Professional Documents
Culture Documents
Catenary System Techniques and Standarts
Catenary System Techniques and Standarts
5, SEPTEMBER/OCTOBER 1971
Abstract-British and Western European experience, design tion and radio interference experience and suppression
standards, and techniques associated with electrified railway power techniques; and construction time and cost breakdown
supply facilities are outlined. Aspects surveyed include utility
supply to commercial frequency railway loads, substation design data.
standards, catenary system design and maintenance, telecommunica- The techniques presented are confined to those which
tion and radio interference experience and suppression techniques, are believed adaptable for use on railroad supply systems
costs, and construction time. This survey outlines information operated at 25-kV commercial frequency. Basic data and
obtained during 1967 visits with state railway, power system, and experience on the French and British 25-kV 50-Hz and the
manufacturing company engineers in Great Britain, France, Ger- German and Swedish 15-16kV 162/3-Hz systems are
many, and Sweden. The survey confines itself to experiences and
data which are believed applicable to commercial frequency (60- outlined. Since it is believed that most future United
Hz) 25-kV electrification. A substantial part of the European railway States electrifications will be on single or double track
catenary system and railway substation technology and experience lines, catenary designs outlined are those applicable to
outlined in the survey appears applicable to future American railway single or double track iinstallations only.
electrifications. The basic information presented in this paper was
obtained from: 1) discussions with engineers responsible
INTRODUCTION for the electrification planning, substations, and catenary
IN THE LAST 20 years the mileage of electrically systems of the British, French, German, and Swedish
operated railways has increased threefold with the State Railway Systems; 2) discussions with the Central
majority of this increase occurring in Europe, the USSR, Electricity Generating Board-British State Power Sys-
Japan, India, and South Africa. Planned increases should tem-(CEGB) and Electricity de France-French State
raise world mileage from today's 57 000 to approximately Power System (EDF) planning engineers responsible
100 000 route mi by 1975. Increased interest in future for service to 50-Hz single-phase railway loads; 3) dis-
United States railroad electrification is evidenced by the cussions with engineers of British, German, French,
Edison Electric Institute's establishment of an Electri- Swedish, and Swiss manufacturers engaged in the supply
fication Committee, the joint utility-railroad electrification and erection of equipment used in ac electrification; and
study of the New York Central's New York-Cleveland 4) various technical papers, specifications, and booklets
Line, the construction of the commercial frequency furnished by the previously listed engineers.
(60 Hz)- 25-kV Muskingum Electric Railroad by the
American Electric' Power System, and preliminary UTILITY SUPPLY TO 50-Hz LOADS
electrification studies by railroads and power companies Great Britain (CEGB)
in the western United States. 1) The railway is not allowed to operate 25-kV system
Because of the extensive mileages electrified since 1955 in parallel with power transmission system.
at commercial frequency (50 to 60 Hz), a major portion of 2) Specify the phase to which the substations will be
the recent advances in railway electrification engineering connected in order to-obtain maximum load balance.
and construction techniques has been related to Western 3) Maximum allowed unbalance between phase voltages
European and British electrification work. This paper is 5 percent.
presents a survey of Western European-British practice 4) One would not consider overbuilding catenary with
in: utility supply of railway loads at commercial fre- transmission lines because of a) effects on railway for
quency; railway supply substation design and facilities; conductor or insulator failure and b) difficulty of main-
catenary system design and maintenance; telecommunica- taining transmission lines.
5) Have a computer program which includes negative
Paper 71 TP 42-IGA, approved by the Land Transportation sequence system representation for the study of railway
Committee of the IEEE IGA Group for presentation at the 1968
IEEE-ASME Joint Railroad Conference, Chicago, Ill., March loads.
27-28. Manuscript received June 11, 1971. 6) Railway ra-te bills on simultaneous peak demand in
The author is with American Electric Power Service Corporation,
New York, N. Y. 10008. mW rather than on individual station peaks (also MWh).
ROSS: RAILWAY SIJBSTATIONS AND CATENARY SYSTEMS 667
7) No harmonic problems on power system have been system can tolerate the unbalance and that no power
encountered. There could be a problem where extensive system angle problem exists.
cable systems are served at the same point as railway load. 2) Voltage unbalance should not be allowed to exceed 5
8) Locomotives are not built to feed power back into percent. M\Iotor damage is not immediate and will not
the power system when coasting or slowing down (no be evident until motors in a given area begin to fail at, say,
back-feed). 20 years instead of 30.
9) Most railway supply points have a three-phase fault
of approximately 3000 MVA. SUBSTATIONS
10) Railway load has odd harmonic content which In Great Britain CEGB owns 132-kV bus, 132/25-kV
approximates 1/N relationship, (i.e., fundamental 100 A, transformer, and transformer 25-kV oil circuit breaker
third 33 A, fifth 20 A, etc.). This is based on several tests (OCB). In France Societe National des Chemins de Fer
that have been carried out. Frangais-French State Railways (SNCF) owns the entire
11) Railway load power factor is 0.88. station. Figs. 1 and 2 illustrate typical stations.
12) Railway loads are served at 132 kV except for a
few 66-kV buses in the London area which have a high High Side Switching
short-circuit MVA. There will be two 275/25-kV stations 1) Great Britain: Usually try to serve railway load from
if electrification is extended from Liverpool to Scotland. existing station bus. If not, manual switching is adequate
because railway is designed to operate with one station
France (EDF) out of service. Transformers have high side motor
1) Railway substations are operated in parallel with operated air break (MOAB) switch.
EDF whenever possible. 2) France: Same as Great Britain except transformers
2) While nearly all stations have voltage unbalance of have high side circuit breakers. Railway does not de-
less than 5 percent, this is not the maximum tolerable pend on power system to protect transformer. Catenary
limit. During outages of power system facilities or short system is designed to allow trains to operate with station
duration peak load periods, unbalances of as high as out of service.
10 percent may be accepted.
3) Do not specify phase to which railway will connect Transformers
when installing new substations. 1) Great Brttain: Most transformers are installed two
4) Where possibility of 25-kV catenary system flow- to a substation. Do not use Scott connected transformers,
through between substations exists because of trans- load tap-changing (LTC) transformers, or station 25-kV
mission system angle relationship, railway either changes regulators. Railway transformer is subjected to far more
phases or installs relaying to trip station if back-feed frequent short circuits than a power system transformer.
occurs. It is protected by 4-cycle circuit breakers. To quote one
5) Miany stations are supplied at 63 kV in some cases British engineer "the transformer must be mechanically
from buses having three-phase faults of less than 500 strong and able to stand endless short circuits of 10 to 15-
MVA. cycle duration. The only comparable duty I know of is
6) Do not believe that the brief periods of railway peakarc furnace supply." The transformers used have spe-
demand, which are of 5- to 10-min duration and occur cially braced windings. The railway frequently places up to
only a few times each day, will do damage to any equip- 50-percent overloads on the transformer but these are
ment of either EDF or other customers. This is partic- usually of short duration. Transformers have fixed taps
ularly true on lines where the service is mostly freight. 15 percent in 2.5-percent steps.
7) Tests show parallel operation usually reduces voltage 2) France: a) The two sizes in use today are 10 and 15
unbalance. MVA. b) Impedance is 8 or 9 percent. c) Overload ca-
8) There have been voltage dip problems where heavily pability is 50 percent for 15 min; 100 percent for 5 min.
loaded freight trains, which are taking full power on d) Fixed taps 4 5 percent in 2.5-percent steps. e) Use a
grades or while accelerating, cross the isolating section 25-kV voltage regulator where required. 4800 V (± 2400
between substations not in parallel. This is another V) in 16 steps of 300 V. Steps of greater than 300 V produce
reason the French favor parallel operation. surges which might damage the locomotives. f) The 15-
9) The railway favors parallel operation because it MVA transformer weighs about 25 tons and is designed
reduces catenary currents and voltage drops and permits to be moved by motor truck. Every station has two
stations to be spaced farther apart. transformers. g) The railway does not maintain spare
transformers. h) Because of the large number of faults,
Societyfor the Electrification of Railway at 50Hz "the transformers should be of robust design" to quote the
1) Substations generally should not be operated in Chief Engineer of substations of SNCF. Fault rate may
parallel on 25-kV side. Adjacent stations on a severe be as high as 1000 faults per year in a 10- to 15-km catenary
grade might be paralleled if analysis shows that the power section. The 25-kY breakers reclose automatically after
668 IEEE TRANSACTIONS ON INDUSTRY AND GENERAL APPLICATIONS, SEPTEMBER/OCTOBER 1971
INCOMMING LINES OF
ELECTRICITY DE FRANCE
(66KV, 154KV OR 220KV)
INCOMMING LEGEND
HIGH VOLTAGE
LINES (D
( SECTIONALIZiNG SWITCH
132 KV
132KV
MOTOR OPERATED
®AIR BRAKE
132/25 KV SWITCHES
TRANSFORMER fM0l
TRANSFORMER
m 25KV OIL
WI -CIRCUIT BREAKER
IF 25KV TIE TO
RAILWAY SUPPLY CENTRAL ELECTRICITY
Blair A. Ross (M'57-SM'59), for a photograph and biography please see p. 665 of this issue.