1 Background
A Cement parker placement is currently ongoing on OB79. On completion of this intervention, the well will be
converted to a gas producer. This MOC is to comply to the requirement for an actuated Master valve on an eruptive
gas or high GOR well.
The intervention here proposed will be performed during any window to prior to the planned E-line perforation.
2 Current status:
➢ Coiled Tubing Intervention ongoing
✓ The crew must be instructed that the bolts of the flanges are tightened as illustrated below:
▪ At first, four (4) bolts (studs) are tightened with required torque, usually applied with
utilization of the hammer wrench.
▪ Attention must be paid to have an equal gap between lower and upper flanges.
▪ When equal round gap and optimum torque are achieved, the bolts may be tightened.
▪ Operations may be repeated until all four bolts are equally tight.
The rest of bolts are tightened to about same torque as previous four, round the flange
perimeter, either clockwise or anticlockwise direction.
This method reduces the time required for making flange connections and provides equal
torque for all bolts around the flange.
When closing or opening manual gate valves, the gate must not be forced into the seats,
since this action may cause additional seats’ wear and shorten valve’s life.
The best method is to open / close valve until it stops, and then return hand-
wheel about 1/8 of a turn backward.
1
3.2 INSTALL 3” TWCV AND P/TEST
1. Make up a 3’’ TWCV on the lubricator-running tool, R/U lubricator to the XMT.
2. Pressure test the lubricator against SV to 300psi/5min and 3000psi/5min.Chart record all pressure test.
3. Open XMT, ensure well pressure 0psi.
4. RIH and install the 3’’ TWCV in tubing hanger.
5. POOH and secure well.
6. P/test the 3’’ TWCV to 300/3000psi for 5mins respectively
7. Rig down all WH PCE and pressure test equipment.
2
Risk Assessment / Operational Impact: None
a) OB-79 WSO, Perforation and Screen Installation approved program Rev-03 17th -JUNE-2022
Actions to Implement Change (note if action is
completed):
MOC Distribution List: CWI Supervisors / DCD Well Services Supt / DCD DCSI / DCD CWI DGM/D&W GM
Regulator Review/Approval Required? Yes / No If Yes method/date:
Document Change Required? Yes / No If Yes Doc Number:
Position Role Name Signature and Date
Well Intervention & Integrity Authors M. Udeh Martin-
Digitally signed by: Martin-
Chidubem UDEH L0373627
DN: CN = Martin-Chidubem UDEH
Chidubem L0373627 C = FR O = TOTAL OU
= TOTAL AUTHENTIFICATION
UDEH L0373627 INTERNE
Date: 2022.07.09 14:31:40 +01'00'
J0515268
Date: 2022.07.09 14:53:03 +
01'00'
D&W WI & Integrity MGR Reviewer O. OLUBOBOKUN Digitally signed by: Henry
Henry UDE
DN: CN = Henry UDE C =
FR O = TOTAL OU = TOTAL
SIGNATURE INTERNE