Dear Sir,
Please find the Attachment file below.
390) Request to Provide required Power Shut downs for 33KV power line which exists on LC No 559 A1 Side
Approach.pdf
447K
Dear sir, Discussed with Dy EE MSEDCL/Kanhan for shutdown down in front of Mr. Chandrashekhar Kose, your electrical
agency at Kanhan site today, he stated that shut down was arranged several times on WCL Line but not availed. After
meeting with MSEDCL Dy, AE & WCL Electrical officer, they have agreed to provide shut down of 04 hrs on saturday
at i.e. 02.12.2023, please arrange to complete all work within the time frame. MSEDCL agreed to arrange shutdown on
MSEDCL line too for shifting of transformer & for connection of new transformer on required day, please arrange to
complete work as early as possible.
[Quoted text hidden]
--
Regards,
Aniranjan Prasad
Deputy General Manager (Electrical)