aller jusqu'à 65% par rapport à une conception avec le BR470. Ainsi les plates-formes de travail stabilisé
mécaniquement conçus avec une méthode de charge de propagation de façon empirique pour des structures de géogrille hexagonale peut
réduire le coût et le temps de construction et de réduire ou d'éviter la nécessité d'importer le remblai granulaire, tout en créant une plate-
forme de travail durable, sans danger pour le suivi du projet.
1395
Piling 2020
There are three possible categories of shear key (see Fig. 8):
Unreinforced Full Depth: Typically extending through the
weak soil layer(s) and embedded into stronger soils below, the
key completely isolates the weaker layer, preventing extrusion.
The granular fill to these trenches improves the drainage of the
soft underlying soils.
346
Piling 2020
4.3 Rotational Failure - Edge Stability Notwithstanding the design method used to establish the
Further checks on rotational edge stability may be undertaken working platform thickness additional design considerations
using limit equilibrium software (Figure 9), especially where relating to edge stability are necessary. BS8006 provides a
adjacent features (in this case a river channel) could comprehensive guidance or dealing with edge stability and
compromise platform stability. commercially available software packages are a useful
additional design tool. Shear key trenches, particularly when
reinforced, provide a cost-effective solution to enhance edge
stability as described within this paper.
References
British Standards Institute (2016). BS 8006-1+A1:2016:
Code of practice for strengthened/reinforced soils
and other fills, London: British Standards Institute.
British Standards Institute (2013). BS EN 1997-
1:2004+A1:2013, Eurocode 7: Geotechncial Design
– Part 1: General Rules, London: British Standards
Institute.
Building Research Establishment [BRE] (2004). BR 470:
Working platforms for tracked plant, London: BRE
Bookshop.
Construction Industry Research and Information
Figure 9: Limit equilibrium rotational failure check.
Association [CIRIA] (1996). Special Report 123: Soil
Reinforcement with geotextiles, London: Thomas
Telford.
5. Conclusions Corke, D. and Gannon, J. (2010). Economic design of
working platforms for tracked plant. Ground
The safe design of granular temporary working platforms using Engineering, 43, pp 29-31.
rational design methods has, for nearly 20 years, been routine Giffen, A.D. (2015). Design and construction of a
for piling sites. strengthened embankment for an intermodal transfer
facility. Proceedings of the XVI ECSMGE,
Although having been mandated for geotechnical design for Edinburgh, Scotland. pp. 583-588.
nearly 10 years the application of EC7 for the design of Highways England (2016). Manual of Contract
working platforms has not gained industry traction. The Documents for Highways Works [MCHW], Volume 1
BRE470 platform design approach, which has the merit of – Series 600 Earthworks, London:
simplicity, remains popular even though it may not the most Okamura, M., Takemura, J. and Kimura, T. (1998).
efficient design method when incorporating geogrid Bearing capacity predictions of sand overlying clay
reinforcement within the platform design. BRE 470 is also
based on limit equilibrium methods, Soils and
Foundations 38(1), pp. 181–194.
quite sensitive to the angle of friction used in the calculation
Palmeira, E.M. and Antunes, L.G.S. (2010) Large scale
which can be a cause of concern where either high quality
tests on geosynthetic reinforced unpaved roads
aggregate is difficult to source (increasingly problematic
subjected to surface maintenance, Geotextiles and
especially in the south east of the England) or where slurry Geomembranes, 28 (2010), pp. 547-558.
contamination can lead to a reduction in the operative angle of Smith, C.C. and Tatari, A. (2016). Limit analysis of
friction. reinforced embankments on soft soil, Geotextiles and
Geomembranes, 44 (2016), pp. 504-514.
Whilst having the downside of being a more complex
Temporary Works Forum [TWf] Working Platforms
calculation procedure the CIRIA 123 method can yield a more
(2019) Design of granular working platforms for
economic design than the BRE 470 approach. However construction plant. A guide to good practice.
uncertainty in the selection of the load spread angle b needs Transport and Road Research Laboratory [TRRL]
careful consideration. For a small working or where the (1984). Laboratory Report 1132: The Structural
subgrade is not particularly soft, the BRE approach remains the Design of Bituminous Roads. Berkshire, UK.
most used method of design. Where a weaker subgrade is Waste and Resource Action Programme [WRAP] (2010).
present or for large areas the additional complexity and design Sustainable Geosystems in Civil Engineering
costs of the CIRIA 123 approach or numerical analysis can Applications, WRAP, Banbury, UK.
yield overall cost savings.
348
Proceedings of the Institution of
Civil Engineers
Geotechnical Engineering 161
December 2008 Issue GE6
Pages 279–281
doi: 10.1680/geng.2008.161.6.279
Keywords:
design methods & aids/piles &
piling/temporary works
If a piling rig overturns there can be a risk of casualties. ground-supported working platforms constructed of granular
Working platforms are critical for plant stability, and a material, so that an acceptable level of safety is achieved. A
good practice guide to the design, installation, secondary objective of the guide is that safety should be
maintenance and repair of ground-supported working achieved without unnecessary or excessive expenditure.
platforms for tracked plant has been prepared. A
simplified approach to the design calculations has been The guide is not intended to replace or reduce the designer’s
based on a punching shear failure mechanism. The input, but rather to promote the implementation of minimum
platform design is an integrated package, from track design, installation and maintenance standards. The guidance
loading through to geotechnical design. has sought to avoid being over-prescriptive, as this might limit
the scope for innovative solutions, and does not in any way
NOTATION limit the responsibilities of those parties involved in the
cu undrained shear strength of cohesive subgrade provision and operation of a working platform, who must
D depth of platform material exercise their own knowledge, experience and judgement.
Kp tan punching shearing resistance coefficient
L effective track length of plant 2. GOOD PRACTICE GUIDANCE
Nc bearing capacity factor for cohesive subgrade Following an introductory chapter, the guide has four chapters
Nªp bearing capacity factor for granular platform that deal with, respectively, site conditions, design, installation
material and, finally, operation, maintenance and repair.
R bearing resistance
Rc bearing resistance of cohesive subgrade when no The strength of the near-surface ground is critical for the
platform is present design of the working platform, whereas for most construction
Rp bearing resistance of working platform when projects it is the strength at greater depths that is important.
platform is sufficiently deep that bearing The near-surface strength is unlikely to have been determined
resistance is unaffected by underlying cohesive in the site investigation for the construction project, and it may
subgrade be necessary to augment information obtained for the
sc , sp and sª shape factors; functions of W and L construction project with further investigation specifically for
W track width of the plant the working platform. The desk study and site inspection are
ªp bulk unit weight of platform material critically important, and should be carried out with the
9 angle of shearing resistance of granular material platform in mind; it is particularly important to locate any
weak and variable areas. Care must be taken in backfilling trial
1. INTRODUCTION pits to avoid creating additional hazards.
Working platforms are critical for plant stability, and while
most ground-supported working platforms perform well, The design of a working platform is a geotechnical design
overturning of rigs has occurred more frequently than it should. process, and should be carried out by a competent engineer
Although serious incidents involving working platforms are who has full access to the health and safety plan, including the
relatively rare, when they do occur there can be a risk of desk study and all other site investigation information. The
casualties. A good practice guide for ground-supported working quality of the granular platform material is crucial, and it
platforms for tracked plant has been prepared at the instigation should be such that all the performance requirements, in terms
of the Federation of Piling Specialists (FPS). A contract was let of compactibility, durability, trafficability and drainage, can be
by FPS to the Building Research Establishment Ltd (BRE) to met. Materials that will undergo significant crushing when
prepare the guide under the direction of a Steering Group trafficked should be avoided for works of any significant
appointed by FPS. The guide was published in June 2004. 1 duration, because drainage may be impaired. Sometimes it may
be economic to incorporate geosynthetics to strengthen the
The principal objective of the guide is to facilitate the design, working platform as an alternative to using a greater depth of
specification, installation, operation, maintenance and repair of granular material. A separating geofabric between a clay
Loaded area
W L
Platform Punch D
Subgrade
Fig. 1. Hazard posed by poorly backfilled excavations Fig. 2. Punching failure mechanism
4
There are two limiting conditions.
2 Rc ¼ cu Nc sc
2
3 Rp ¼ 0:5ªp WNªp sª
0
0 1 2 3
Equation 1 used in conjunction with the limiting values given D
in Equations 2 and 3 indicates an increase in bearing resistance W
(R) with increasing depth of the platform (D), as illustrated in
Figure 3 for some typical conditions. The graph Fig. 3. Typical increase in bearing resistance (R) with
is in the form of a dimensionless plot of bearing resistance, increasing depth of platform (D) for well compacted granular
R/(cu Nc sc ), against platform depth and loaded width (D/W). platform material on soft clay subgrade
When the platform depth D ¼ 0, the bearing resistance is a
minimum, corresponding to the subgrade alone, Rc /(cu Nc sc ) (see
Equation 2); when D is large (corresponding to a very thick appraised by an appropriately experienced engineer, and in
platform) the maximum bearing resistance is that provided by situations where the routine design calculations are not
an infinite depth of platform material, Rp /(cu Nc sc ) (see appropriate it may be necessary to carry out more sophisticated
Equation 3). For the conditions that apply in Figure 3, the forms of analysis.
latter state is reached when D/W ¼ 2.5 and Rp /(cu Nc sc ) ¼ 5.6.
Between these two limits the bearing resistance of the
combined system can be determined using Equation 1. REFERENCES
1. BUILDING RESEARCH ESTABLISHMENT. Working Platforms for
The guide recommends values for the punching shear Tracked Plant: Good Practice Guide to the Design,
coefficient, Kp tan , for a range of 9 as well as shape factors Installation, Maintenance and Repair of Ground-Supported
for this coefficient and for the subgrade bearing resistance. Working Platforms. Building Research Establishment,
Watford, 2004, BR470.
A simple addition to the capacity of the platform is suggested 2. MEYERHOF G. G. The bearing capacity of foundations under
to take account of the effect of geosynthetic reinforcement. eccentric and inclined loads. Proceedings of 3rd
International Conference on Soil Mechanics and Foundation
This approach to the calculation of the required depth of the Engineering, Zurich, 1953, 1, 440–445.
working platform contains many simplifying assumptions, 3. FOUNDOUKOS M. and JARDINE R. J. The effect of eccentric
which cannot fully represent actual soil behaviour. The method loading on the bearing capacity of shallow foundations.
described in the guide has been calibrated against other design Proceedings of BGA International Conference on
methods for strip loadings and the experience of FPS members. Foundations: Innovations, Observations, Design and
However, the results of calculations should be critically Practice, Dundee, 2003, pp. 297–305.
REFERENCES Watts K. & Jenner C.G. (2008) Large scale Laboratory Assess-
ment of Geogrids to reinforced Granular Working platforms, proc
4th European Geosysnthetics Conf. Edinburgh 2008.
European Technical Approval ETA12/0530, Report number KI-
BR470- Working platforms for tracked plant, 2004 WA K76041 issued by Kiwa Nederland B.V.
Use of ‘structural geosynthetic reinforcement’– A BRE review Tensar Case Study reference-Ref 319 for Stoke
seven years on, BRE2011 Quay_Ipswich_Piling_Platform
Jenner C.G.,Watts, G.R.A, Blackman and The performance of re- Tensar Case Study reference Ref 344 for Crossrail Working Plat-
inforced unpaved sub-bases subjected to trafficking form.
1401