Professional Documents
Culture Documents
Unit Estimate Road Cutting
Unit Estimate Road Cutting
Unit Estimate Road Cutting
2 3.60 7.20
3 3.00 9.00
2x2 2.25 9.00
1 2.25 2.25
2 1.12 2.24
Apron 1 20.10 20.10
49.79 Rm 36.37 1810.86
16 1202 25 mm thick 1:2:4 plain
cement concrete floor with cement
coarse sand and 20 mm gauge
stone ballast laid in pannels
finished with 3 mm floating coat
of neat cement or cement and
marble dust in ratio 1:5 as
specified and removing any
overlaping or mortar at the joints of
panels if any and giving them
uniform finish including.
ASSISTANT ENGINEER
UNIT ESTIMATE OF BYEPASS CHAMBER
Sl.
Ref. Description Qty. Unit Rate Amount
No.
1 2 3 4 5 6
1- 1001 Excavation in foundation in ordinary soil (loam,
clay or sand) including lift upto 1.50m and lead
upto 50m and refilling, watering, ramming of
excavated earth into the space betwwen the
building and sides of foundation trenches or
into the plinth and disposal of surplus earth
upto the distance of 50m from the center of
the foundation trenches. 0.66 Cum 174.35 115.07
2- 1031 Ist. Class brick work in 1:4 cement and
Coarse sand in foundation and plinth
including supply of all material, labour T &
P etc. required for proper completion of
work.
1.36 Cum 6605.17 8983.03
3 1017 Concrete with 40mm gauge Stone ballast,
coarse sand and cement in proportion of 8:4:1
in foundation and floors including supply of all
materials, labour, T&P etc. required for proper
completion of the work. 0.17 Cum 7091.39 1205.54
4- MR Supply cutting and dressing with size
and fixing V-Notch of size 90 x90 cm in
the by pass chamber including
prepration of by pass chamber as per
direction of E/I including supply of all
material, labour T & P etc. required for 1 each 7000.00 4537.20
proper completion of work.
ASSISATANT ENGINEER
UNIT ESTIMATE OF BOUNDARY WALL
(AS PER TYPE DESIGN FOR 10 M LENGTH)
S.N. SOR SCHEDULE ITEM NO. No. L B H QTY. UNIT RATE Amount
Ref.
1 1001 Excavation in foundation in ordinary
soil (loam,clay or sand) including
lift up to 1.50 m& lead up to 50
m,refilling,watering and ramming of
evcavated earth into the trenches or
space betwwen the building and
sides of foundation trenches or into the
plinth and disposal of surplus earth
up to the distance of 50 mfrom the
center of the foundation trenches.
ASSISTANT ENGINEER
UNIT ESTIMATE OF 3.60 M WIDE AND 1.2 M WICKET GATE WITH PILLARS
S.N. Ref. SCHEDULE ITEM NO. No. L B H QTY. UNIT RATE AMOUNT
1 1001 Excavation in foundation in ordinary
soil (loam, clay or sand) including lift
up to 1.50 m& lead up to 50m,
refilling, watering and ramming of
evcavated earth into the trenches
or space betwwen the building and
sides of foundation trenches or into
the plinth and disposal of surplus
earth up to the distance of 50
mfrom the center of the foundation
trenches.
8 Analysis 1.2 M Wicket Gate as per type Design. 1 job 16100.00 16100.00
2 3.60 7.20
2 1.20 2.40
9.60 Sqm 160.17 1537.63
12 MR Finishing walls with water proof
cement paint of approved make and
quality on new work with two
coats to give an even shade
including supply of all material,
labour T & P etc. required for
proper completion of work.
ASSISTANT ENGINEER
UNIT ESTIMATE OF 1.20M WICKET GATE WITH PILLARS
ASSISTANT ENGINEER
UNIT ESTIMATE OF SINGLE ROOM STAFF QUARTER
Sl.N Ref.
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
1 1001 Excavation of earth in ordinary soil (loam clay or and)
including lift upto 1.5 m and lead upto 50 m.filling,
watering and ramming of excavated earth in between the
building and sides of the foundation trenches or into the
plinth and disposal of surplus earth upto a distance of 50
m from the center of the foundation trenches. 29.14 m³ 174.35 5080.56
2 1011 Concrete with 40 mm gauge Ist class brick ballast,local
sand and cement in proportion (8:4:1) in foundation
including supply of all materials, labour,T&P etc required
for proper compltion of work. 4.17 m³ 5221.10 21771.99
3 1029 Ist class brick work in 1:6 cement and local sand mortar in
labour,T&P etc required for proper compltion of work. 26.17 m³ 5966.03 156131.01
4 1054 20 mm thick D.P.C. With cement and approved coarse
labour, T&P etc required for proper compltion of work. 9.46 m² 282.78 2675.10
5 1029+ Same as item no 3 but in super structure for wall up to 1
1035 brick thick) 25.43 m³ 6284.32 159810.26
6 1149 Mild steel of iron work of small sizes and sections for
chaukhats of doors such as holding down bolts, hold fast ,
teeroads, clamps grating etc. ( when not included in and
over all rate) wrought to required form including supply of
steel bolts, nut and their fixing required for proper
completion of the work. 6.25 Qtls 8155.08 50969.25
7 1069 Supply and fixing of plywood doors and shutters. 14.85 m2 7173.11 106520.68
8 1019 R.C.C. Work cement,coarse sand and 20 mm gauge
approved stone ballast in proper ratio of 1:1.5:3 excluding
supply of reinforcement and it bending but including its
fixing and binding the same with 0.5 mm thick binding wire
(to be supply by the contractor) centering nd shuttering
supply of all materials, labour,T&P etc required for proper
compltion of work. 6.59 m³ 10112.66 66642.43
9 1151 Mild steel or Iron work in plain work such as R.C.C. Work
wrough to required shape as necessary including its
bending and supply of steel,wastage, over lapping and
hooks etc complete required for proper completion of
work. 5.16 Qtls 10900.46 56246.37
10 1190 12 mm thick plaster with cement local sand mortar in 1:6
(over brick work with 3 mm floating coat of neat cement
including supply of all materials, labour,T&P etc required
for proper compltion of work. From GL upto supper
structure. 294.95 m² 157.31 46398.58
11 1188 + Same as above but in proprtion 1:4 with cement and fine
1191 sand mortar on ceiling 35.05 m² 222.75 7807.39
Sl.N Ref.
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
12 1202 25 mm thick 1:2:4 plain cement concrete floor with
part of cemnet,4 part of local sand and 8 part ist class brick
supply of all materials, labour, T&P etc complete. 7.50 Rm 1371.13 10283.48
SUB TOTAL 790842.87
19 LS Electrification work complete. 5% of sub total 39542.14
20 LS Sanitation work Water supply work complete. 10% of sub total 79084.29
1 2 3 4 5 6
Assistant Engineer
UNIT ESTIMATE OF NALLA/CULVERT CROSSING UPTO AV. 200MM DIA PIPE CROSSING
(FOR 3.0 M LENGTH)
ASSISTANT ENGINEER
UNIT ESTIMATE OF NALLA/ROAD CROSSING UPTO AV. 100MM DIA PIPE CROSSING
(FOR 3.00 M LENGTH)
1 2 3 4 5 6 7 8 9 10 11
Supply of 200mm dia DI K-7 pipe for encasing.
1 UPJN 1 3.00 3.00 m 1724.00 5172.00
ASSISTANT ENGINEER
UNIT ESTIMATE OF CROSSING OF CULVERT AND ROAD DRAIN
(0.50M TO 1.50M) WIDTH FOR ONE No.
Sl.
Description Qty. Unit Rate Amount
No.
1 2 3 4 5 6
1 Dismantling of some portion of
culvert/drain and laying of pipeline and
again reconstruction of some portion of
culvert/drain including supply of all
materials labour T&P etc. complete.
(a) Materials
i Materials for both side as 1st class brick,
cement and sand. Job L.S. 6000.00
(b) Labour
i Mistri 1 No. 520.00 520.00
ii Labour 3 No. 400.00 1200.00
iii T&P etc. Job L.S. 1000.00
TOTAL 8720.00
Add 10% C.P. 872.00
TOTAL Rs. 9592.00
Say 9595.00
Assistant Engineer
UNIT ESTIMATE OF CROSSING OF CULVERT
(FOR 3.5 M WIDE)
Sl.N
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
1 Excavation for pipe line in ordinary soil (loam clay or and)
including lift upto 1.5 m and lead upto 50 m.filling, watering
and ramming of excavated earth in between the building and
sides of the foundation trenches or into the plinth and
disposal of surplus earth upto a distance of 50 m. 2.30 cum 215.63 495.95
2 Supply of 150mm dia DI K-7 pipe for encasing. 5.50 m 1639.00 9014.50
Assistant Engineer
UNIT ESTIMATE OF CROSSING OF ROAD
(FOR 3.5 M WIDE)
Sl.N
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
Dismantling and Reinstatement of bituminous road surface.
1
2.63 sqm 1541.38 4053.8294
2 Excavation for pipe line in ordinary soil (loam clay or and)
including lift upto 1.5 m and lead upto 50 m.filling, watering
and ramming of excavated earth in between the building and
sides of the foundation trenches or into the plinth and
disposal of surplus earth upto a distance of 50 m. 4.74 cum 215.63 1022.09
3 Supply of 150mm dia DI K-7 pipe for encasing. 5.50 m 1639.00 9014.50
4 Supply of 150mm dia DI K-7 specials conforming to relevant
ISS suitable for above DI K-7 pipes F.O.R. destination 10% of item no. 2 901.45
including all taxes and insurance.
4 Carting from the store (up to 8 kms) the 150mm dia DI pipe
and specials to the site of work lowering them into trenches
and laying true to alignment and gradient including the
supply of jointing materials such as nut & bolts, rubber
insertion, white lead etc. complete but excluding cost of
trenching and cutting of pipes etc. for making of lengths but
including making joints. 5.50 m 58.56 322.08
5 Insertion of distribution pipe into the encasing pipe including
supply of T&P. 6.50 m 200.00 1300.00
6 Provision for baricating etc. 10.00 m 100.00 1000.00
7 Labour for traffic diversion. 2.00 no. 400.00 800.00
Total 18413.95
Say 18420.00
Assistant Engineer
UNIT ESTIMATE OF CROSSING OF ROAD
(FOR 7.0 M WIDE)
Sl.N
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
1 Dismantling and Reinstatement of bituminous road
surface.
5.60 sqm 1541.38 8631.728
2 Excavation for pipe line in ordinary soil (loam clay or
and) including lift upto 1.5 m and lead upto 50
m.filling, watering and ramming of excavated earth
in between the building and sides of the foundation
trenches or into the plinth and disposal of surplus
earth upto a distance of 50 m.
Assistant Engineer
ABSTRACT OF COST RECHARGING WORK
ASSISATANT ENGINEER
FOR UNIT ESTIMATE & DRAIN PER/METER WITH LEVELLING AND DRESSING OF WATER
WORKS COMPOUND FOR
RAIN WATER HARVESTING
ABSTRACT OF COST
ASSISATANT ENGINEER
COST OF SETTLING TANK WATER STORAGE TANK
ABSTRACT OF COST
Sl.
No. Description Qty. Unit Rate Amount
1 2001 Earth work in excavation of earth and
out at same for construction settling
tank. Upto 1.50 M depth.
33.06 Cum 215.73 7132.03
3002 1.50 M to 3.00 M depth 33.06 Cum 285.96 9453.84
4 1188 Plaster work 12mm thick in 1:4
cement mortar with cement and
coarse sand mortar. 63.69 Sqm. 199.98 12736.73
5 1149 MS work slab of settling tank. 290.00 Kg 81.55 23649.73
6 1024 R.C.C. work in 1:1.5:3 with cement
coarse sand and 20mm stone ballast
complete work with supply of all
materials placing of steel and
concrete etc. all complete. 2.23 Cum 12059.33 26892.31
7 MR Construction of fabricated MS
Manhole cover HD 20 with angle iron
and shutter with locking arrangement
and strainer in wall for water storage. 1.00 Job L.S. 3500.00
8 MR Fixing of angle iron footrest in wall of
settling tank with weeding mounding
etc. all complete. 10.00 No. 250.00 2500.00
9 LS Site clearance and other unforeseen
items.
1.00 Job L.S. 35.36
Total 85900.00
ASSISATANT ENGINEER
ABSTRACT OF COST (RECHARGING WELL)
Sl.
No. Description Qty. Unit Rate Amount
(A) Materials
1 Pipe rate Supply of PVC pipe 6 Kg/Cm2 110mm
OD with coupler.
30 M 651.00 19530.00
2 Supply of bell mouth piece for top
face of well with jali. 01 No. 220.00 220.00
(B) Labour
1 2043 Carting of PVC pipe of 110mm dia 6
Kg/Cm2 from store to site of work
with loading, unlaoding etc. all
complete.
01 Job 36.27 36.27
2 MR Making 150mm dia nominal dia bore
palm and pressure method complete
work.
30 M 600.00 18000.00
3 MR Lowring of 110mm dia PVC pipe in
prepared bore. 12 M 140.00 1680.00
4 MR Provision for slotted pipe for
discharge of water. 12 M 1850.00 22200.00
5 MR Fixing of bell mouth piece at top of
110mm dia pipe of boring. 01 Job L.S. 650.00
6 MR Site clearance and other unforeseen
items. - -
L.S. 33.73
Total 62350.00
ASSISATANT ENGINEER
MEASUREMENT OF WORK UNIT ESTIMATE OF DRAIN PER M WITH LEVELING
AND DRESSING OF WATER WORKS COMPOUND
Sl.
No. Description of work No. L B D/H QUANTITY
1 2 3 4 5 6
1 Earth work in excavation in
foundation trenches complete
works.
1 1.00 0.90 0.40 0.36 Cum
2 P.C.C in 1:4:8 cement, coarse
sand and brick ballast in
foundation trenches complete
work.
1 1.00 0.90 0.10 0.09 Cum
3 Brick work in 1:4 cement and
coarse sand for construction of
drain complete work.
2 1.00 0.23 0.30 0.14 Cum
4 Plaster work in side of wall in
1:4 cement and local sand
mortar.
2 1.00 .23+.30 - 1.06 Sqm
5 P.C.C in 1:2:4 for making in
semicircular surface at base of
drain.
1 1.00 0.03 - 0.03 Sqm
6 Site clearance 1 Job - -
ASSISATANT ENGINEER
DETAIL MEASUREMENT FOR CONSTRUCTION OF SETTLING TANK
ASSISATANT ENGINEER
CONSTRUCTION OF RECHARGING WELL
Sl.
No. Description of work No. 1 B D/H QUANTITY
1 2 3 4 5 6
(A) Materials
1 Supply of PVC pipe 6 Kg/Cm2
110mm OD with coupler.
1 30.00m 30.00 m
2 Supply of bell mouth piece for
top face of well with jali.
1 1 No. 1 No.
(B) Labour
1 Carting of PVC pipe of 110mm
dia 6 Kg/Cm2 from c/store to
site of work with loading,
unlaoding etc. all complete.
1 Job 1 Job
2 Making 150mm dia nominal
dia bore palm and pressure
method complete work.
1 30.00 30.00 M
3 Lowring of 110mm dia PVC
pipe in prepared hole.
1 12.00 12.00 M
4 Provision slotted pipe for
discharge for water 12 M 12.00 M
5 Fixing of bell mouth piece at
top of 110mm dia pipe of
boring.
1 Job 1 Job
6 Site clearance and other
unforeseen items. 1 Job 1 Job
ASSISATANT ENGINEER
DESIGN OF THRUST BLOCK
Dia of pipe d in cm = 15.00
Deviation angle α in degree 90.00
Max. water pressure p in Kg/cm 2 3.00
density of concrete Уc in Kg / m 3 2,400.00
Soil Density assumed Уs in Kg / m 3 1,800.00
density of water Уw in Kg / m 3
1,000.00
Angle of internal friction Ф in degrees 30.00
Minimum cover of soil over thrust block C in m 0.60
Cohession of sandy soil chin Kg / m 2 0.00
Cross sectional Area A = תx d 2 /4 in cm 2 176.63
Sin α/2 = Sin 90/2 = Sin 45 0.71
RCC 1:1.5:3
L B H Qty.
0.70 0.70 0.70 0.343
RCC 1:1.5:3
L B H Qty.
0.85 0.85 0.85 0.614
2 Concrete with cement, coarse sand & 20 mm nominal 0.34 Cum 6609.76 2247.32
size(20-40 mm) stone ballast in proportion of 1:4:8 in
foundations including supply of all materials, labour, T&P
etc. required for proper completion of the work.
3 Ist class brick work in 1:4 cement & coarse sand mortar 1.83 Cum 6605.17 12087.46
in foundation and plinth including supply of all materials,
labour, T&P etc. required for proper completion of the
work.
4 12 mm thick plaster with cement mortar in proportion of 6.60 Sqm. 199.98 1319.87
1:4 consisting of cement and Banda(Ken) / Hamirpur
(Betava) fine sand (F.M. not less than 1.25 mm) over brick
work including supply of all materials, labour, T&P etc.
required for proper completion of the work.
5 150 mm thick R.C.C. manhole cover in 1:1½:3 cement, 0.36 Cum 16285.13 5862.65
coarse sand and 12 to 20 mm gauge, stone grit with
suitable hole 100 mm dia at suitable place including
supply of all materials, labour, T&P etc. and fixing it in
position etc. all complete.
6 Mild steel work in RCC work wrought to required shape 55.00 Kg. 109.00 5995.25
as necessary, its fixing and binding. Also including supply
of all material, labour and T&P etc. for proper completion
of the work.
12 mm dia bar both way at 100 mm c/c.
ASSISTANT ENGINEER
UNIT ESTIMATE OF SLUICE VALVE CHAMBER
SURFACE BOX TYPE
Sl. Ref.
No Description of works Qty Unit Rate Amount
1 2 3 4 5 6
1 1001 Excavation of earth in ordinary soil (loam clay or
and) including lift upto 1.5 m and lead upto 50
m.filling, watering and ramming of excavated earth
in between the building and sides of the
foundation trenches or into the plinth and
disposal of surplus earth upto a distance of 50 m
from the center of the foundation trenches. 0.75 m³ 174.35 130.76
2 1011 Concrete with 40 mm gauge Ist class brick ballast,
localsand and cement in proportion (8:4:1) in
foundation including supply of all materials,
labour, T&P etc required for proper compltion of
work. 0.07 m³ 5221.10 365.48
3 1015 C.C. Work cement,coarse sand and 20 mm gauge
approved stone ballast in proper ratio of 1:2:4
including supply of all materials, labour,T&P etc
required for proper compltion of work. 0.16 m³ 8445.73 1351.32
4 Supply & fixing 0f 150 x 150 mm CI surface box of
IS mark heavy duty, including supply of all
materials, labour, T&P etc required for proper
completion of work. 1.00 each 4200.00 4200.00
5 Site Clearance and other unforeseen items Job L.S. 52.44
Total 6100.00
Say Rs 6100.00
Assistant Engineer
UNIT ESTIMATE OF AIR VALVE CHAMBER
(350MM TO 350MM)
Sl.N Ref.
o Description of works Qty Unit Rate Amount
1 2 3 4 5 6
1 1001 Excavation of earth in ordinary soil (loam clay or and)
including lift upto 1.5 m and lead upto 50 m.filling, watering
and ramming of excavated earth in between the building and
sides of the foundation trenches or into the plinth and
disposal of surplus earth upto a distance of 50 m from the
center of the foundation trenches. 0.60 m³ 174.35 104.61
2 1011 Concrete with 40 mm gauge Ist class brick ballast, local sand
and cement in proportion (8:4:1) in foundation including
supply of all materials, labour, T&P etc required for proper
compltion of work. 0.13 m³ 5221.10 678.74
3 1029 Ist class brick work in 1:6 cement and fine sand 1.25 F.M.
(fineness modulous) mortar in foundation and plinth
including supply of all materials, labour,T&P etc required for
proper compltion of work. 0.33 m³ 5966.03 1968.79
4 1190 12 mm thick plaster with cement, local sand mortar in 1:6
(over brick work with 3 mm floating coat of neat cement)
minimum thickness not less than 10 mm including supply of
all materials, labour,T&P etc required for proper compltion
of work. From GL upto supper structure. 2.91 m² 157.31 457.77
5 Supply ang fixing position 500 mm dia medium duty C.I.
Manhole cover (Perforated) with locking arrangement 1.00 no 5200.00 5200.00
6 Site Clearance and other unforeseen items Job L.S. 90.08
Total 8500.00
Say 8500.00
Assistant Engineer
UNIT ESTIMATE FOR FIRE HYDRANT CHAMBER
(750 MM x 450 MM)
Sl.
Ref. Description Unit Quantity Rate Amount in Rs.
No.
1 2 5 3 4 6
1 1001 Excavation of earth in foundation in ordinary soil
(loan, clay or sand) including lift up to 1.50m and leap
up to 50.00 m refilling of excavated earth in to space
between building and sides of foundation trench,
watering, ramming and disposal of surplus earth up
to 50 m from the center of the trench. Cum 3.50 174.35 610.23
2 1011 Concrete with 40 mm gauge Ist class brick ballast,
local sand and cement in proportion (8:4:1) in
foundation including supply of all materials, labour,
T&P etc required for proper compltion of work. Cum 0.15 5221.10 783.17
3 1029 First class brickwork in 1:6 cement and local sand
mortar in foundation and plinth including supply of all
materials, labour T&P etc required for proper
completion of work. Cum 1.21 5966.03 7218.90
4 1019 R.C.C. work with cement, coarse sand and 20 mm
gague approved stone ballast in proportion of 1:1.5:3
in slab excluding supply of reinforcement and its
bending but including its fixing and binding the same
with 0.50 mm thick binding wire (to be supplied by
contractor) and including necessary centering, and
shuttering supply of all materials labour, T&P etc.
required for proper completion of the work. Cum 0.20 10112.66 2022.53
5 1151 Mild steel or iron work in plain work such as RCC of
RB work (when not included in over all rates) wought
to required shape as necessary including supply of
steel and wastage. Qtl. 0.30 10900.46 3270.14
6 1190 12 mm thick plaster with cement and local sand
mortar in proportion of 1:6 over brickwork, minimum
thickness not be less than 10 mm including supply of
all materials labour, T&P etc required for proper
completion of work. Sqm 5.01 157.31 788.12
7 Site Clearance and other unforeseen items Job L.S. 306.92
Total 15000.00
Say 15000.00
Assistant Engineer
Analysis of Rate
(Rate in Rs.)
Item-1 Dismantling of B.O.E. Road
Sl. No. Description of Item Unit Quantity Rate Amount
DSR Ref no. 15.24
1 Supply all labour, T&P for dismantling of BOE road including stacking
serviceable material and disposal of unserviceable material within 50
metres etc. complete.
Rate for 9.09 per sqm
(i) Beldar No. 0.25 360.00 90.00
(ii) Coolies No. 1.00 360.00 360.00
Total 450.00
Sundries 2% 9.00
Total 459.00
Add 10% C.P. 45.90
Total 504.90
504.90
Rate per SQM 504.90 / 9.09 55.54
(Rate in Rs.)
Item-2 Dismantling of INTERLOCKING Road
Sl. No. Description of Item Unit Quantity Rate Amount
DSR Ref.
Details of Cost per Sq.m.
No.
16.83 Supply of all labour, T&P for dismantling of Interlocking paver block
road with rubbish including disposal of unserviceable materials within 1 Sq.m. 50.49 50.49
50 metres etc. complete.
15.1 Supply of all labour, T&P for demolishing of lean concrete in base of
road including stacking of serviceable materials and disposal of 1 Sq.m. 32.72 32.72
unserviceable materials within 50 metres etc. complete.
TOTAL 83.21
SAY 83.21
Supply of all labour, T&P for dismantling of Interlocking paver block
1 road with rubbish including disposal of unserviceable materials within
50 metres etc. complete.
Detail of cost for 10 cum
Beldar No. 0.25 360.00 90.00
Coolie No. 1.00 360.00 360.00
Sub Total 450.00
T&P and Sundries L.S. 2% 9.00
Sub Total 459.00
Add 10% C.P. 45.90
TOTAL 504.90
Rate for per cum 504.90 / 10.00 50.49
Supply of all labour, T&P for demolishing of lean concrete in base of
2 road including stacking of serviceable materials and disposal of
unserviceable materials within 50 metres etc. complete.
Detail of cost for 10 cum
Beldar No. 0.44 360.00 158.40
Coolie No. 0.37 360.00 133.20
Sub Total 291.60
T&P and Sundries L.S. 2% 5.83
Sub Total 297.43
Add 10% C.P. 29.74
TOTAL 327.17
Rate for per cum 327.17 / 10.00 32.72
(Rate in Rs.)
Item-3 Dismantling of C.C. Road
Sl. No. Description of Item Unit Quantity Rate Amount
DSR Ref.
Details of Cost per Sq.m.
No.
15.1 Supply of all labour, T&P for demolishing of lean concrete in base of
road including stacking of serviceable materials and disposal of 1 Sq.m. 32.72 32.72
unserviceable materials within 50 metres etc. complete.
Supply of all labour, T&P for demolishing of cement concrete road
15.2.1 including stacking of serviceable materials and disposal of 1 Sq.m. 93.31 93.31
unserviceable materials within 50 metres etc. complete.
TOTAL 126.03
SAY 126.03
Supply of all labour, T&P for demolishing of lean concrete in base of
1 road including stacking of serviceable materials and disposal of
unserviceable materials within 50 metres etc. complete.
Detail of cost for 10 cum
Beldar No. 0.44 360.00 158.40
Coolie No. 0.37 360.00 133.20
Sub Total 291.60
T&P and Sundries L.S. 2% 5.83
Sub Total 297.43
Add 10% C.P. 29.74
TOTAL 327.17
Rate for per cum 327.17 / 10.00 32.72
Supply of all labour, T&P for demolishing of cement concrete road
including stacking of serviceable materials and disposal of
2
unserviceable materials within 50 metres etc. complete. (concrete 1:3:6
richer mix)
Detail of cost for 10 cum
Beldar No. 1.59 360.00 572.40
Coolie No. 0.72 360.00 259.20
Sub Total 831.60
T&P and Sundries L.S. 2% 16.63
Sub Total 848.23
Add 10% C.P. 84.82
TOTAL 933.05
Rate for per cum 933.05 / 10.00 93.31
(Rate in Rs.)
Item-4 Dismantling of Bituminous Road
Sl. No. Description of Item Unit Quantity Rate Amount
15.43.2
Supply all labour, T&P for dismantling bitumenous road manually/mechanical
including stacking of serviceable materials and disposal of unserviceable
materials within 50 metres lead as per direction of Engineer-in-charge
TOTAL 5874.62
Cost of 36.00 sqm 5874.62
Cost of 1 sqm 163.18
Rate per SQM 163.18
Analysis of Rate
Item-1 Re-instatement of BOE Road
S. No. Description of Item Unit Quantity Rate Amount
DSR Ref.
15.2 Permanent reinstatement of BOE with 25% new
brick and 75% used old brick including all material
labour, T&P etc complete
Rate for 10 Per Sqm
(a) Labour
i) Mason Nos. 0.90 520 468.00
ii) Bhisti Nos. 1.98 400 792.00
iii) Coolie Nos. 0.05 360 18.00
iv) Sundries L.S. 2% 25.56
1303.56
(b) Material
25% new burnt bricks. Nos. 160 7.80 1248.00
Local Sand cum 0.15 650.00 97.50
S. Total 1345.50
TOTAL (A+B) 2649.06
Add C.P. @ 10% 264.91
2913.97
ASSISTANT ENGINEER
Page 50
Laying & Jointing and fixing of Sluice Valve Sluice Valve Fixing Cost Flanged Jointing
Qty Rate Amount
2445+2180 50mm dia Nos. 430.16 2 271.66 543.32 973.48
2445+2180 65mm dia Nos. 430.16 2 271.66 543.32 973.48
2445+2180 80mm dia Nos. 430.16 2 271.66 543.32 973.48
2445+2181 100mm dia Nos. 430.16 2 394.31 788.62 1218.78
4 2445+2182 125mm dia Nos. 430.16 2 448.85 897.70 1327.86
2446+2183 150mm dia Nos. 699.59 2 601.92 1203.84 1903.43
2446+2184 200mm dia Nos. 699.59 2 683.31 1366.62 2066.21
2447+2185 250mm dia Nos. 1358.43 2 951.38 1902.76 3261.19
2447+2186 300mm dia Nos. 1358.43 2 1053.32 2106.64 3465.07
2448+2187 350mm dia Nos. 1859.00 2 1393.66 2787.32 4646.32
2448+2188 400mm dia Nos. 1859.00 2 1853.52 3707.04 5566.04
2450 Fixing of 20-25mm dia Screw Down 645.35
5 Air Valve
2451+2180 Fixing of 65-80mm dia Flanged Air 331.03 1 271.66 271.66 602.69
6 Valve or Fire Hydrant
As per Dismantling Reinstatement
Dismentling and Reinstatement of road SOR As per Analysis As per Analysis
1302 BOE Road Sqm. 535.30 55.54 291.40
7
1323 C.C. Road Sqm. 2370.95 126.03 2207.09
1324 Bitumen Road Sqm. 1455.87 163.18 2462.86
Interlocking 83.21 1207.50
1 2 3 4 5 6
1 Excavation of earth in ordinary soil (loam clay or
and) including lift upto 1.5 m and lead upto 50
m.filling, watering and ramming of excavated earth
in between the building and sides of the 4.2 m³ 269.53 1132.03
foundation trenches or into the plinth and
disposal of surplus earth upto a distance of 50 m
from the center of the foundation trenches.
2 Supply & fixing of PVC saddle including supply of
all materials, labour,T&P etc required for proper 1 no 470.00 470.00
compltion of work.
3 Supply & fixing of brass ferrule 6 mm size in
existing main including supply of all materials,
labour,T&P etc required for proper compltion of
1 no 220.00 220.00
work.
4 Supply of MDPE pipe grade PE 80, 20 mm dia
30 m 40.00 1200.00
medium quality including all taxes etc complete.
5 Laying & Jointing of MDPE 20 mm dia medium
30 m 20.00 600.00
quality pipe including all specials etc complete
6 Supply & fixing of brass bib cock. Including all
3 no 200.00 600.00
matreials, labour T&P etc complete.
7 Supply & fixing of brass gate valve 20 mm dia.
1 no 650.00 650.00
Including all matreials, labour T&P etc complete.
8 Site Clearance and other unforeseen items Job L.S. 27.97
Total 4900.00
Say Rs 4900.00
Project Engineer
CARTING OF HDPE PIPE ( 63-200mm)
1 Carting from store 0-8 km. of 63 mm dia HDPE pipe to the site of
work, specials,fittings,laying true to aligment and gradient including
testing but excluding trenchningand making joints.
Total 9515.71
Rate per cum 614.71
Say( Cum) 615.00
ASSISTANT ENGINEER