Professional Documents
Culture Documents
Risk Plan Shard London Team 3 Saniya Sabina Swapneel Pooja 2
Risk Plan Shard London Team 3 Saniya Sabina Swapneel Pooja 2
Risk Plan Shard London Team 3 Saniya Sabina Swapneel Pooja 2
[For internal use only contains sensitive information. Not for sharing with outside company parties]
Shard London Bridge Project
Project Description
The Shard London Bridge, previously known as London Bridge Tower, is a mixed-use building
project in London. Designed by Renzo Piano, the structure has been constructed on the site of
an existing 1970s office building, known as Southwark Towers, adjacent to London Bridge
station. It provides a mix of shopping, office, hotel, leisure and residential uses, as well as
offering a variety of public spaces, including viewing galleries.
VERSION HISTORY
TABLE OF CONTENTS
INTRODUCTION...............................................................................................................3
1.1 Purpose Of The Risk Management Plan.......................................................3
RISK MANAGEMENT PROCEDURE...............................................................................3
2.1 Process..........................................................................................................3
2.2 ROLES AND RESPONSIBILITIES.......................................................................4
2.3 Risk Identification..................................................................................................4
2.3.1 Methods for Risk Identification....................................................................5
2.4 Risk Analysis.........................................................................................................6
2.4.1 Qualitative Risk Analysis.............................................................................6
2.4.2 Quantitative Risk Analysis...........................................................................6
2.5 Risk Response Planning................................................................................7
2.6 Risk Monitoring, Controlling, And Reporting..................................................9
2.7 Risk Contingency Budgeting........................................................................10
3.0 TOOLS AND PRACTICES...................................................................................10
4.0 CLOSING A RISK.................................................................................................10
5.0 LESSONS LEARNED..........................................................................................11
APPENDIX A: RISK MANAGEMENT PLAN APPROVAL.............................................12
APPENDIX B: REFERENCES........................................................................................12
APPENDIX C: KEY TERMS............................................................................................12
INTRODUCTION
1.1 PURPOSE OF THE RISK MANAGEMENT PLAN
The project risk management plan is intended for guiding the project management team
throughout the entire process of managing project risks which includes major steps such as
Identifying Risks, Analyzing Risks, Response to the risks and Controlling or monitoring of
the risks. The risk management plan’s primary purpose is to provide the team with a
clear understanding of the necessary actions to be taken in order to protect the project from
hidden and identified threats and to utilize existing opportunities for improving project
performance. A mitigation approach is adopted for the Shard London Bridge Project
wherein preemptive actions are applied to either mitigate the specific risks during the
construction or to reduce the impact of the risk occurred.
these risks. The below process will be used to respond to project risks
Identification: Once the team identifies the risks affecting our project as well as project
outcomes. These risks after a careful discussion will be used to prepare a Project Risk
Register
Analysis: After the identification of the risks the team will determine the probability of
these risks happening along with their effects. The team will then study the impact of
these risks on the overalls goals for the project as well as the objectives. These will be
further recorded in the Project Risk Register
Evaluation: After thoroughly studying the risks these will be provided a ranking on the
basis of their significance and repercussions and noted in the Project Risk Register
Response: This crucial process step will be utilized to plan a response towards the
risks according to their ranks from highest to lowest. A plan will be laid out to attend
these risks or mitigate them to an acceptable level. This process step will be used to
PMGT 530 Risk Management Plan Team 3 Page 3 of 14
[For internal use only contains sensitive information. Not for sharing with outside company parties]
Shard London Bridge Project
create approaches ignorer to mitigate or prevent risks as well as any contingency plans
required in emergencies. These approaches will be further added to the Project Risk
Register
Monitor & Review: Using the Project Risk Register, this process step in the Risk
Management Process will be used to carefully monitor, evaluate the current standing of
the risks and then further review if any changes need to be made ignorer to mitigate the
risks.
Role Responsibilities
Entire Project Stakeholders Identifying the Risks
Project Manager Managing the Risk Register
Entire Project Stakeholders Evaluating the Risks
Entire Project Stakeholders Identifying the different options of the Responses
that can be provided to the Risks
Project Manager Final Approval on the Responses to the Risk
Project Manager Planning for the Probability of the occurrence of the
of Risks
Project Manager Monitoring and Reviewing Risks / and the reporting
of risks
Following matrix will be used to define the probability and impact for the risks:
Among these risks, the very high and high risks, scaled 4 and 5 will be further prioritized
for risk response planning and contingencies if required.
2.5 RISK RESPONSE PLANNING
In the response strategies elaborated below, the efforts should be taken equally by the
risk management team and the Project manager pertaining to the severity of the project.
The strategies adopted will be time bound and a single action can serve as response for
multiple risk events. The strategies can also be selected by the subject matter experts
and the stakeholders. The person in charge, who is assigned to implement the
strategies are mentioned below.
Use this risk strategy when risk is identified but project team cannot manage the
Project
Escalate risk due to lack of authority. Project team will be well acquainted with the
Manager
escalation processes to tackle such risks.
In this risk strategy, we will try to lessen the impact of the risk. This can be done
Risk
by reducing the risk probability or risk impact. For example, risk arising from
Management
Mitigate resource leaving in the middle of the project. This can be mitigated by bringing in
team
another resource from some other team in the organization until new resource is
member
appointed on board.
This strategy is used when there is a scarcity of the skills or resources to tackle Project
Transfer the risk or there is no time to plan for the risk. Taking insurance is one of the risk Management
transfer strategy. team
Risk
In this strategy we will try to remove the risk or risk impact completely. This can Management
Avoid
be done by making changes in project scope, schedule or plan. team
member
Project
Accept In this strategy we will take no action and acknowledge the project risk.
Manager
Risk
Responses Assigned To
Strategy
Similar actions are taken in response to this risk strategy as mentioned in the
Project
Escalate negative risk responses. Project team sees to it that the opportunity is out of
manager
project scope and escalates to the authorities.
This risk response strategy is exactly opposite to Avoid strategy discussed in the Risk
Exploit above section. Resources are invested to exploit the risk opportunity which can Management
benefit the entire project by reducing duration or cost. team member
Project
Project teams use this strategy to increase the probability of the positive impacts
Enhance management
of an opportunity which can benefit the project.
team
This positive risk strategy includes sharing some or all the opportunity to a third Project
Share
party who can help capture the opportunity for the benefit of the entire project. Manager
This strategy is similar to negative risk strategy, where no action is needed, and Project
Accept
the project risk is accepted as it is. manager
Determine the occurrences of risk triggers which help in reducing the risks in the
initial stages
Maintain the risk identification, analysis and monitoring recurring process in the
project
Recommend corrective measures which can be further used to reduce and mitigate
risks
Update the risk management and risk response plans timely; weekly
Save the unapproved change requests in the archives that can be used on the
future.
2.7 RISK CONTINGENCY BUDGETING
The budget allocated for this project is £2bn. The overall project budget is divided into
various categories such as; Construction, Resources, Equipment and supplies and
Work capital. The Contingency budget for each category is allocated individually which
makes it easier to track manage the project budgeting. The project manager is
responsible for maintaining the risk management and budgeting. There will be a firm of
advisors who are experts in each category. The project manager ensures the regular
communication with the advisory firm, sponsors and other stakeholders and will review,
reevaluate any new risks associated with those categories and authorize the
expenditures to handle the risks.
2. Each stage of the project will be evaluated, and a retrospective will be conducted so that
the lessons learned can be documented all along the project and improvement can be
made as needed.
3. The lessons learned document will have the detailed information on what the risks were
and how they were solved all along the project.
4. Entire team should be contributing to the lessons learned to make sure everything is well
documented.
We hereby approve that the Risk Management plan created is up to date and contains all the
information required to for a thorough risk assessment process.
____________________________
Project Manager In-charge
____________________________
APPENDIX B: REFERENCES
The following table summarizes the documents referenced in this document.
Document Name Description Location
Tom Kendrick Text Book for Risk Management N/A
Practice Standards Book for Risk Management N/A
for Risk by PMI
Management
Project Description Description and terms for https://www.designbuild-network.com/projects/london-bridge/
the Shard Bridge design
project
Risk Management Public Health Emergency / https://www.phe.gov/about/amcg/contracts/Documents/risk-
Plan / Qualitative Office of Acquisitions, management.pdf
Risk Assessment Management, Contracts
and Grants.