TUNNEL PROJECTS IN OMAN:

LATEST TECHNOLOGIES AND


CONSTRUCTION TECHNIQUES

Copyright © 2015 IQPC Middle East. All rights reserved.


WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 1
Produced by IQPC Middle East in association with the Bridges and Highways Oman event taking place in September 2015 in Muscat, Oman.
Oman’s infrastructure is on the verge in order to successfully negotiate
of a huge expansion, with numerous the difficult terrain over the projected
road projects, bridge structures, course of construction.
tunnel constructions and national
railway networks being developed When the Ministry of Transport and
over the next 5 years. This is an Communications (MoTC) opened
essential part of the 9th five year a $1 billion tender for the pre-
plan of the Supreme Council for qualification for the construction
Planning (SPC) which has a long- work in August 2013, there were
term strategic focus on diversifying 33 construction and engineering
sources of national economy in order companies – mostly of an
to improve the welfare of Oman’s international background – who
citizens, increase their social benefits applied.1
and enhance the contribution of
private sector to the country’s GPD. Oman: High Speed Railway
Segment 1
Among the Omani To that end, tens of billions of dollars
are being invested in ambitious The Oman Railway Company (ORC)
Government’s infrastructure projects that will forge has selected a consortium of 18
key transport greater trade and transport links companies to design and build the
first segment of its proposed high
infrastructure between the various cities of the
speed rail network that will connect
Sultanate as well as its neighbouring
expansion goals countries in the GCC. As the scale the Sultanate’s port cities of Sohar,
is the construction of these infrastructure projects Duqm and Salalah with each other
increases, so do the challenges and as well as crossing borders to
of strategic linking complexities associated with their connect to other GCC countries.
roads between the construction. Ultimately, the entire network is
envisaged to span 2,135 km with the
various wilayats Cost-effective tunnelling represents appropriate supporting infrastructure
(provinces) a significant piece of the transport to allow high speed trains to travel
network puzzle as the mountainous
throughout the terrain of Oman and the varying soil
along it at speeds of up to 350 kmph
for passenger travel and 200 kmph
Sultanate in consistency of its coastal regions for freight transport.2
order to stimulate present significant challenges that
Segment 1 of the HSR will include
need to be overcome with cutting-
interprovincial trade edge technology and advanced 10 separate tunnels that make
and traffic. construction techniques. up 4.7km in total, including two
1.57km tunnels.3 The second tender
Tunnel Projects submitted by the ORC is for the
complex series of civil construction
Underway in Oman works covering the tunnels
themselves along with earthworks,
Musandam, Oman: Diba- bridges, structure track works,
Lima-Khasab road project stations and depots. The budget for
the entire ORC project is $15 billion
Among the Omani Government’s key
and segment 1 is expected to be
transport infrastructure expansion
completed sometime in 2018.4
goals is the construction of strategic
linking roads between the various
wilayats (provinces) throughout 1Construction Week Online, Atkins faces competition
for Omani road project, 17/11/2014
the Sultanate in order to stimulate 2 Oman Projects, Oman National Railway Project,
interprovincial trade and traffic. 24/05/2015
3 Tunnel Builder, Oman National High Speed Railway,

The Diba-Lima-Khasab road project 18/01/2015


4 Railway Technology, October’s top stories: Oman’s
is of particular note as part of this $15 billion rail network, 01/11/2013
strategy not only for its length
but primarily for the associated
challenges in its construction. The
65km coastal road will require no
fewer than 7 tunnels and 18 bridges

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 2


“Historically, the
Middle East hasn’t
had a lot of tunnelling
work other than a few
major highway cut-
and-cover tunnels
and small-diameter
Tunnel Boring Machines pipe jacking. But
(TBMs), Earth Pressure in the last six
Balance Machines (EPBs) years, starting with
and Slurry Machines the Dubai Metro
“Slurry machines are typical soft- and followed by
ground TBMs used for tunnelling in Abu Dhabi’s deep
highly permeable, unstable ground
or beneath buildings sensitive to sewerage tunnels,
New Technologies ground disturbances.” this has changed and
and Construction “[EPB machines] are typically is set to drastically
Techniques used in soft ground with cohesive increase in the
or even incohesive soils, where
“Historically, the Middle East hasn’t there is high clay content and low future.”
had a lot of tunnelling work other water permeability. Where shield Paul Groves, the UAE-based
than a few major highway cut-and- excavation is carried out in unstable Head of UK Consultant Atkins’
cover tunnels and small-diameter soils, a loss of stability of the tunnel Tunnelling Network Group.
pipe jacking. But in the last six face is prevented by creating a
years, starting with the Dubai Metro support pressure, known as the earth
and followed by Abu Dhabi’s deep pressure balance shield.” – Hubert
sewerage tunnels, this has changed Lang, Herrenknecht Chairman
and is set to drastically increase in Advisor
the future.” – Paul Groves, the UAE-
based Head of UK Consultant Atkins’ TBMs, often referred to as ‘moles’,
Tunnelling Network Group. come in a variety of forms depending
on the type of tunnel that needs to
Today, there are more ways of be cut. Their cutter head array at the
creating tunnels than ever. As face is followed by its supporting
infrastructure in the Middle East infrastructure along the body, which
becomes increasingly sophisticated can be as long as 150 metres. They
with ambitious road, rail and metro are capable of boring through most
networks envisaged by various conditions, from soft, waterlogged
Middle Eastern governments and ground to hard rock. In the Gulf’s
transport authorities, modern coastal areas such as Oman, soft
methods are becoming increasingly ground TBMs and slurry machines
attractive due to their ability to solve are employed to excellent effect
complex terrain-based challenges where groundwater penetration is
and ensure a robust, durable build. expected to be an issue as they bore

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 3


through the soft or mixed condition delay. However recent tunnelling
“[EPB machines] rock and then treat and pump the projects call for very large cross-
slurry out of the tunnel.5 sectional areas at shallow depth
are typically used which means that the cut-and-cover
in soft ground with Due to the instability of the soil method has needed to evolve. This
and rock in many Oman coastal
cohesive or even areas, tunnels in progress need
is where the top-down approach
comes in.
incohesive soils, to be supported by vast shields to
where there is high protect the face of the excavation On the Dubai Metro project, for
from collapse while the tunnel lining example, a top-down approach to
clay content and low is being constructed inside the building the cut-and-cover tunnels
water permeability. bore. Propping up tunnels is not was used for sections with depths
a new principle and dates back to of up to 27 metres below ground
Where shield the 15th Century but the size and level. Permanent diaphragm walls
excavation is carried sophistication of tunnel shielding were installed before excavation
out in unstable soils, has increased exponentially as the commenced down to tunnel roof slab
use of cutting-edge EPB machines level using a temporary strut restraint
a loss of stability of demonstrates. Sequential use of to stop the face and walls from
the tunnel face is concrete lining in concert with the falling in.6 After this, the roof slab
use of EPBs protects the tunnel was cast before the lower part of the
prevented by creating and its workers from sagging or excavation was dug out beneath it to
a support pressure, collapse, avoiding costly delays and base slab level. This approach will be
known as the earth dangerous working conditions. employed at a number of tunnels in
the ORC high speed railway network.
pressure balance The latest TBMs and their supporting
infrastructure can achieve a tunnel- Microtunnelling
shield.” laying rate of 30 metre per day.
Hubert Lang, Herrenknecht
“Microtunnelling is really anything
Chairman Advisor
Top-Down Cut-and-Cover under 3 metres in diameter, the
Approach main difference between this
and larger tunnelling is that the
“The advantage is that in some operator operates it from the top.
circumstances, the top-down The machine is pushed through the
approach can offer simpler ground, followed by the pipe, and
construction sequencing operations the only time anyone goes into the
and the early slab casting gives tunnel is for a physical inspection.” –
stiff lateral restraint, which can Mamdouh Nasr, Middle East Director
be preferable to using temporary at Swiss Contractor Company
struts or anchors. This is a great -Implenia
benefit when faced with looking after
sensitive buildings and structures,” While the tunnels involved in the
– Paul Groves, the UAE-based Head current projects to expand Oman’s
of UK Consultant Atkins’ Tunnelling transport infrastructure are among
Network Group
5MEED, Tunnelling Techniques, 29/04/2012
6Parsons, Dubai Metro
The simple cut-and-cover approach
has been put to good use in the
Middle East for the last 30 years
and is often the most appropriate
methodology for creating durable
tunnels without undue expense or

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 4


“Microtunnelling is
really anything under
3 metres in diameter,
the main difference
the biggest and longest in the Breaking Through with
country, an equally important between this and
innovation is the improvement the Latest Tools and
larger tunnelling is
of microtunnelling techniques in Techniques
support of these grand designs. that the operator
The governments and transport
Microtunnels are essentially classed
authorities in the Middle East
operates it from the
as utility tunnels that are 3 metres
or less in diameter. They are have been quick to realise the top. The machine is
designed to quickly and efficiently benefits of introducing cutting- pushed through the
install pipelines for the use of waste edge construction technologies
treatment, power cabling and all and methodologies. Oman is no ground, followed
manner of utility purposes. exception as the scale of its projects by the pipe, and the
and inherently complex terrain call
Unlike traditional open-shield pipe- for a more sophisticated approach
only time anyone
jacking, the modern microtunnelling in order to ensure that the proposed goes into the tunnel
process is entirely remote-controlled infrastructure projects are completed is for a physical
and guided, meaning that hydraulic promptly and safely.
jacks push micro-boring machines inspection.”
into the earth and the pipe follows The tunnels currently being planned Mamdouh Nasr, Middle East
once the drive section is completed. and constructed are an essential Director at Swiss Contractor
Human operators only enter the element of the national road and Company -Implenia
tunnel for physical inspection, rail network expansions that have
guiding the process from above been devised by the Ministry of
ground by utilising advanced control Transport and Communications.
consoles.7 Tenders issued by the MoTC have
already drawn the attention of
leading national and international
engineering and construction
companies, who are eager to
demonstrate the effectiveness
of their technological approach.
Successful completion of these
projects will no doubt lead to further
expansion and refinement of the
Sultanate’s transport infrastructure
as Oman keeps pace with the rest of
the Middle East.

7 Construction Week Online, Eng. Essa Al Maidoor


explains microtunnelling, 31/08/2014

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 5


Sources:
http://www.constructionweekonline.com/article-30163-atkins-faces-
competition-for-omani-road-project/

http://www.muscatdaily.com/Archive/Business/PMC-tender-floated-for-
Musandam-road-project-362a

http://tunnelbuilder.com/Archive/Projects/Oman.aspx

http://www.omanprojects.com/Member/MoreInfo.asp?LoginId=77&LoginNam
e=osco&ProjectId=93288

http://omanobserver.om/major-viaducts-tunnels-to-drive-up-cost-of-oman-
rails-segment-1/

http://www.railway-technology.com/features/feature-octobers-top-stories-
oman-rail-network-marmaray-tunnel-opens/

http://www.constructionweekonline.com/article-29790-eng-essa-al-maidoor-
explains-microtunnelling/

http://www.meed.com/tunnelling-techniques/3134511.article

http://www.parsons.com/projects/Pages/dubai-metro.aspx

http://www.timesofoman.com/News/48384/Article-Diversification-is-long-term-
strategic-plan-of-Omans-ninth-five-year-plan

http://www.constructionweekonline.com/article-26617-tender-for-key-1bn-
oman-road-expected-by-april/

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 6


Join the leading project owners, contractors, consultants, equipment suppliers and technology
providers from 13-15 September 2015 at the Crowne Plaza Muscat, Oman, and discuss
upcoming projects in Oman, strategies for bridge and highway project planning and best practices
for design and construction of transport infrastructure.
For more information or to register visit www.bridgeshighwaysoman.com or contact us at
enquiry@iqpc.ae / +971 4 364 2975.

Copyright © 2015 IQPC Middle East. All rights reserved.

This document may not be copied, published, or distributed, in whole or in part, or modified in any way, including by removing the copyright notice
or references to IQPC Middle East, without the written permission of the copyright owners. This document and the information contained herein is
provided on an “AS IS” basis and IQPC Middle East disclaims all warranties, expressed or implied, including but not limited to any warranty that the
use of the information herein will not infringe any ownership rights or any implied warranties of merchantability or fitness for a particular purpose.

Publisher contact details: Shrutika Shetty | IQPC Middle East | enquiry@iqpc.ae

WWW.BRIDGESHIGHWAYSOMAN.COM TUNNEL PROJECTS IN OMAN: LATEST TECHNOLOGIES AND CONSTRUCTION TECHNIQUES 7