Professional Documents
Culture Documents
Critical Path Analysis
Critical Path Analysis
Critical Path Analysis involves using a network diagram to manage the various tasks required to
complete a project. The use of Critical Path Analysis can help a manager to complete a project in the
shortest space of time possible and identify critical activities.
EST Activity
5 C
1
2
7 6
LFT
Each circle (node) is numbered and represents the start and end of an activity.
A straight line represents the activity. Activity number above the line, duration below the line, for
example, 8 weeks.
The earliest start time (EST) of an activity is shown in the top right of the left-side node; for example,
activity C EST is week 5.
The latest finish time (LFT) of an activity is shown in the bottom right of the left-side node.
The critical path is the route through the network diagram where there is no float time. These
activities are critical because, if they overrun, the expected duration of the project will be extended.
Identifying the float time on activities and the critical path is the last stage of completing network
analysis.
• Carrying out network analysis can help managers to identify key activities, improve
efficiency and manage resources effectively. .
Now try this
1. What are the EST and LFT on a network diagram?
2. What is the ‘float’ on an activity?
3. What is meant by the ‘critical path’?
Example of a completed Critical Path Analysis diagram
Use the notes below to interpret the information shown in this network diagram.
The benefits of Critical Path Analysis
• Projects and strategies often involve multiple factors, agents and stakeholders – calculating
the time taken to complete an activity can be very difficult.
• It does not take into account qualitative issues such as employees morale or relationships
between workers.
• It does not take into account qualitative issues such as employee morale or relationships
between workers.
• It relies on estimations. If these are correct so are the ESTs and LFTs. Strategies will not be
implemented on time if this is incorrect.
• It does not take into account unexpected events and significant external factors beyond the
business’s control, such as key staff on long term absence.