71. Answer: b
Explanation: For cantilever beams with udl on entire span, the maximum deflection = wl 4/8EI
4
y = wl4/8EI = 25 × 3 / 8 × 4000 = 0.063m.
72. Answer: a
Explanation: b = 40cm = 400mm, t = 10mm, dh = 18mm
Net section area = 400×10 – 16×10 = 3820mm2 = 38.2 cm2.
73. Answer: d
Explanation: The section giving minimum area of plate is considered for design. So, section 1-5-7-6-3
is used for net area of flat.
74. Answer: b
Explanation: Width of pavement=7m
Rise of crown=7/2*1/50=7/100=0.07.
75. Answer: d
Explanation: This represents a series of depressions connected with shallow surface drains which are
in turn connected to lateral and main outlet drains. So, therefore this diagram represents a system of
random field drain system.
76. Answer: b
Explanation: Volume of water passing the drain in one day = (1/100 x 12 x 104) = 1200 m3/day
Volume of water passing the drain in one second = (1200/24 x 3600) = 1/72 m 3/sec
Q = 1/72 m3/sec
Q = 1/n x A x R2/3 x S1/2
A = πD2/4, P = πD, R = A/P = D/4
1/72 = (1/0.015) x (πD2/4) x (D/4) x (0.5/100)
On solving the value of D = 17.4 cm
Use D = 20 cm.
77. Answer: b
Explanation: The specific speed of a Pelton turbine ranges from 10 to 30. Francis turbine has a
specific speed between 60 to 300 and the specific speed of Kaplan and propeller turbine lies in
between 300 to 1000.
78. Answer: a
Explanation: The discharge over the weir without any velocity of approach is given by –
Q = C.L H3/2 where C = 1.66 when the width of rectangular crest > 0.9 m, L is the length of the weir
and H is the head of water over the weir.
Q = 1.66 x 55 x 1.2^3/2 = 120 cumecs.
79. Answer: d
Explanation: Approximately 1.52 m3 of dry concrete is required for 1 m3 of wet concrete. The quantity of
sand required for RCC (1:2:4) for 15 cubic metres of work is [2/(1+2+4)] x 1.52 x 15 m 3 i.e. 6.51 m3.
80. Answer: c
Explanation: For dams higher than 30 m, the top width (A) is given by the following formula-
A = 1.65 (H + 1.5)1/3 where H is the height of the dam.
A = 1.65 (50 + 1.5)1/3 = 6.13 m.