Gender Study Timeline

SL. Tasks Key role of Consulting Key role of CARE Timeline of Task Completion
Firm
01. ToR Development Ashrafiz & Faisal November 14, 2023
02. PR raise in PS Parvin November 15, 2023
03. PR Approval Zubaid & Marc November 19, 2023
04. Solicit RFQ to Limited vendor Procurement Unit November 21, 2023
05. Proposal receives and forward to Procurement Unit December 10, 2023
Program for Technical Evaluation
06. Technical Evaluation Sazzad- assigned December 14, 2023
Program staff & other
units
07. SBA Signing & Draft PO share with Selected Firm Procurement Unit December 19, 2023
selected vendor & PO Issue
08. Contract agreed and signed by both Selected Firm Procurement Unit December 21, 2023
parties
SHOUHARDO III Plus
team will update
The consultant will
09. Kick Off Meeting about the status of the 1-2 Week of January 2024
reconfirm the study tool
study and handover
the final study tool
SHOUHARDO III Plus
Consultants will arrange Technical team will
the training of the join the session to
10. Enumerators Training Week 3 of January 2024
enumerators on data provide their feedback
acquisition for updating the
enumerators.
11. Field data collection The consultant(s) will SHOUHARDO III Plus Week 4-5 of January 2024
conduct the survey using Technical team will
digital methods randomly visit the field
(KOBO/ODK), deploying team and will cross-
the team in the field. They check the data quality
will maintain the data assessment plan
quality assessment plan prepared by the
and accuracy. consultant(s).
Consultant(s) will prepare
the transcripts and share SHOUHARDO III Plus
12. Data Cleaning and analysis them with CARE. Also, Technical team will Week 1-2 of February 2024
share the data analysis review the dataset
plan.
SHOU III Plus Technical
Draft Report and Feeback on the Draft The consultant(s) will team will review the
13. Week 3-4 of February 2024
Report prepare the Draft Report. Draft Report and
provide feedback on it.
SHOU III Plus Technical
Draft Report and Feeback on the Draft The consultant(s) will team will review the
14. Week 5 of February 2024
Report prepare the Draft Report. Draft Report and
provide feedback on it.