Construction Specifications - Electrical
Construction Specifications - Electrical
PMT OPRNS
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA YAA
ENGG CERT
LSS
10-01382-0008
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
CONSTRUCTION SPECIFICATIONS – ELECTRICAL
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ Prepared by:
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
DECEMBER, 2015
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA YAA
ENGG CERT
TABLE OF CONTENTS
LSS
00
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. Codes and Standards: Comply with all applicable Codes and Standards including,
but not limited to, those listed below:
00
DATE:
01/21/2016 Forward to the Company Representative for review and approval the following submittals.
CONSTRUCTION Refer also to appropriate Specification sections for other submittal requirements.
AGENCY
YAA
01/21/2016 A. General: Submit the following in accordance with Conditions of Contract and
DATE:
OPERATIONS Division 1 Specification Sections.
ASZ
01/21/2016 B. Prior to Commencing WORK: Shop drawings of proposed installations that deviate
DATE:
from the original design.
CONTROL NUMBER
VERIFICATION
EDSD
1. Major raceways systems, size and location, for both exterior and interior;
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
SECTION 16010
1 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
adjusting instructions.
DATE
00
DISCIPLINE
ENGINEER Refer to the appropriate specification sections for specific requirements. Otherwise,
ANP
01/21/2016
deliver products to the WORK Site properly identified with names, model numbers, types,
DATE:
PROJECT
grades, compliance labels, and other information needed for identification.
ENGINEER
LSS
01/21/2016
PART 2 - PRODUCTS
DATE:
CERTIFIED
YAA Refer to the appropriate specification sections for specific requirements.
01/21/2016
DATE:
CONSTRUCTION
PART 3 - EXECUTION
AGENCY
YAA
B. Provide all necessary raceway offsets, fittings, boxes and supporting materials
EDSD
C. Where interferences occur, the Company Representative shall decide which items
APPROVAL/CERTIFICATION REQUIREMENTS,
must be relocated.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16010
10-01382-0008-0001
2 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
building components.
LSS
F. Arrange for chases, slots, and openings in other building components during
progress of construction, to allow for electrical installations.
constructed.
I. Where mounting heights are not detailed or dimensions, install systems, materials,
and equipment to provide the maximum headroom possible.
K. Install systems, materials, and equipment level and plumb, parallel and
perpendicular to other building systems and components.
NO.
REV
00
DISCIPLINE
L. Install electrical equipment to facilitate servicing, maintenance, and repair or
ENGINEER replacement of equipment components. As much as practical, connect equipment
ANP
01/21/2016
for ease of disconnecting, with minimum of interference with other installations.
DATE:
PROJECT
ENGINEER M. Install access panel where units are concealed behind finished surfaces. Access
LSS
01/21/2016
panels are specified in Division 16 Section 16050 "BASIC ELECTRICAL
DATE: MATERIALS AND METHODS."
CERTIFIED
YAA
01/21/2016 N. Install systems, materials, and equipment giving right-of-way priority to systems
DATE:
CONSTRUCTION
required to be installed at a specified slope.
AGENCY
YAA
DATE:
Documents.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16010
3 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
D. Upon written instructions from the Company Representative, uncover and restore
YAA
ENGG CERT
E. Cut, remove and legally dispose of selected electrical equipment, components, and
materials as indicated, including, but not limited to, removal of electrical items
indicated to be removed and items made obsolete by the new WORK.
F. Protect the structure, furnishings, finishes, and adjacent materials not indicated or
scheduled to be removed.
ISSUED FOR IFC
DESCRIPTION
G. Provide and maintain temporary partitions or dust barriers adequate to prevent the
spread of dust and dirt to adjacent areas.
I. Patch finished surfaces and building components using new materials specified for
the original installation and experienced CONTRACTOR. CONTRACTOR's
qualifications refer to the materials and methods required for the surface and
building components being patched.
JO/EWO
01/21/2016 BI-01382
DATE
END OF SECTION
NO.
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16010
10-01382-0008-0001
4 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. This Section includes general construction materials and methods for application
with electrical installations as follows:
ISSUED FOR IFC
DESCRIPTION
2. Fire-rated sealants for sealing penetrations in fire and smoke barriers, floors
and fire-rated walls.
A. Codes and Standards: Comply with all applicable Codes and Standards including,
JO/EWO
01/21/2016 BI-01382
00
DISCIPLINE
and Accessories)
ENGINEER
ANP
NFPA 70 National Electrical Code (NEC)
01/21/2016
UL Underwriter’s Laboratories
DATE:
PROJECT
SAUDI ARAMCO Construction Safety Manual
ENGINEER
SAUDI ARAMCO Engineering Standards (SAES)
LSS
01/21/2016
DATE:
CERTIFIED
1.03 SUBMITTALS
YAA
01/21/2016 A. General: Submit the following in accordance with Conditions of Contract and
DATE:
CONSTRUCTION Division 1 Specification Sections.
AGENCY
YAA
01/21/2016 1. Product data for each type or access doors, panels and sealants.
DATE:
OPERATIONS
ASZ 2. Schedules indicating proposed methods and sequence of operations for
01/21/2016 selective demolition prior to commencement of WORK. Include coordination
DATE:
for shut-off of electrical service, and details for dust and noise control.
CONTROL NUMBER
VERIFICATION
DATE:
A. Sealants:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
1. Deliver sealant materials such as duct seal and modular base conduit or
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16050
1 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
materials.
PART 2 - PRODUCTS
2.01 SOIL MATERIALS: All fill materials shall be subject to the approval of the Company
Representative.
A. On-Site Fill Material: All approved usable material removed from excavation shall
be used, as far as practicable, for backfill. Soil rock mixture which is free from
JO/EWO
01/21/2016 BI-01382
larger than 60mm (2-1/2” more or less), shall be considered as suitable material for
fill.
NO.
REV
00
DISCIPLINE
B. Borrow Fill: If on-site fill material is unsuitable for backfill as determined by
ENGINEER Company Representative, CONTRACTOR shall use materials from approved
ANP
01/21/2016
borrow fill.
DATE:
PROJECT
ENGINEER C. Sand envelope for underground cable and conduit installation shall be dry sand free
LSS
01/21/2016
from stones, rubble, debris, waste and other deleterious matter.
DATE:
CERTIFIED
YAA 2.02 FIRE-RESISTANT JOINT SEALANTS
01/21/2016
DATE:
CONSTRUCTION
A. Two-part, foamed-in place, silicone sealant formulated for use in through-
AGENCY
YAA
penetration fire-stopping around cables, pipes, and duct penetrations through fire-
01/21/2016 rated walls and floors. Sealants and accessories shall have fire-resistance ratings
DATE:
OPERATIONS
indicated, as established by testing identical assemblies in accordance with ASTM-
ASZ
E-814, by Underwriters’ Laboratories, Inc., or other approval equal.
01/21/2016
DATE:
2.03 FIRE-RESISTANT ACCESS DOORS AND PANELS
CONTROL NUMBER
VERIFICATION
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16050
10-01382-0008-0001
2 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
PART 3 - EXECUTION
YAA
ENGG CERT
A. Install sealant, including forming, packing, and other accessory materials, to fill
openings, around electrical services penetrating floors and walls, to provide fire-
stops with fire-resistance ratings indicated for floor or wall assembly in which
penetration occurs. Comply with installation requirements established by
manufacturer.
ISSUED FOR IFC
DESCRIPTION
A. Set frames accurately in position and securely attached to supports, with face
panels plumb and level in relation to adjacent finish surfaces.
SAES-S-070.
DATE
B. Excavate trenches to the uniform width, sufficiently wide to provide ample working
room and a minimum of 150 to 230mm (6 to 9 inches) clearance on both sides of
raceways and equipment.
NO.
REV
00
DISCIPLINE
ENGINEER C. Where rock is encountered, carry excavation below required elevation and backfill
ANP
01/21/2016
with a layer of dry sand prior to installation of raceways and equipment. Provide a
DATE:
PROJECT
minimum of 150mm (6 inches) of sand cushion between rock bearing surface and
ENGINEER electrical installations.
LSS
01/21/2016
DATE: 3.04 BACKFILL
CERTIFIED
YAA
DATE:
SECTION 16050
10-01382-0008-0001
3 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
DATE:
DATE:
DATE:
DATE:
DATE:
THIS INDICATES THAT REV. NO.__________ 00
00 01/21/2016 BI-01382 ISSUED FOR IFC YAA
OF THIS DRAWING IS COVERED, FOR ALL
LSS YAA ASZ
CONTROL NUMBER
YAA
ASZ
YAA
ANP
LSS
APPROVAL/CERTIFICATION REQUIREMENTS,
AGENCY
BY:
PROJECT
BY DRAWING COMPLETION CERTIFICATE
ENGINEER
01/21/2016
ENGINEER
01/21/2016
01/21/2016
DISCIPLINE
01/21/2016
CERTIFIED
01/21/2016
OPERATIONS
CONSTRUCTION
10-01382-0008-0001
(DCC) NO. _____________________ DATE:
DHAHRAN
Saudi Aramco 2616-ENG (03/99)
4.
RESIDENTIAL AREA
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL
EXPAND DHAHRAN RESIDENTIAL COMMUNITY –DD PKG 6
Removal of trash and debris.
SAUDI ARABIA
DOC
END OF SECTION
EWO:
A S60
DWG.TYPE PLANT NO. INDEX
SAUDI ARABIAN OIL COMPANY
10-01382-0008
SK-P60004
DRAWING NO.
4 of 4
10
OF
148
SHT.NO.
SECTION 16050
00
EDSD/2616-0399.doc
REV.NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. This Section includes raceways normally used in SAUDI ARAMCO facilities for
electrical wiring. Types of raceways in this section include the following:
ISSUED FOR IFC
DESCRIPTION
A. Codes and Standards: Comply with all applicable Codes and Standards including,
but not limited to, those listed below:
NO.
REV
00
DISCIPLINE
ENGINEER
ANP
1. SBC 401 Saudi Building Code – Volume 4
01/21/2016
DATE:
PROJECT
2. American National Standards Institute/American Society of Mechanical
ENGINEER
Engineers (ANSI/ASME)
LSS
01/21/2016
DATE:
CERTIFIED
ANSI/ASME B1.20.1 Pipe Threads, General Purpose (Inch)
YAA ANSI C80.1 Rigid Steel Conduit - Zinc Coated
01/21/2016 ANSI C80.3 Electrical Metallic Tubing - Zinc Coated
DATE:
CONSTRUCTION
AGENCY
YAA 3. Canadian Standards Association (CSA)
01/21/2016
DATE:
OPERATIONS
4. Factory Mutual Research Corporation (FM)
ASZ
01/21/2016
5. National Fire Protection Association (NFPA)
DATE:
CONTROL NUMBER
VERIFICATION
SECTION 16110
10-01382-0008-0001
1 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
1.03 SUBMITTALS
ISSUED FOR IFC
DESCRIPTION
2. Samples, 6 inches long of each type and size of surface raceway with
required finish.
JO/EWO
01/21/2016 BI-01382
PART 2 - PRODUCTS
NO.
REV
00
DISCIPLINE
2.01 MANUFACTURERS:
ENGINEER
ANP
01/21/2016
A. Available Manufacturer: Subject to compliance with requirements, manufacturers
DATE:
PROJECT
offering products which shall be incorporated with WORK include, but not limited
ENGINEER to, the following:
LSS
01/21/2016
DATE: B. Manufacturers: Subject to compliance with requirements, provide products from
CERTIFIED
YAA the following:
01/21/2016
DATE:
CONSTRUCTION
1. Rigid Steel Conduit
AGENCY
YAA
Alflex Corporation
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
PANASONIC
(DCC) NO. _____________________
SECTION 16110
10-01382-0008-0001
2 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
6. Conduit Bodies:
O-Z/Gedney
Other Approved Manufacturers
NO.
REV
00
DISCIPLINE
2.02 STANDARDS COMPLIANCE
ENGINEER
ANP
01/21/2016
The following products shall conform to the appropriate standards and requirements:
DATE:
PROJECT
ENGINEER A. Metal Conduit and Tubing:
LSS
01/21/2016
DATE: 1. Rigid Steel Conduit: ANSI C80.1, except hot-dip galvanized (per SAES-P-
CERTIFIED
YAA 104).
01/21/2016
DATE:
CONSTRUCTION
2. Electrical Metallic Tubing (EMT): ANSI C80.3.
AGENCY
YAA
SECTION 16110
10-01382-0008-0001
3 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
C. Conduit Bodies:
YAA
ENGG CERT
2. Metallic Conduit and Tubing: Use metallic conduit bodies. Use bodies with
threaded hubs for threaded raceways.
3. EMT Installations: For Conduit 1 inch and smaller, use bodies with
ISSUED FOR IFC
DESCRIPTION
PART 3 - EXECUTION
Comply with SBC 401, the National Electrical Code and SAES-P-104. General
requirements for conduit and conduit fittings shall be as follows:
A. Direct buried conduit shall be (a) threaded PVC coated rigid steel or (b) PVC
JO/EWO
01/21/2016 BI-01382
B. Conduits above ground in outdoor and industrial facilities shall be threaded, rigid
steel.
NO.
REV
00
DISCIPLINE
C. Where rigid steel conduit is run entirely within a concrete slab, it may be installed
ENGINEER without a PVC coating.
ANP
01/21/2016
DATE:
PROJECT
D. Intermediate metal conduit (IMC) is prohibited.
ENGINEER
LSS
01/21/2016
E. The minimum conduit size for aboveground installation shall be 3/4 inch, except on
DATE: instrument panels, inside builldings, on prefabricated skids, and in non-industrial
CERTIFIED
YAA areas, where the minimum size conduit shall be 1/2 inch. The minimum size for
01/21/2016 underground installation shall be 1 inch, unless otherwise indicated.
DATE:
CONSTRUCTION
AGENCY
YAA
F. Conduit and threaded conduit fittings shall have tapered (NPT) threads per
01/21/2016 ANSI/ASME B1.20.1.
DATE:
OPERATIONS
ASZ
3.02 INSTALLATION
01/21/2016
DATE:
A. General: Install electrical raceways in accordance with manufacturer's written
CONTROL NUMBER
VERIFICATION
SECTION 16110
10-01382-0008-0001
4 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
protection.
LSS
4 Protect stub-ups from damage where conduits rise from floor slabs.
Arrange so curved portion of bends is not visible above the finished slab.
5. Make bends and offsets so the inside diameter is not effectively reduced.
Unless otherwise indicated, keep the legs of a bend in the same plane and
the straight legs of offsets parallel.
ISSUED FOR IFC
DESCRIPTION
6. Use raceway fittings that are of types compatible with the associated
raceway and suitable for the use and location.
parallel or banked runs from the same center line so that the bends are
parallel. Factory elbows may be used in banked runs only where they can
be installed parallel. This requires that there be a change in the plane of
NO.
REV
00
DISCIPLINE
the run such as from wall to ceiling and that the raceways be of the same
ENGINEER size. In other cases provide field bends for parallel raceways.
ANP
01/21/2016
DATE:
PROJECT
10. Join raceways with fittings designed and approved for the purpose and
ENGINEER make joints tight. Make raceway terminations tight. Where terminations
LSS
01/21/2016
are subject to vibration, use bonding bushings or wedges to assure
DATE: electrical continuity. Where subject to vibration or dampness, use insulating
CERTIFIED
YAA bushings to protect conductors.
01/21/2016
DATE:
CONSTRUCTION
11. Tighten set screws of threadless fittings with suitable tool.
AGENCY
YAA
01/21/2016 12. Terminations: Where raceways are terminated with locknuts and bushings,
DATE:
OPERATIONS
align the raceway to enter squarely and install the locknuts with dished part
ASZ
against the box. Where terminations cannot be made secure with one
01/21/2016
locknut, use two locknuts, one inside and one outside the box.
DATE:
CONTROL NUMBER
VERIFICATION
13. Where terminating in threaded hubs, screw the raceway or fitting tight into
the hub so the end bears against the wire protection shoulder. Where
EDSD
chase nipples are used, align the raceway so the coupling is square to the
DATE:
14. Install pull wires in empty raceways. Use no. 14 AWG zinc-coated steel or
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16110
10-01382-0008-0001
5 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
monofilament plastic line having not less than 200-lb tensile strength.
YAA
ENGG CERT
Leave not less than 12 inches of slack at each end of the pull wire.
LSS
B. Field-cut conduit threads shall be coated with a zinc rich protective coating.
Threads of plugs, junction boxes and other fittings shall be lightly lubricated with a
rust preventive grease such as Crouse Hinds thread lubricant (SAMS 14-839-050)
or High Purity Goop (SAMS 26-011-087) before assembly.
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16110
10-01382-0008-0001
6 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
B. Cable tray support devices are specified here and in Section 16190 "Supporting
Devices."
A. Codes and Standards: Comply with all applicable Codes and Standards including,
but not limited to, those listed below:
00
DISCIPLINE
3. Factory Mutual Research Corporation (FM)
ENGINEER
ANP
01/21/2016
4. National Electrical Manufacturers Association (NEMA)
DATE:
PROJECT
ENGINEER NEMA Standard VE 1 Metallic Cable Tray Systems
LSS
01/21/2016
DATE: 5. Underwriters Laboratories (UL)
CERTIFIED
YAA
single manufacturer.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16111
1 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
1.03 SUBMITTALS
YAA
ENGG CERT
PART 2 - PRODUCTS
2.01 MANUFACTURERS
the following:
DATE
00
DISCIPLINE
The George-Ingraham Corp.
ENGINEER GS Metals Corp.
ANP
01/21/2016
Mono-Systems, Inc.
DATE:
PROJECT
MP Husky Corp.
ENGINEER P-W Industries, Inc.
LSS
01/21/2016
Square D Co.
DATE: Saudi Electric Industries Co; Ltd. (SEICO)
CERTIFIED
YAA WESCOSA
01/21/2016 Other Approved Manufacturers
DATE:
CONSTRUCTION
AGENCY
YAA
2.02 MATERIALS
01/21/2016
DATE:
OPERATIONS
A. GENERAL REQUIREMENTS
ASZ
01/21/2016
1. Cable tray systems shall be of indicated types, sizes, and NEMA classes
DATE:
and shall be complete with manufacturer's recommended covers, barrier
CONTROL NUMBER
VERIFICATION
DATE:
2. Cable tray products shall have rounded edges and smooth surfaces.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16111
10-01382-0008-0001
2 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
Exceptions:
00
DISCIPLINE
ENGINEER
ANP
Cable tray supports and connectors, including bonding jumpers shall be as
01/21/2016
recommended by cable tray manufacturer.
DATE:
PROJECT
ENGINEER D. FASTENERS FOR SUPPORTS
LSS
01/21/2016
DATE:
CERTIFIED
Unless otherwise indicated on the drawings, fasteners to connect cable tray
YAA supports to the building structure shall be as follows:
01/21/2016
DATE:
CONSTRUCTION 1. Expansion Anchors: Carbon steel wedge or sleeve type.
AGENCY
YAA
E. FIRE STOPPING
EDSD
General: Materials shall be UL listed and labeled and FM approved for fire ratings
DATE:
consistent with penetrated barriers. Materials may include but not limited to the
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16111
3 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
following:
YAA
ENGG CERT
2. Sealing Fittings: Suitable for sealing cables in sleeves or core drilled holes.
F. WARNING SIGNS
JO/EWO
01/21/2016 BI-01382
00
01/21/2016
D. Conform to manufacturer's recommendations for selection and installation of
DATE: supports per SAES-P-104, also conform to the following:
CONTROL NUMBER
VERIFICATION
Exception: Plant structural members used as supports for conduit and other
EDSD
(clamps, bolts, nuts, etc.) must however comply with the requirements.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
SECTION 16111
10-01382-0008-0001
4 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
00
SECTION 16111
10-01382-0008-0001
5 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
FG 1 per SAES-P-104.
LSS
K. Direction Changes: Make changes in direction of cable tray with standard cable
tray fittings.
L. Locate cable tray above piping except as required for tray accessibility and as
otherwise indicated.
M. Firestopping: Where cable trays penetrate fire and smoke barriers including walls,
ISSUED FOR IFC
DESCRIPTION
partitions, floors, and ceilings, install fire- stopping at penetrations after cables are
installed.
N. Sleeves for Future Cables: Install capped sleeves for future cables through
firestopped cable tray penetrations of fire/smoke barriers.
O. Working Space: Install cable trays with sufficient space to permit access for
installing cables.
3.02 GROUNDING
NO.
REV
00
DISCIPLINE
Electrically ground cable trays and ensure continuous electrical conductivity of cable tray
ENGINEER system. Use tray as an equipment ground conductor for itself only, not for connected
ANP
01/21/2016
equipment.
DATE:
PROJECT
ENGINEER 3.03 WARNING SIGNS
LSS
01/21/2016
DATE: After installation of cable trays is completed, install warning signs, on or in proximity to
CERTIFIED
YAA cable trays, where easily seen by occupants of space.
01/21/2016
DATE:
CONSTRUCTION
3.04 FIELD TESTING
AGENCY
YAA
01/21/2016 A. Grounding: Test cable trays to ensure electrical continuity of bonding and
DATE:
OPERATIONS
grounding connections.
ASZ
01/21/2016
B. Anchorage: For critical requirements only and as directed by the Company
DATE:
Representative, test pull-out resistance of one of each type, size, and anchorage
CONTROL NUMBER
VERIFICATION
Furnish equipment, including jacks, jigs, fixtures, and calibrated indicating scales
DATE:
required for reliable testing. Obtain the Architect's approval before transmitting
BY:
fastening fails test, replace fastener and retest until satisfactory results are
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16111
10-01382-0008-0001
6 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
achieved.
YAA
ENGG CERT
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16111
10-01382-0008-0001
7 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
1.01 DESCRIPTION
A. This Section includes aluminum cable runway, fittings, support brackets and
hanger clip.
ISSUED FOR IFC
DESCRIPTION
A. Codes and Standards: Comply with all applicable Codes and Standards including
but not limited to, those listed below:
1.03 SUBMITTALS
DATE
00
DISCIPLINE
ENGINEER
ANP
B. Product Data: For each type of cable runway, fittings and accessory item.
01/21/2016
DATE:
PROJECT
C. Installation Instructions: Manufacturer installation instructions for cable runway.
ENGINEER
LSS
01/21/2016
1.04 EXTRA MATERIALS
DATE:
CERTIFIED
YAA A. Furnish spares of the following item:
01/21/2016
DATE:
CONSTRUCTION
1. Cable runway 600 mm-width/10 ft length 6 ea.
AGENCY
YAA
DATE:
SECTION 16112
10-01382-0008-0001
1 of 2
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
PART 2 - PRODUCTS
YAA
ENGG CERT
2.01 MANUFACTURES
LSS
Square D. Co. - Al Abdul Karim Trading Est.; Tel. 834-3855, Fax 834-7308
Chatsworth Products Inc. - SESCO; Tel. 857-7738, Fax. 857-3293
Wahah Electric Company of Saudi Arabia Ltd. (WESCOSA). Tel. 857-7587, Fax:
857-1684.
ISSUED FOR IFC
DESCRIPTION
Other manufacturers
2.02 MATERIALS
B. Cable Runway Fittings: Cable runway fittings shall consist of universal splice plate
JO/EWO
01/21/2016 BI-01382
for straight runs, angle type slicing kits for either 45º or 90º vertical angle, junction
kits for making "T" connections, and auxiliary cable brackets to isolate power
DATE
cables from signal cables. Cable runway fittings shall be of the same manufacturer
as the cable runway to ensure complete compatibility. Fittings shall be made of
aluminum and when fitted shall not cause any reduction in strength of the cable
NO.
REV
00
DISCIPLINE
runway.
ENGINEER
ANP
01/21/2016
PART 3 - EXECUTION
DATE:
PROJECT
ENGINEER 3.01 INSTALLATION
LSS
01/21/2016
DATE: A. General: Install cable runway system in accordance with the layout shown on
CERTIFIED
YAA drawing. Cable runway shall be installed level and parallel to building structure on
01/21/2016 horizontal runs. Vertical runs shall be plumb. Use standard fittings for making
DATE:
CONSTRUCTION
bends. Field fabricated fittings not acceptable. Make up all splice joints tight.
AGENCY
YAA
01/21/2016 B. Cable Runway Supports: Use threaded rods and approved hangers, or wall
DATE:
OPERATIONS
brackets. Locations of supports are shown on drawings but may be slightly altered
ASZ
with the concurrence of SAUDI ARAMCO Representative, in order to avoid
01/21/2016
interference. Cable runway shall be supported at not more than 2000 mm
DATE:
intervals, as per details shown on drawing.
CONTROL NUMBER
VERIFICATION
EDSD
END OF SECTION
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16112
(DCC) NO. _____________________
10-01382-0008-0001
2 of 2
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
B. Related Sections: The following sections contain requirements that relate to this
Section:
C. Definitions
JO/EWO
01/21/2016 BI-01382
1. Duct: The general term for electrical conduit and other raceway, either
metallic or nonmetallic, specified for use underground, embedded in earth
DATE
or concrete.
2. Duct Bank: A group of two or more ducts in a continuous run between two
NO.
REV
00
DISCIPLINE
points.
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
1.02 QUALITY ASSURANCE
ENGINEER
LSS
01/21/2016
A. Codes and Standards: Comply with all applicable Codes and Standards including,
DATE: but not limited to, those listed below:
CERTIFIED
YAA
DATE:
SECTION 16119
1 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
1.03 SUBMITTALS
B. Product data for duct bank materials, and miscellaneous components. Include:
JO/EWO
01/21/2016 BI-01382
Raceway supports.
00
DISCIPLINE
ENGINEER D. Coordination drawings showing duct profiles and coordination with other utilities
ANP
01/21/2016
and underground structures.
DATE:
PROJECT
ENGINEER 1.04 DELIVERY, STORAGE, AND HANDLING
LSS
01/21/2016
DATE: A. Deliver ducts to site with ends capped. Store non-metallic ducts with supports to
CERTIFIED
YAA prevent bending, warping, and deforming.
01/21/2016
DATE:
CONSTRUCTION
1.05 PROJECT CONDITIONS
AGENCY
YAA
01/21/2016 A. Subsurface conditions were investigated during the design of the project. Reports
DATE:
OPERATIONS
of these investigations are available for informational purposes only. Data in the
ASZ
reports are not intended as representations or warranties of accuracy regarding
01/21/2016
continuity of conditions (between soil borings or test kits). The Owner will assume
DATE:
no responsibility for interpretations or conclusions drawn from this material.
CONTROL NUMBER
VERIFICATION
the path of construction under this section was obtained through investigations
DATE:
during the design of the project. Reports of these investigations are available for
BY:
SECTION 16119
10-01382-0008-0001
2 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
this information.
LSS
A. Coordination of the Work: Coordinate layout and installation with final arrangement
of ducts/ duct bank as influenced by actual final location of other utilities in the field.
Coordinate elevations of duct/ duct bank and raceway entrances into Buildings with
final profiles of conduits as determined by coordination with other utilities and
underground obstructions. Revise locations and elevations from those indicated as
ISSUED FOR IFC
DESCRIPTION
A. Furnish the following extra materials matching products installed, packaged with
protective covering for storage and with identification labels clearly describing
contents.
PART 2 - PRODUCTS
JO/EWO
01/21/2016 BI-01382
2.01 MANUFACTURERS
DATE
00
DISCIPLINE
ENGINEER B. Manufacturers: Subject to compliance with requirements, provide products by one
ANP
01/21/2016
of the following:
DATE:
PROJECT
ENGINEER 1. Nonmetallic Ducts:
LSS
01/21/2016
DATE: Saudi Plastic Products Company (SAPPCO)
CERTIFIED
YAA Anamet, Inc.
01/21/2016 Can-Tex Industries.
DATE:
CONSTRUCTION
Carlon.
AGENCY
YAA
Decoduct
01/21/2016 Other Approved Manufacturers
DATE:
OPERATIONS
ASZ
2.01 DUCTS AND FITTINGS
01/21/2016
DATE:
A. General: Ducts and duct fittings and accessories for which listing has been
CONTROL NUMBER
VERIFICATION
B. General: Ducts and duct fittings and accessories for which listing has been
DATE:
SECTION 16119
10-01382-0008-0001
3 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
A. Duct Supports: Rigid PVC spacers selected to provide minimum duct spacings
and concrete cover depths indicated, while rigidly supporting ducts during
concreting.
00
DISCIPLINE
worker's hands or materials.
ENGINEER
ANP
01/21/2016
PART 3 - EXECUTION
DATE:
PROJECT
ENGINEER 3.01 WIRING METHOD
LSS
01/21/2016
DATE: A. General: Install ducts for wiring runs indicated. Provide sizes as indicated.
CERTIFIED
YAA
01/21/2016 1. Single Duct Runs: PVC-coated galvanized rigid steel conduit, direct buried in
DATE:
CONSTRUCTION
earth.
AGENCY
YAA
01/21/2016 2. Duct Banks: Heavy wall plastic utilities duct type DB, encased in concrete.
DATE:
OPERATIONS
ASZ
3. Duct Banks: PVC-coated galvanized rigid steel conduit buried in earth.
01/21/2016
DATE:
3.02 EXCAVATION AND BACKFILL
CONTROL NUMBER
VERIFICATION
duty, hydraulic-operated compaction equipment shall not be used and trenching for
DATE:
SECTION 16119
10-01382-0008-0001
4 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
required pitch.
YAA
ENGG CERT
stones, soft spots, and sharp objects. Where necessary, add a 3-inch layer
of stone-free sand or earth to trench bottom and compact to density of
adjacent undisturbed soil to provide suitable bearing for ducts. Backfill over
and around ducts on bottom of trench with stone-free sand or earth to 6
inches minimum above tops of ducts and compact by hand or pneumatic
tamper to density of adjacent undisturbed earth.
ISSUED FOR IFC
DESCRIPTION
3. For each additional layer of direct-buried ducts above bottom ducts, backfill
over and around each layer of ducts with stone-free sand or earth to 6
inches minimum above tops of ducts and compact by hand or pneumatically
to density of adjacent undisturbed earth.
A. Curves and Bends: Use manufactured elbows for stub-ups at equipment and at
DATE
building entrances. For all other curves and bends, except as otherwise indicated,
use manufactured long sweep bends with a minimum radius of 25 ft. in both
horizontal and vertical directions.
NO.
REV
00
DISCIPLINE
ENGINEER B. Joints in ducts and fittings shall be made up watertight in accordance with
ANP
01/21/2016
manufacturer's instructions. Couplings shall be staggered so those of adjacent
DATE:
PROJECT
ducts do not lie in the same plane.
ENGINEER
LSS
01/21/2016
C. Duct Entrances to Buildings: Steel or schedule 80 PVC conduit. Transformations
DATE: from underground duct to conduit shall be made 6.5 ft. (2.0 meters) minimum,
CERTIFIED
YAA outside the building wall and shall use fittings manufactured for the purpose. Install
01/21/2016 in accordance with the following:
DATE:
CONSTRUCTION
AGENCY
YAA
1. Concrete-Encased Ducts: Install reinforcing in duct banks through
01/21/2016 disturbed earth near buildings and excavations and coordinate duct bank
DATE:
OPERATIONS
with structural design at wall so duct bank is supported at wall without
ASZ
reducing structural or watertight integrity.
01/21/2016
DATE:
D. Direct-Buried, Nonencased Duct Entering Nonwaterproofed Walls: Install a
CONTROL NUMBER
VERIFICATION
schedule 40 galvanized steel pipe sleeve for each duct. Caulk space between
conduit and sleeve with duct sealing compound on both sides for moisture-tight
EDSD
seal.
DATE:
BY:
SECTION 16119
10-01382-0008-0001
5 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
anchored into the masonry construction with one or more integral flanges
and the membrane waterproofing secured to the device in a permanently
LSS
watertight manner.
deforming of ducts, and secure separators to the earth and to ducts to prevent
floating during concreting. Do not use tie wires or reinforcing steel in such a way
as to form conductive or magnetic loops around ducts or duct groups.
G. Concreting: Spade concrete carefully during pours to prevent voids under and
between conduits and at exterior surface of envelope. Do not use power-driven
agitating equipment unless specifically designed for duct bank application. Pour
each run of envelope between terminations in one continuous operation. Where
more than one pour is necessary, terminate each pour in a vertical plane and install
3/4-inch reinforcing rod dowels extending 18 inches into the concrete on each side
JO/EWO
01/21/2016 BI-01382
H. Reinforcing: Reinforced duct banks where they cross disturbed earth and where
indicated. Size and arrangement of reinforcing steel as indicated.
NO.
REV
00
DISCIPLINE
I. Forms: The walls of the trench may be used to form the side walls of the duct bank
ENGINEER provided the soil is self-supporting and concrete envelope can be poured without
ANP
01/21/2016
soil inclusions. Use forms where the soil is not self-supporting.
DATE:
PROJECT
ENGINEER J. Minimum Clearances Between Ducts: Three inches between ducts and exterior
LSS
01/21/2016
envelope wall, 2 inches between ducts for like services, and 4 inches between
DATE: power and signal ducts.
CERTIFIED
YAA
01/21/2016 K. Depth: Except as otherwise indicated, top of duct bank shall be 24 inches below
DATE:
CONSTRUCTION
finished grade, minimum, in nontraffic areas, and 30 inches below finished grade,
AGENCY
YAA
minimum, in vehicular traffic areas.
01/21/2016
DATE:
OPERATIONS
L. Stub-ups: Duct stub-ups to equipment shall be galvanized rigid steel. For
ASZ
equipment mounted on outdoor concrete pads, steel conduit shall extend a
01/21/2016
minimum of 5 ft. away from edge of pad. Install insulated grounding bushings on
DATE:
the terminations. The steel conduits shall be coupled to the ducts with adapters
CONTROL NUMBER
VERIFICATION
designed for the purpose and the whole encased with 3 inches of concrete.
EDSD
terminations. For spare ducts, seal bore of ducts at terminations. Use sealing
BY:
pressure.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16119
10-01382-0008-0001
6 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
N. Pulling Cord: Install 100-pound test nylon cord in ducts including spares.
YAA
ENGG CERT
B. Duct Integrity: Rod ducts with a mandrell 1/4-inch smaller in diameter than internal
ISSUED FOR IFC
DESCRIPTION
A. Clean Ducts: Clean full length of ducts with a round bristle brush with a diameter
1/2 inch greater than internal diameter of duct.
00
DISCIPLINE
in accordance with section "Landscape Work." Restore disturbed paving as
ENGINEER indicated.
ANP
01/21/2016
DATE:
PROJECT
ENGINEER END OF SECTION
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16119
(DCC) NO. _____________________
10-01382-0008-0001
7 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. This Section includes wires, cables, and connectors for power, lighting, signal,
control and related systems rated 600 volts and less.
ISSUED FOR IFC
DESCRIPTION
B. Included in this Section is control wiring used for the interconnection of electrical
control devices, such as pushbuttons, electromechanical relays, etc., and also
microprocessor based protection relays for power distribution and motors.
D. This Section does not cover internal wiring of manufactured equipment approved
by SAUDI ARAMCO.
JO/EWO
01/21/2016 BI-01382
A. Codes and Standards: Comply with all applicable Codes and Standards including,
but not limited to, those listed below:
NO.
REV
00
DISCIPLINE
ENGINEER 1. SBC 401 (Saudi Building Code – Volume 4)
ANP
01/21/2016
DATE:
PROJECT
2. American National Standards Institute (ANSI)/ National Fire Protection
ENGINEER Association (NFPA)
LSS
01/21/2016
DATE: NFPA 70 National Electrical Code (NEC)
CERTIFIED
YAA
Fiber Members
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16230
10-01382-0008-0001
1 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
PART 2 - PRODUCTS
2.01 MANUFACTURERS
offering products which shall be incorporated with WORK include, but not limited
to, the following:
DATE
00
DATE:
01/21/2016 Riyadh Cable Company
PROJECT
ENGINEER
Saudi Cable Company
LSS Alpha Wire Company
01/21/2016 Belden Wire and Cable Company Inc.
DATE:
CERTIFIED Mitsubishi Cable Industries
YAA
Saudi Modern Co. for Cables, Ltd.
DATE:
01/21/2016 Okonite Company, Inc.
CONSTRUCTION Other Approved Manufacturers
AGENCY
YAA
DATE:
01/21/2016 2. Connectors for Wires and Cable Conductors:
OPERATIONS
ASZ Square D Company
01/21/2016 Burndy Co.
DATE:
Thomas and Betts
CONTROL NUMBER
VERIFICATION
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16230
2 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
A. Low voltage jacketed cables shall comply with NEC or IEC 502.
LSS
1. NEC low voltage cables shall be rated 600V, shall have a minimum
temperature rating of 90 deg C dry/75 deg C wet, and shall conform to UL
Standards according to the particular type (e.g. UL 1277, including its
vertical tray flame test, for type TC tray cables, etc.).
2. IEC 502 type cables shall be rated 600/1000V, shall have a minimum rating
ISSUED FOR IFC
DESCRIPTION
B. Low voltage unjacketed insulated wires, shall comply with NEC or SSA 55.
1. NEC low voltage wires shall be rated 600V, shall have a minimum
temperature rating of 90 deg C dry/75 deg C wet, and shall conform to UL
Standards according to the particular type (e.g. UL 83 for THHN/THWN and
UL 44 for XHHW).
2. SSA 55 type low voltage wires shall be rated 450/750V, shall have a
JO/EWO
01/21/2016 BI-01382
minimum rating of 85 deg C, and shall meet the flame test of IEC 332-1.
Exception:
DATE
For wiring of equipment such as lighting fixtures, etc., that require higher
NO.
REV
00
01/21/2016
E. Wiring Insulation for Interior Building Wiring: Unless otherwise indicated, provide
DATE: THHN/THWN insulation for all conductor sizes, except for equipment grounding
CONTROL NUMBER
SECTION 16230
10-01382-0008-0001
3 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
B. Copper compression (crimped) type connectors shall be used for splicing and
terminating stranded conductors, except as noted below:
b. In non-industrial applications.
00
permitted.
DISCIPLINE
ENGINEER
ANP
01/21/2016
C. The use of solder lugs is prohibited. Compression connectors for 230mm square
DATE: (4/0 AWG) and larger conductors shall be two hole NEMA design.
PROJECT
ENGINEER
LSS
D. All compression connectors for 10mm square (8 AWG) and larger conductors shall
01/21/2016
DATE: have a manufacturer’s reference die number and conductor size printed or
CERTIFIED
YAA stamped on the connector.
01/21/2016
DATE:
CONSTRUCTION
Exception:
AGENCY
YAA
The use of dieless compression tools is acceptable, provided that the tool is
01/21/2016
suitable for the connector, and, (for 8 AWG and larger conductor connectors), the
DATE:
tool ram embosses the tool manufacturer’s logo on the crimp.
OPERATIONS
ASZ
01/21/2016
E. Insulated ring tongue, locking fork tongue, or flanged fork tongue compression
DATE: (crimped) terminals shall be used for control wiring.
CONTROL NUMBER
VERIFICATION
Exception:
EDSD
Only ring tongue compression (crimped) terminals shall be used for current
DATE:
transformer circuits.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16230
10-01382-0008-0001
4 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
identification is required when conductor numbering systems are shown on the drawings.
Wires at termination points shall be identified by the use of permanently embossed wire
markers of the heat-shrinkable or slip-on type. Wrap-around, rigid snap-on, or adhesive
type markers are not permitted.
A. Color code secondary service, feeder, and branch circuit conductors with
factory applied color as follows:
B. Except for ground conductor in which green is mandatory, use conductors with
black insulation or jacket and color-code with Scotch No. 35 color-coding tape or
DATE
equivalent for specified insulations and jackets not manufactured by the selected
vendor with integral colors. Color-code each conductor entering every box,
cabinet, panel board, through, and wire way. In wire ways and other locations
NO.
REV
00
DISCIPLINE
where conductors are accessible, color-code conductors every 1500mm (5 FT).
ENGINEER
ANP
01/21/2016
PART 3 - EXECUTION
DATE:
PROJECT
ENGINEER 3.01 INSTALLATION OF WIRES AND CABLES
LSS
01/21/2016
DATE: A. General: Install electrical cables, wires, and connectors in compliance with NEC.
CERTIFIED
YAA
DATE:
SECTION 16230
10-01382-0008-0001
5 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
H. Install splice and tap connectors which possess equivalent or better mechanical
YAA
ENGG CERT
I. Use splice and tap connectors which are compatible with conductor material.
J. Provide adequate length of conductors within electrical enclosures and train the
conductors to terminal points with no excess. Bundle multiple conductors, with
conductors larger than 6mm square (10 AWG) cabled in individual circuits. Make
terminations so there is no bare conductor at the terminal.
ISSUED FOR IFC
DESCRIPTION
A. Cables shall be 500V DC megger tested after installation and prior to placing in
service.
JO/EWO
01/21/2016 BI-01382
B. Prior to energizing, test wires and cables for electrical continuity and for short-
circuits.
DATE
C. Subsequent to wire and cable hook-ups, energize circuits and demonstrate proper
functioning. Correct malfunctioning units, and retest to demonstrate compliance.
NO.
REV
00
DISCIPLINE
ENGINEER C. Correct the deficiencies found at no cost to SAUDI ARAMCO.
ANP
01/21/2016
DATE:
PROJECT
D. Low voltage (600, 450/750, or 600/1000 V rated) cables, including splices to
ENGINEER existing cables, shall be 1000 V DC megger tested after installation and prior to
LSS
01/21/2016
placing in service per SAES-P-104, Section 13.1
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16230
10-01382-0008-0001
6 of 6
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. This section includes conductor cables and splices, terminations, and accessories
for 13,200 V underground electrical distribution systems.
ISSUED FOR IFC
DESCRIPTION
A. Codes and Standards: Comply with all applicable Codes and Standards including,
DATE
00
DISCIPLINE
SAES-P-104 Wiring Methods and Materials
ENGINEER
ANP
15-SAMSS-502 Medium Voltage Power Cable 5KV through 35KV
01/21/2016
DATE:
PROJECT
B. Installer Qualifications: Splices and terminations on cables rated 1000V shall be
ENGINEER
made by personnel certified in accordance with SAUDI ARAMCO General
LSS
01/21/2016
Instruction 2.705.
DATE:
CERTIFIED
YAA C. Field Testing Organization Qualifications: To qualify for acceptance, an
01/21/2016 independent testing organization must demonstrate, based on evaluation of
DATE:
CONSTRUCTION organization-submitted criteria conforming to ASTM E 699, that it has the
AGENCY
YAA experience and capability to conduct satisfactorily the testing indicated.
01/21/2016
DATE:
OPERATIONS
D. Cable Testing after Installation: Conform to the requirements of SAES-P-104.
ASZ
DATE:
detailed specifications.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16124
1 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
A. Reels shall be made of steel, lagged with wood, and shall be marked with a
durable label securely attached to a flange of the reel and plainly stating Buyer’s
ISSUED FOR IFC
DESCRIPTION
Purchase Order number, shipping length of cable on reel, number, type and size of
conductors, cable configuration, and voltage rating. Cable ends shall be sealed
and capped.
C. Cable reels shall be covered, or turned on their sides, when not in use for long
periods to prevent UV damage.
1.05 WARRANTY
JO/EWO
01/21/2016 BI-01382
00
DISCIPLINE
addition to, and not a limitation of, other rights and remedies SAUDI ARAMCO may
ENGINEER have against the CONTRACTOR under the Contract Documents.
ANP
01/21/2016
DATE:
PROJECT
B. Special Project Warranty Period: 2 years beginning on the date of Substantial
ENGINEER Completion.
LSS
01/21/2016
DATE: PART 2 - PRODUCTS
CERTIFIED
YAA
01/21/2016
B. Manufacturers: Subject to compliance with requirements, provide products by the
DATE: following:
CONTROL NUMBER
VERIFICATION
1. Cable
EDSD
DATE:
SECTION 16124
10-01382-0008-0001
2 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
A. General: Cable shall be the types and sizes as indicated on the drawings and shall
conform to 15-SAMSS-502.
insulated, conforming to IEC 502 or AEIC (CS5 or CS6). Substitution of IEC cable
with AEIC cable, if IEC cable is specified, and vice versa, is prohibited.
DATE
00
DISCIPLINE
1. IEC 502 Class 2 annealed copper, plain or metal coated
ENGINEER
ANP
01/21/2016
2. AEIC Class B annealed copper, plain or metal coated
DATE:
PROJECT
ENGINEER D. Conductor Screen: Extruded semi conductive compound, or a layer of extruded
LSS
01/21/2016
semi-conducting compound over a semi-conducting tape.
DATE:
CERTIFIED
YAA E. Insulation Screen (Non-metallic part): Layer of extruded semi-conducting
01/21/2016 compound. Semi-conducting coatings (paints) are not allowed. The extruded
DATE:
CONSTRUCTION
compound shall be removable (strippable).
AGENCY
YAA
01/21/2016 F. Insulation Screen (Metallic part): Copper shielding tape, helically applied over the
DATE:
OPERATIONS
semicon-shielded, insulated conductor.
ASZ
01/21/2016
G. Concentric Neutral Conductor: If concentric neutral conductor is specified, it shall
DATE:
take the place of the copper shielding tape. It shall consist of copper wires with the
CONTROL NUMBER
VERIFICATION
SECTION 16124
10-01382-0008-0001
3 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
I. Metallic Armor or Metallic Cover: If specified, metallic armor or cover shall conform
LSS
1. IEC 502 Metallic armor shall be galvanized steel double tape armor,
or galvanized steel wire armor
J. All cables shall have a continuous overall outer PVC jacket, suitable for 90 ºC
maximum rated conductor temperature.
K. Cables shall be suitable for direct burial and for installation in duct banks and cable
trays.
00
DISCIPLINE
ENGINEER 2. AEIC Buyer’s System Voltage Nominal/Class: 13.2/15KV
ANP
01/21/2016
DATE:
PROJECT
Rated Voltage: 15KV
ENGINEER
LSS
01/21/2016
Insulation Thickness: Corresponding to 133 percent
DATE: insulation level in accordance with the referenced standard.
CERTIFIED
YAA
SECTION 16124
10-01382-0008-0001
4 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
D. Splicing shall be made with standard splicing kits and shall be one of the following
types:
1. Combination tape and cold shrink rubber sleeve kit with re-jacketing by cast
epoxy resin encasement or other waterproof, abrasion resistant material.
2. Heat shrink splice kit of uniform cross section polymeric construction with
ISSUED FOR IFC
DESCRIPTION
2. Load Break Cable Terminators: Elbow type units, make/break and with
continuous current rating as indicated. Each terminator shall be
coordinated with insulation diameter and conductor size and material of
NO.
REV
00
DISCIPLINE
cable being terminated. Terminator body shall have capacitively coupled
ENGINEER test point.
ANP
01/21/2016
DATE:
PROJECT
PART 3 - EXECUTION
ENGINEER
LSS
01/21/2016
3.01 EXAMINATION
DATE:
CERTIFIED
YAA A. Examine raceways, cable racks and other cable installation locations for
01/21/2016 cleanliness of raceways, minimum bending radii of cables, and conditions affecting
DATE:
CONSTRUCTION
performance of cable. Pull a mandrell through raceways to check for suitable
AGENCY
YAA
conditions. Do not proceed with cable installation until unsatisfactory conditions
01/21/2016 have been corrected.
DATE:
OPERATIONS
ASZ
3.02 INSTALLATION OF CABLES
01/21/2016
DATE:
A. General: Install cable accessory items in accordance with manufacturer's written
CONTROL NUMBER
VERIFICATION
B. Pull conductors simultaneously where more than one cable is indicated in same
DATE:
SECTION 16124
10-01382-0008-0001
5 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
C. Use pulling means including, fish tape, cable, rope, and basket weave wire/cable
YAA
ENGG CERT
grips that will not damage cables or raceways. Do not use rope hitches for pulling
attachment to cable.
LSS
B. Install splices using standard kit. Conform to kit manufacturer's written instructions.
C. Installation of Terminations
JO/EWO
01/21/2016 BI-01382
00
SECTION 16124
10-01382-0008-0001
6 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
to test organization.
LSS
C. Schedule tests and notify the Company Representative at least ten (10) working
days in advance of schedule for test commencement.
3. Procedures: Comply with the INETA Standard and IEEE 400. Upon
satisfactory completion of tests, attach a label to tested components.
JO/EWO
01/21/2016 BI-01382
00
DISCIPLINE
defective items. Testing organization shall submit written reports to the Company
ENGINEER Representative and CONTRACTOR.
ANP
01/21/2016
DATE:
PROJECT
ENGINEER END OF SECTION
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16124
7 of 7
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
A. This Section includes cabinets, boxes, and fittings for electrical installations and
certain types of electrical fittings not covered in other sections. Types of products
ISSUED FOR IFC
DESCRIPTION
A. Codes and Standards: Comply with all applicable Codes and Standards including
but not limited to, those listed below
NO.
REV
00
DISCIPLINE
SBC 401 Saudi Building Code – Volume 4
ENGINEER
ANP
BS 4662 Boxes for Flush Mounting of Electrical Accessories –
01/21/2016 Requirements, Test Methods and Dimensions
DATE:
PROJECT
NFPA 70 National Electrical Code (NEC)
ENGINEER
NEMA National Electrical Manufacturers Association
LSS
01/21/2016
NEMA 250 Enclosures for Electrical Equipment (1000 Volts Maximum)
DATE:
CERTIFIED
NEMA ICS 6 Enclosures for Industrial Control and Systems
YAA UL Underwriters Laboratories
01/21/2016 SAES-P-104 Wiring Methods and Materials
DATE:
CONSTRUCTION SAES-P-100 Basic Power System Design Criteria
AGENCY
YAA
1. Product data for cabinets and enclosures with classification higher than
NEMA 1.
EDSD
DATE:
2. Shop drawings for enclosures and cabinets that are to be shop fabricated,
BY:
(nonstock items). For shop fabricated junction and pull boxes, show
APPROVAL/CERTIFICATION REQUIREMENTS,
SECTION 16135
10-01382-0008-0001
1 of 5
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
PART 2 - PRODUCTS
LSS
2.01 MANUFACTURERS
Adalet-PLM
NO.
REV
00
DISCIPLINE
Cooper Industries, Inc.
ENGINEER Killark Electric Mfg. Co.
ANP
01/21/2016
OZ/ Gedney
DATE:
PROJECT
Robroy Industries, Inc.
ENGINEER Spring City Electrical Mfg. Co.
LSS
01/21/2016
Woodhead Industries, Inc.
DATE: Other Approved Manufacturers
CERTIFIED
YAA
01/21/2016 3. Cabinets:
DATE:
CONSTRUCTION
AGENCY
YAA
Electric Panelboard, Inc.
01/21/2016 Erickson Electrical Equipment Co.
DATE:
OPERATIONS
Spring City Electrical Mfg. Co.
ASZ
Square D Co.
01/21/2016
Alfanar Co.
DATE:
Other Approved Manufacturers
CONTROL NUMBER
VERIFICATION
PART 3 - EXECUTION
EDSD
DATE:
A. Locations: Install items where indicated and where required to suit NEC, SAES-P-
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16135
10-01382-0008-0001
2 of 5
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
B. Cap unused knockout holes where blanks have been removed and plug unused
YAA
ENGG CERT
conduit hubs.
LSS
C. Support and fasten items securely in accordance with Division 16 Section 16190
"Supporting Devices."
D. Sizes shall be adequate to meet NEC volume requirements, but in no case smaller
than sizes indicated.
E. Remove sharp edges where they may come in contact with wiring or personnel.
ISSUED FOR IFC
DESCRIPTION
3.02 APPLICATIONS
Comply with the provisions of the NEC, and in addition, comply with the following:
A. In outdoor plant areas, within the perimeter of process units, equipment and
terminal enclosures shall be either one of the following:
1. NEMA Type 4X
2. IEC 529 Type IP65 or better
JO/EWO
01/21/2016 BI-01382
B. In outdoor plant areas, outside the perimeter of process units, equipment and other
industrial areas, equipment and terminal enclosures shall be either one of the
following:
DATE
1. NEMA Type 3 or 4
NO.
REV
00
E. Enclosures and junction boxes having an internal volume exceeding 2000 cubic
EDSD
centimeters (122 cubic inches) shall be provided with Type 300 Series stainless
DATE:
SECTION 16135
10-01382-0008-0001
3 of 5
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
Class I locations by NEC Article 501, shall meet the hazardous area equipment
YAA
ENGG CERT
A. Locations in Special Finish Materials: For outlet boxes for receptacles and
switches mounted in desks or furniture cabinets or in glazed tile, concrete block,
marble, brick, stone or wood walls, use rectangular shaped boxes with square
corners and straight sides. Install such boxes without plaster rings. Saw cut all
recesses for outlet boxes in exposed masonry walls.
ISSUED FOR IFC
DESCRIPTION
B. Gasketed Boxes: At the following locations use cast metal, threaded hub type
boxes with gasketed weatherproof covers:
1. Exterior locations.
2. Where surface mounted on unfinished walls, columns or pilasters. (Cover
gaskets may be omitted in dry locations).
3. Where exposed to moisture laden atmosphere.
4. At food preparation equipment within four ft. of steam connections.
5. Where indicated.
JO/EWO
01/21/2016 BI-01382
C. Mounting: Mount outlet boxes for switches with the long axis vertical or as
indicated. Mount boxes for receptacles either vertically or horizontally but
DATE
consistently either way. Locate box covers or device plates so they will not span
different types of building finishes either vertically or horizontally. Locate boxes for
NO.
REV
00
switches near doors on the side opposite the hinges and close to door trim, even
DISCIPLINE
ENGINEER though electrical floor plans may show them on hinge side.
ANP
01/21/2016
DATE: D. Ceiling Outlets: Where wiring is concealed, use minimum of 86 x 86mm x 41mm
PROJECT
ENGINEER deep boxes for 1-gang outlets; and 86 x 146mm x 41mm deep for 2-gang outlets,
LSS
in accordance of BS 5733 , unless otherwise indicated.
01/21/2016
DATE:
CERTIFIED E. Cover Plates for Surface Boxes: Use plates sized to box front without overlap.
YAA
01/21/2016
DATE: F. Protect outlet boxes to prevent entrance of plaster, and debris. Thoroughly clean
CONSTRUCTION
AGENCY foreign material from boxes before conductors are installed.
YAA
01/21/2016
DATE: 3.04 INSTALLATION OF PULL AND JUNCTION BOXES
OPERATIONS
ASZ
A. Box Selection: For boxes in main feeder conduit runs, use sizes not smaller than
01/21/2016
DATE: 8-inches square by 4-inches deep. Do not exceed 6 entering and 6 leaving
CONTROL NUMBER
SECTION 16135
10-01382-0008-0001
4 of 5
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
250 MCM 20
LSS
B. Cable Supports: Install clamps, grids, or devices to which cables may be secured.
Arrange cables so they may be readily identified. Support cable at least every 30-
inches inside boxes.
C. Mount pull boxes in inaccessible ceilings with the covers flush with the finished
ceiling.
D. Size: Provide pull and junction boxes for telephone, signal, and other systems at
ISSUED FOR IFC
DESCRIPTION
C. Set cabinets in finished spaces flush with walls, unless indicated shown otherwise.
DATE
3.06 GROUNDING
A. Electrically ground metallic cabinets, boxes, and enclosures. Where wiring to item
NO.
REV
00
DISCIPLINE
includes a grounding conductor, provide a grounding terminal in the interior of the
ENGINEER cabinet, box or enclosure.
ANP
01/21/2016
DATE: 3.07 CLEANING AND FINISH REPAIR
PROJECT
ENGINEER
LSS
A. Upon completion of installation, inspect components. Remove burrs, dirt, and
01/21/2016
DATE: construction debris and repair damaged finish including chips, scratches, abrasions
CERTIFIED
YAA and weld marks.
01/21/2016
DATE:
B. Galvanized Finish: Repair damage using a zinc-rich paint recommended by the
CONSTRUCTION
AGENCY
YAA
tray manufacturer.
01/21/2016
DATE: C. Painted Finish: Repair damage using matching corrosion inhibiting touch-up
OPERATIONS
coating.
ASZ
01/21/2016
DATE:
CONTROL NUMBER
END OF SECTION
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16135
10-01382-0008-0001
5 of 5
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
DIVISION 16 - ELECTRICAL
YAA
ENGG CERT
PART 1 - GENERAL
Socket Outlets
Socket Outlets Incorporating Residual-Current Devices
Switches
A. Codes and Standards: Comply with all applicable Codes and Standards including
but not limited to, those listed below:
00
DISCIPLINE
Installations: General Requirements (BS 3676-1)
ENGINEER
ANP
BS EN 60669-2-1 Switches for Household and Similar Fixed Electrical
01/21/2016 Installations: Particular Requirements - Electronic Switches
DATE:
PROJECT
BS 1363-2 Specification for 13 A Switched Socket-Outlets
ENGINEER
LSS
01/21/2016
BS 4662 Boxes for Flush Mounting of Electrical Accessories -
DATE:
CERTIFIED
Requirements, Test Methods and Dimensions
YAA BS 5733 Specification for General Requirements for Electrical
01/21/2016 Accessories
DATE:
CONSTRUCTION BS 7288 Specification for Socket Outlets Incorporating Residual
AGENCY
YAA Current Devices
01/21/2016
DATE:
OPERATIONS
B. BS and IEC Compliance: Provide wiring devices which comply with applicable BS
ASZ and IEC Standards.
01/21/2016
DATE:
1.03 SUBMITTALS
CONTROL NUMBER
VERIFICATION
2. Samples.
(DCC) NO. _____________________
10-01382-0008-0001
SECTION 16143
1 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
PART 2 - PRODUCTS
YAA
ENGG CERT
2.01 MANUFACTURERS
LSS
MK by Honeywell
Legrand Co.
ISSUED FOR IFC
DESCRIPTION
Schneider Electric Co
Other Approved Manufacturers
B. Receptacles:
DATE
00
DISCIPLINE
units designed for installation in 72mm x 72mm x 47mm deep; and duplex
ENGINEER unit designed for installation in 72mm x 132mm x 47mm deep outlet boxes
ANP
01/21/2016
without adapter, grounding type, complying with BS 4662 Standard.
DATE:
PROJECT
ENGINEER 2. Receptacles Equipped with Residual Current Devices (RCD): Provide
LSS
01/21/2016
single and duplex, 13-ampere, 250-volt, 2-pole, 3-wire, grounding type,
DATE: flush-mounted switched receptacles equipped with RCD, with passive
CERTIFIED
YAA control ciruit and complying with BS 7288 Standard in areas required by
01/21/2016 NFPA-70. Provide single units designed for installation in 72mm x 72mm x
DATE:
CONSTRUCTION
47mm deep; and duplex units designed for installation in 72mm x 132mm x
AGENCY
YAA
47mm deep outlet boxes, without adapter, grounding type, complying with
01/21/2016 BS 4662 Standard.
DATE:
OPERATIONS
ASZ
3. Weatherproof Receptacles Equipped with Residual Current Devices (RCD):
01/21/2016
Provide weatherproof duplex, 13-ampere, 250-volt, 2-pole, 3-wire,
DATE:
grounding type, flush-mounted switched receptacles equipped with RCD,
CONTROL NUMBER
VERIFICATION
with passive control circuit and complying with BS 7288 and BS EN 60529
Standards for outdoor areas. Provide units complete with rear-entry back
EDSD
boxes.
DATE:
BY:
SECTION 16143
10-01382-0008-0001
2 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
switches with neon indicators, one gang, 250-volt; and 50-ampere, flush-mounted,
YAA
ENGG CERT
double- pole switches with neon indicators, 250-volt, one-gang, complying with BS
EN 60669-1 Standards. Provide units designed for installation in 72mm x 72mm x
LSS
47mm deep outlet boxes without adapter, grounding type, complying with BS 4662
Standard; and with engraved faceplates indicating equipment controlled.
60669-1 Standards for outdoor areas. Provide units complete with rear-
entry back boxes.
NO.
REV
00
DISCIPLINE
F. LED Dimmers: Unless otherwise indicated, provide 240-volt, 70-watt, LED
ENGINEER intelligent dimmers complying with BS EN 60669-2-1 Standard. Provide units
ANP
01/21/2016
designed for installation in 72mm x 72mm x 47 mm deep mounting boxes without
DATE:
PROJECT
adapter, grounding type, complying with BS 4662 Standard.
ENGINEER G. Wall Plates: Single and combination, of types, sizes, and with ganging and cutouts
LSS
01/21/2016
as indicated. Provide stainless steel plates for areas subject to hard usage or open
DATE: to the public.
CERTIFIED
YAA H. Door Chime: Provide Sleek and simple decorative design chime to fit selected
01/21/2016 décor, Mounted vertically or horizontally, fully adjustable volume, multi tone
DATE:
CONSTRUCTION
selection, powered by transformer, illuminated by LED indicators, Compatible with
AGENCY
YAA
most bell pushes, with standard normally open contacts, 1Ph, 230V, 60Hz.
01/21/2016
DATE:
OPERATIONS
PART 3 - EXECUTION
ASZ
01/21/2016
3.01 INSTALLATION OF WIRING DEVICES AND ACCESSORIES
DATE:
A. Install wiring devices and accessories as indicated, in accordance with
CONTROL NUMBER
VERIFICATION
DATE:
B. Coordinate with other work, including painting, electrical boxes and wiring
BY:
Work.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16143
10-01382-0008-0001
3 of 4
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
C. Install wiring devices only in electrical boxes which are clean; free from excess
YAA
ENGG CERT
3.02 PROTECTION
A. Prior to energizing circuits, test wiring for electrical continuity, and for short-circuits.
DATE
00
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16143
YAA
ENGG CERT
4 of 4
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. This Section includes circuit and motor disconnects (otherwise known as enclosed
switches, disconnects, disconnect switches or safety switches).
A. Code and Standards: Comply with all applicable Codes and Standards including,
but not limited to, those listed below:
00
01/21/2016
2. Maintenance data for circuit and motor disconnects, for inclusion in
DATE: Operation and Maintenance Manual specified in Division 16 Section 16010
OPERATIONS
"Basic Electrical Requirements"
ASZ
01/21/2016
DATE: PART 2 - PRODUCTS
CONTROL NUMBER
VERIFICATION
2.01 MANUFACTURERS
EDSD
DATE:
offering products which shall be incorporated in the work include, but are not
APPROVAL/CERTIFICATION REQUIREMENTS,
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16170
YAA
ENGG CERT
1 of 3
B. Manufacturers: Subject to compliance with requirements, provide products by the
following:
LSS
Crouse-Hinds Co.
Cutler-Hammer Inc.
General Electric Co.
Square D Company.
Westinghouse Electric Corp.
ISSUED FOR IFC
DESCRIPTION
A. General: Provide circuit and motor disconnect switches in types, sizes, duties,
features, ratings, and enclosures as indicated. For motor and motor starter
disconnects, provide units with horsepower ratings suitable to the loads.
2.03 ACCESSORIES
NO.
REV
00
DISCIPLINE
ENGINEER A. Electrical Interlocks: Provide number and arrangement of interlock contacts in
ANP
switches as indicated.
01/21/2016
DATE:
PROJECT
ENGINEER PART 3 - EXECUTION
LSS
01/21/2016
DATE: 3.01 INSTALLATION
CERTIFIED
YAA
01/21/2016
General: Follow switch manufacturers' printed installation instructions. Comply with the
DATE:
provisions of SBC 401, the NEC, SAES-P-100 and SAES-P-104 requirements and
CONSTRUCTION
AGENCY
YAA
installation conditions. In addition, comply with the following:
01/21/2016
DATE: A. In outdoor plant areas, within the perimeter of process units, equipment and
OPERATIONS
terminal enclosures shall be either one of the following:
ASZ
01/21/2016
DATE: 1. NEMA Type 4X
CONTROL NUMBER
B. In outdoor plant areas, outside the perimeter of process units, and other industrial
DATE:
areas, equipment and terminal enclosures shall be either one of the following
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
1. NEMA Type 4X
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16170
YAA
ENGG CERT
2 of 3
C. In outdoor plant and other industrial areas located in severe corrosive
environments (severe corrosive locations are enumerated under Section 16110
LSS
2. IEC 529 Type IP65 or better, manufactured of stainless steel (Type 304 or
better), or copper free cast aluminum or plastic (including fiberglass).
D. Enclosures that are rated (a) NEMA Type 3, 4 or 4X, or (b) IEC 529 Type IP54, or
better, shall have Type 300 Series stainless steel hardware, except aluminum
enclosures may have aluminum or aluminum alloy hinges.
E. Enclosures and junction boxes having an internal volume exceeding 2000 cubic
centimeters (122 cubic inches) shall be provided with Type 300 Series stainless
steel breather and drain fittings.
JO/EWO
01/21/2016 BI-01382
00
01/21/2016
DATE: END OF SECTION
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16170
YAA
ENGG CERT
3 of 3
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
This Section includes secure support from the building structure for electrical items by
means of hangers, supports, anchors, sleeves, inserts, seals, and associated fastenings.
A. Codes and Standards: Comply with all applicable Codes and Standards including
but not limited to, those listed below:
00
01/21/2016
2. Hanger and support schedule showing manufacturer's figure number, size,
DATE: spacing, features, and application for each required type of hanger, support,
CONTROL NUMBER
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
1 of 7
PART 2 - PRODUCTS
LSS
2.01 MANUFACTURERS
00
GS Metals Corp.
DISCIPLINE
ENGINEER Killark Electric Mfg. Co.
ANP
O-Z/Gedney
01/21/2016
DATE: Raco, Inc.
PROJECT
ENGINEER Red Seal Electric Corp.
LSS
Spring City Electrical Mfg. Co.
01/21/2016
DATE: Thomas & Betts Corp.
CERTIFIED
YAA Other Approved Manufacturers
01/21/2016
DATE:
2.02 COATINGS AND MATERIALS FOR SUPPORTING DEVICES
CONSTRUCTION
AGENCY
YAA
01/21/2016
A. Conform to manufacturer's recommendations for selection and installation of
DATE: supports. Per SAES-P-104, also conform to the following:
OPERATIONS
ASZ
Exception: Plant structural members used as supports for conduit and other
DATE:
01/21/2016
electrical equipment are not included in this section. Attachment hardware
(clamps, bolts, nuts, etc) must however comply to the requirements.
CONTROL NUMBER
VERIFICATION
EDSD
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
2 of 7
b. Outdoor onshore locations within one kilometer from the shoreline of
the Arabian Gulf, all of the Rastanura Refinery and Terminal, and
LSS
straps, threaded C-clamps with retainers, ceiling trapeze hangers, wall brackets,
and spring steel clamps.
00
floors and walls. Construct seals with steel sleeve, malleable iron body, neoprene
DISCIPLINE
ENGINEER sealing grommets or rings, metal pressure rings, pressure clamps, and cap screws.
ANP
01/21/2016
DATE: D. Cable Supports for Vertical Conduit: Factory-fabricated assembly consisting of
PROJECT
ENGINEER threaded body and insulating wedging plug for nonarmored electrical cables in riser
LSS
conduits. Provide plugs with number and size of conductor gripping holes as
01/21/2016
DATE: required to suit individual risers. Construct body of malleable-iron casting with hot-
CERTIFIED
YAA dip galvanized finish.
01/21/2016
DATE:
E. U-Channel Systems: 16-gage steel channels unless indicated otherwise. Provide
CONSTRUCTION
AGENCY
YAA
fittings and accessories that mate and match with U-channel and are of the same
01/21/2016
manufacture.
DATE:
OPERATIONS
2.04 FABRICATED SUPPORTING DEVICES
ASZ
01/21/2016
DATE: A. General: Shop- or field-fabricated supports or manufactured supports assembled
CONTROL NUMBER
DATE:
shapes. Connect with welds and machine bolts to form rigid supports. Conform to
APPROVAL/CERTIFICATION REQUIREMENTS,
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
3 of 7
C. Pipe Sleeves: Provide pipe sleeves (normally two sizes larger than conduit/pipe
passing through) of one of the following:
LSS
1. Sheet Metal: Fabricate from galvanized sheet metal; round tube closed
with snaplock joint, welded spiral seams, or welded longitudinal joint.
Fabricate sleeves from the following gage metal for sleeve diameter noted:
ISSUED FOR IFC
DESCRIPTION
PART 3 - EXECUTION
JO/EWO
01/21/2016 BI-01382
3.01 INSTALLATION
00
B. Coordinate with the building structural system and with other electrical installation.
DISCIPLINE
ENGINEER
ANP
C. Conform to manufacturer's recommendations for selection and installation of
01/21/2016
DATE: supports, in addition to the requirements specified in this Section.
PROJECT
ENGINEER
LSS
D. Strength of each support shall be adequate to carry present and future load
01/21/2016
DATE: multiplied by a safety factor of at least four. Where this determination results in a
CERTIFIED
YAA safety allowance of less than 200 lbs, provide additional strength until there is a
01/21/2016
minimum of 200 lbs safety allowance in the strength of each support.
DATE:
CONSTRUCTION
AGENCY
YAA
E. Install individual and multiple (trapeze) raceway hangers and riser clamps as
01/21/2016
necessary to support raceways. Provide U- bolts, clamps, attachments, and other
DATE: hardware necessary for hanger assembly and for securing hanger rods and
OPERATIONS
conduits.
ASZ
01/21/2016
DATE: F. Support parallel runs of horizontal raceways together on trapeze-type hangers.
CONTROL NUMBER
VERIFICATION
fasteners may be used in lieu of hangers only for 1-1/2-inch and smaller raceways
DATE:
serving lighting and receptacle branch circuits above suspended ceilings only. For
BY:
hanger rods with spring steel fasteners, use 1/4-inch-diameter or larger threaded
APPROVAL/CERTIFICATION REQUIREMENTS,
steel. Use spring steel fasteners that are specifically designed for supporting
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
4 of 7
H. Space supports for raceways in accordance with the following Table. Space
supports for raceway types not covered by the above in accordance with SBC 401
LSS
00
01/21/2016
larger
DATE:
Up to 2 Shaftway 14 10 -
CONSTRUCTION
AGENCY
YAA
2-1/2 Shaftway 16 10 -
01/21/2016
3 & larger Shaftway 20 10 -
DATE:
OPERATIONS
Any Concealed 10 10 -
ASZ
01/21/2016 * Maximum spacings for RSC above apply to straight runs only. Otherwise the
DATE:
maximums for EMT apply.
CONTROL NUMBER
VERIFICATION
I. Support exposed and concealed raceway within 1 foot of an unsupported box and
00
OF THIS DRAWING IS COVERED, FOR ALL
access fittings. In horizontal runs, support at the box and access fittings may be
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
5 of 7
omitted where box or access fittings are independently supported and raceway
terminals are not made with chase nipples or threadless box connectors.
LSS
J. In vertical runs, arrange support so the load produced by the weight of the raceway
and the enclosed conductors is carried entirely by the conduit supports with no
weight load on raceway terminals.
M. In open overhead spaces, cast boxes threaded to raceways need not be supported
separately except where used for fixture support. Support sheet metal boxes
directly from the building structure or by bar hangers. Where bar hangers are
used, attach the bar to raceways on opposite sides of the box and support the
JO/EWO
01/21/2016 BI-01382
raceway with an approved type of fastener not more than 24 inches from the box.
N. Sleeves: Install in concrete slabs and walls and all other fire- rated floors and walls
DATE
for raceways and cable installations. For sleeves through fire-rated wall or floor
construction, apply UL- listed firestopping sealant in gaps between sleeves and
NO.
REV
00
enclosed conduits and cables in accordance with "Fire Resistant Joint Sealers"
DISCIPLINE
ENGINEER requirement of Division 16 Section 16050.
ANP
01/21/2016
DATE: O. Conduit Seals: Install seals for conduit penetrations of slabs on grade and exterior
PROJECT
ENGINEER walls below grade and where indicated. Tighten sleeve seal screws until sealing
LSS
grommets have expanded to form watertight seal.
01/21/2016
DATE:
CERTIFIED
YAA P. Fastening: Unless otherwise indicated, fasten electrical items and their supporting
01/21/2016
hardware securely to the building structure, including but not limited to conduits,
DATE:
raceways, cables, cable trays, busways, cabinets, panelboards, transformers,
CONSTRUCTION
AGENCY
YAA
boxes, disconnect switches, and control components in accordance with the
01/21/2016
following:
DATE:
OPERATIONS
1. Fasten by means of wood screws or screw-type nails on wood, toggle bolts
ASZ
on hollow masonry units, concrete inserts or expansion bolts on concrete or
01/21/2016
DATE: solid masonry, and machine screws, welded threaded studs, or spring-
CONTROL NUMBER
provided with lock washers and nuts may be used instead of expansion
EDSD
2. Do not weld conduit, pipe straps, or items other than threaded studs to steel
APPROVAL/CERTIFICATION REQUIREMENTS,
structures.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16190
YAA
ENGG CERT
6 of 7
Q. Holes cut to depth of more than 1-1/2 inches in reinforced concrete beams or to
depth of more than 3/4 inch in concrete shall not cut the main reinforcing bars. Fill
LSS
R. Ensure that the load applied to any fastener does not exceed 25 percent of the
proof test load. Use vibration- and shock- resistant fasteners for attachments to
concrete slabs.
3.02 TESTS:
ISSUED FOR IFC
DESCRIPTION
A. Test pull-out resistance of one of each type, size, and anchorage material for the
following fastener types:
1. Expansion anchors.
2. Toggle bolts.
JO/EWO
01/21/2016 BI-01382
B. Provide all jacks, jigs, fixtures, and calibrated indicating scales required for reliable
testing.
NO.
REV
00
DISCIPLINE
ENGINEER C. Obtain the Structural Engineer's approval before transmitting loads to the structure.
ANP
01/21/2016
DATE: D. Test to 90 percent of rated proof load for fastener. If fastening fails test, revise all
PROJECT
ENGINEER similar fastener installations and retest until satisfactory results are achieved.
LSS
01/21/2016
DATE:
CERTIFIED
YAA END OF SECTION
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16190
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
7 of 7
YAA
ENGG CERT
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
includes requirements for electrical identification components including but not limited to
the following:
A. Codes and Standards: Comply with all applicable Codes and Standards including
but not limited to, those listed below:
NO.
REV
00
DISCIPLINE
ENGINEER 1. Electrical Component Standard: Components and installation shall comply
ANP
01/21/2016
with SBC 401 (Saudi Building Code Volume 4) and ANSI/NFPA 70
DATE:
PROJECT
"National Electrical Code," with the SBC 401 requirements prevailing over
ENGINEER the NFPA 70 provisions.
LSS
01/21/2016
DATE: 2. ANSI Compliance: Comply with requirements of ANSI Standard A13.1,
CERTIFIED
YAA "Scheme for the Identification of Piping Systems," with regard to type and
01/21/2016 size of lettering for raceway and cable labels.
DATE:
CONSTRUCTION
AGENCY
YAA
1.03 SUBMITTALS
01/21/2016
DATE:
OPERATIONS
A. General: Submit the following in accordance with Conditions of Contract and
ASZ
Division 1 Specification Sections:
01/21/2016
DATE:
1. Product Data for each type of product specified.
CONTROL NUMBER
VERIFICATION
PART 2 - PRODUCTS
EDSD
DATE:
2.01 MANUFACTURERS
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
offering products that may be incorporated in the Work include, but are not limited
(DCC) NO. _____________________
10-01382-0008-0001
SECTION 16195
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
1 of 4
YAA
ENGG CERT
A. Colored Adhesive Marking Tape for Raceways of Certain Systems: Self adhesive
JO/EWO
01/21/2016 BI-01382
vinyl tape not less than 3 mils thick by 1 inch to 2 inches in width.
Identification: Flexible acrylic bands sized to suit the raceway diameter and
arranged to stay in place by pre-tensioned gripping action when coiled around the
NO.
REV
00
raceway.
DISCIPLINE
ENGINEER
ANP
C. Underground Line Marking Tape: Permanent, bright-colored, continuous
01/21/2016
DATE: printed, plastic tape compounded for direct-burial service not less than 6 inches
PROJECT
ENGINEER wide by 4 mils thick. Printed legend indicative of general type of underground line
LSS below.
01/21/2016
DATE:
CERTIFIED D. Wire/Cable Designation Markers: Permanently embossed wire markers of the
YAA
01/21/2016
heat-shrinkable or slip-on type. Wrap-around, rigid snap-on, or adhesive type
DATE: markers are not permitted.
CONSTRUCTION
AGENCY
YAA
E. Engraved, Plastic-Laminated Labels, Signs, and Instruction Plates: Engraving
01/21/2016
DATE: stock melamine plastic laminate, 1/16-inch minimum thick for signs up to 20 square
OPERATIONS
inches, or 8 inches in length; 1/8-inch thick for larger sizes. Engraved legend in
ASZ
white letters on black face and punched for mechanical fasteners.
01/21/2016
DATE:
CONTROL NUMBER
F. Baked-Enamel Warning and Caution Signs for Interior Use: Preprinted aluminum
VERIFICATION
signs, punched for fasteners, with colors, legend, and size appropriate to the
EDSD
location.
DATE:
BY:
steel backing, with colors, legend, and size appropriate to the location. Provide 1/4
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16195
YAA
ENGG CERT
2 of 4
H. Fasteners for Plastic-Laminated and Metal Signs: Self-tapping stainless steel
screws or number 10/32 stainless steel machine screws with nuts and flat and lock
LSS
washers.
PART 3 - EXECUTION
3.01 INSTALLATION
00
DISCIPLINE
ENGINEER D. Conductor Color Coding:
ANP
01/21/2016
DATE: 1. Provide color coding for secondary service, feeder, and branch circuit
PROJECT
ENGINEER conductors throughout the project secondary electrical system as follows:
LSS
01/21/2016
DATE: Phase 400y/230 Volts
CERTIFIED
YAA
01/21/2016 A Brown
DATE:
CONSTRUCTION
B Black
AGENCY
YAA
C Gray
01/21/2016
Neutral Blue
DATE:
OPERATIONS
Ground Green-and-yellow
ASZ
01/21/2016
2. For specified insulations and jackets not manufactured by the selected
DATE:
vendor with integral colors, use conductors with black insulation or jacket
CONTROL NUMBER
VERIFICATION
wire way. In wire ways and other locations where conductors are
DATE:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16195
YAA
ENGG CERT
3 of 4
a. Apply colored, pressure-sensitive plastic tape in half- lapped turns
for a distance of 6 inches from terminal points and in boxes where
LSS
splices or taps are made. Apply the last two laps of tape with no
tension to prevent possible unwinding. Use 1-inch-wide tape in
colors as specified. Do not obliterate cable identification markings
by taping. Tape locations may be adjusted slightly to prevent such
obliteration.
b. In lieu of pressure-sensitive tape, colored cable ties may be used for
ISSUED FOR IFC
DESCRIPTION
END OF SECTION
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16195
YAA
ENGG CERT
4 of 4
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
00
SBC 401 (Saudi Building Code Volume 4) and ANSI/NFPA 70 "National Electrical
10-01382-0008-0001
Code," with the SBC 401 requirements prevailing over the NFPA 70 provisions.
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
1 of 12
E. ANSI/IEEE Compliance: Comply with applicable requirements of ANSI/IEEE
Standards including C2, "National Electrical Safety Code."
LSS
1.03 SUBMITTALS
C. Shop drawings for each transformer, including dimensional plans, sections, and
elevations showing minimum clearances, installed devices, and materials lists.
F. Installer certificates signed by the Contractor certifying that Installers comply with
the requirements specified under "Quality Assurance" below.
DATE
00
Hevi-Duty Electric.
EDSD
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
2 of 12
RTE Components.
Shape Magnetronics, Inc.
LSS
B. Windings: 2-winding type, designed for operation with high- voltage windings
connected to a 3-phase, 3-wire, 60 Hz, grounded neutral system.
C. Sound Level: Sound level of transformers for this project shall be minimum of 3 dB
less than NEMA TR 1 standard sound levels for transformer type and size
JO/EWO
01/21/2016 BI-01382
for reference with regard to sound levels even though it has been rescinded as an
overall transformer standard).
NO.
REV
00
DISCIPLINE
ENGINEER D. Unusual Service Conditions: Provide transformers designed for the following
ANP
conditions:
01/21/2016
DATE:
PROJECT
ENGINEER 1. Forced-air-cooled transformers shall comply with the following
LSS
requirements:
01/21/2016
DATE:
CERTIFIED
YAA 2. Forced-air-cooling equipment shall consist of cooling fans, temperature
01/21/2016
sensing devices, and controls complete with housing, mounting devices,
DATE:
conduit, and wiring. Operation of cooling fans shall be automatically and
CONSTRUCTION
AGENCY
YAA
sequentially controlled by temperature sensing devices. A manually
01/21/2016
operable switch shall be connected in parallel with the automatic control
DATE: contacts. Controls shall be enclosed in a cabinet located on the side of the
OPERATIONS
transformer 60 inches or less above the base.
ASZ
01/21/2016
DATE: 3. Cooling Fans: Propeller type, with aluminum blades and TEFC motors,
CONTROL NUMBER
DATE:
E. Provisions for Future Forced-Air Cooling: Include the following provisions where
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
3 of 12
operated control device with thermal element mounted in a well, and
provisions for mounting the control cabinet, the conduit, and the fans.
LSS
in all three coils for the future installation of sensors directly in the air ducts
of each coil to monitor coil temperature, and provisions for future mounting
of cooling fans, control cabinet, and conduit.
A. General: Comply with NEMA Standard ST 20, "Dry-Type Transformers for General
JO/EWO
01/21/2016 BI-01382
1. Enclosures:
NO.
REV
00
DISCIPLINE
ENGINEER a. Indoor, ventilated.
ANP
b. Outdoor, ventilated.
01/21/2016
DATE: c. Totally enclosed, nonventilated.
PROJECT
ENGINEER
LSS 2. Cooling System:
01/21/2016
DATE:
CERTIFIED
YAA
a. ANSI/IEEE Standard C57.12.01, Class AA.
b. ANSI/IEEE Standard C57.12.01, Class AA/FA.
01/21/2016
DATE: c. Equipped for future forced-air cooling; Class AA/FFA.
CONSTRUCTION
AGENCY
YAA
3. Insulation Class: 220 deg C.
01/21/2016
DATE:
OPERATIONS
4. Insulation Temperature Rise:
ASZ
01/21/2016
DATE: a. 80 deg C maximum rise above 40 deg C.
CONTROL NUMBER
a. 60 kV
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
b. 75 kV.
(DCC) NO. _____________________
c. 95 kV
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
4 of 12
d. 100 kV.
LSS
a. Four nominal 2.5 percent taps, two above and two below rated high
voltage.
b. Four nominal 2.5 percent taps, below rated high voltage.
ISSUED FOR IFC
DESCRIPTION
00
DISCIPLINE
ENGINEER 5. High-Temperature Alarm: Sensor at transformer with local audible and
ANP
visual alarm and contacts for remote alarm.
01/21/2016
DATE:
PROJECT
ENGINEER 2.04 PAD-MOUNTED TRANSFORMERS
LSS
01/21/2016
DATE: A. General: Comply with ANSI/IEEE C57.12.22 and with the following features and
CERTIFIED
YAA ratings:
01/21/2016
DATE:
B. General: Comply with ANSI/IEEE C57.12.26 and with the following features and
CONSTRUCTION
AGENCY
YAA
ratings:
01/21/2016
DATE: 1. Insulating Liquid: Mineral oil, conforming to ASTM D-3487 "Specifications
OPERATIONS
for Mineral Insulating Oil Used in Electrical Apparatus," Type II, tested in
ASZ
accordance with ASTM D-117 "Guide to Test Methods and Specifications
01/21/2016
DATE: for Electrical Insulating Oils of Petroleum Origin."
CONTROL NUMBER
VERIFICATION
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
5 of 12
extinguish small arcing and shall have a minimum fire point of 330 deg C, a
maximum convective heat release of 350 BTU/cu. ft. when tested in
LSS
B. Full-Capacity Voltage Taps: Four nominal 2.5 percent taps, two above and two
below rated high voltage, with externally operable tap changer for deenergized
use, with position indicator.
C. High Voltage Terminals: Arranged for radial feed, with 3-phase, 2-position, gang-
operated load-break switch, oil immersed in transformer tank, with hook-stick-
operated handle in the primary compartment.
D. High-Voltage Terminals: Arranged for loop feed with 3-phase, 4- position, gang-
JO/EWO
01/21/2016 BI-01382
00
DISCIPLINE
ENGINEER F. Surge Arresters: Comply with NEMA Standard LA 1, Distribution Class, supported
ANP
from tank wall within high-voltage compartment, one for each primary phase.
01/21/2016
DATE:
PROJECT
ENGINEER G. Separable Insulated Connectors: Insulated bushing, parking stand, feed-through
LSS
bushing, and dead-front elbow-type lightning arrester for each high-voltage
01/21/2016
DATE: terminal. Provide three portable insulated bushings for parking-energized load-
CERTIFIED
YAA break connectors on parking stands.
01/21/2016
DATE:
H. Secondary Feeder Breaker: Molded case type, mounted in secondary
CONSTRUCTION
AGENCY
YAA
compartment; frame, trip, and interrupting ratings as indicated; complying with UL
01/21/2016
Standard 489, "Molded Case Circuit Breakers and Circuit Breaker Enclosures."
DATE:
OPERATIONS
I. Accessories: Provide the following accessories:
ASZ
01/21/2016
DATE: 1. One-inch drain valve with sampling device.
CONTROL NUMBER
VERIFICATION
2. Dial-type thermometer.
EDSD
DATE:
4. Pressure-vacuum gage.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
6 of 12
6. Mounting provision for low-voltage current transformers and potential
transformers.
LSS
9. KWH meter.
ISSUED FOR IFC
DESCRIPTION
00
01/21/2016
4. Insulation Temperature Rise: 65 deg C.
DATE:
OPERATIONS
5. Basic Impulse Insulation Level: 60 kV, 75 kV, 95 kV and 110 kV.
ASZ
01/21/2016
DATE: B. Full-Capacity Voltage Taps: Four nominal 2.5 percent taps, two above and two
CONTROL NUMBER
below rated high voltage, with externally operable tap changer for deenergized use
VERIFICATION
DATE:
C. Cooling System:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
7 of 12
3. Equipped for future forced-air cooling; Class OA/FFA.
LSS
00
DISCIPLINE
ENGINEER 5. Drain Valve: 1-inch drain valve with sampling device.
ANP
01/21/2016
DATE: 6. Dial-type thermometer.
PROJECT
ENGINEER
LSS
7. Liquid level gage.
01/21/2016
DATE:
CERTIFIED
YAA 8. Pressure-vacuum gage.
01/21/2016
DATE:
9. Pressure relief device: Self-sealing, with indicator.
CONSTRUCTION
AGENCY
YAA
01/21/2016
10. Low-voltage busway connection.
DATE:
OPERATIONS
11. Alarm contacts for above gages.
ASZ
01/21/2016
DATE: 12. Grounding and bonding components complying with UL Standard 467,
CONTROL NUMBER
PART 3 - EXECUTION
DATE:
BY:
3.01 INSTALLATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
8 of 12
B. Identify transformers in accordance with Division 16 Section "Electrical
Identification."
LSS
2. Form concrete pads with steel channels conforming to ASTM A 36, size
and location as indicated. Miter and weld corner and provide cross bracing.
Anchor or key to floor slab.
JO/EWO
01/21/2016 BI-01382
3. Form concrete pads with framing lumber with form release compounds.
Chamfer top edge and corners of pad.
DATE
4. Install reinforcing bars, tied to frame, and place anchor bolts and sleeves to
NO.
REV
00
01/21/2016
DATE: B. Ground substation type transformers to ground bus to provide a maximum of 10-
CONTROL NUMBER
weldments.
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
9 of 12
3.04 FIELD QUALITY CONTROL
LSS
A. Manufacturer's Field Services: Arrange and pay for the services of a factory-
authorized service representative to supervise the field assembly and connection of
components and the pretesting and adjustment of transformer, components, and
accessories.
00
01/21/2016
DATE: 5. Reports: The testing organization shall maintain a written report of
CONTROL NUMBER
DATE:
6. Testing organization shall submit written test reports to the Architect and
BY:
Contractor.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
7. Testing shall include a turns ratio test at each tap setting, winding
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
10 of 12
addition, for liquid-filled transformers, insulating liquid shall be sampled and
tested.
LSS
D. Test Failures: Correct deficiencies identified by tests and make ready for retest.
Verify that the total system meets the specified requirements.
3.06 PROTECTION
3.07 DEMONSTRATION
NO.
REV
00
A. Training: Arrange and pay for the services of a factory- authorized service
DISCIPLINE
ENGINEER representatives to demonstrate transformers and accessories and training of
ANP
Owner's staff.
01/21/2016
DATE:
PROJECT
ENGINEER B. Training: Train Owner's staff in operation and maintenance for at least one day.
LSS
Include both classroom training and hands-on equipment operation and
01/21/2016
DATE: maintenance procedures. Training shall include:
CERTIFIED
YAA
01/21/2016
1. Safety precautions.
DATE:
CONSTRUCTION
AGENCY
YAA
2. Features and construction of project transformers and accessories.
01/21/2016
DATE: 3. Routine inspection and test procedures.
OPERATIONS
ASZ
4. Routine cleaning.
01/21/2016
DATE:
CONTROL NUMBER
protective devices.
EDSD
DATE:
7. Fuse selection.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
11 of 12
9. Features, operation, and maintenance of separable insulated connector
system.
LSS
C. Schedule training with Owner and Architect with at least seven days' advance
notice.
ISSUED FOR IFC
DESCRIPTION
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16322
YAA
ENGG CERT
12 of 12
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
1. Control buildings.
2. Outdoor Industrial Areas and Process Plant Areas.
A. Applicable Codes and Standards: Comply with all applicable Codes and
NO.
REV
00
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
1 of 8
1.03 SUBMITTALS
LSS
B. Product data for ground rods, connectors and connection materials, and grounding
fittings.
ISSUED FOR IFC
DESCRIPTION
PART 2 - PRODUCTS
2.01 MANUFACTURERS
JO/EWO
01/21/2016 BI-01382
00
01/21/2016
DATE: Products: Of types indicated and of sizes and ratings to comply with SBC 401 and the
OPERATIONS
NEC. Where types, sizes, ratings, and quantities indicated are in excess of NEC
ASZ
requirements, the more stringent requirements and the greater size, rating, and quantity
01/21/2016
DATE: indications govern.
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
2 of 8
2.03 WIRE AND CABLE CONDUCTORS
LSS
A. Conductor Materials:
1. Conductors shall be soft drawn copper and shall conform to the following
applicable standards:
ISSUED FOR IFC
DESCRIPTION
B. Conductors shall be insulated and PVC-jacketed with green or green with yellow
stripes, unless indicated otherwise.
JO/EWO
01/21/2016 BI-01382
A. General: UL-listed and labeled as grounding connectors for the materials used.
DATE
00
DISCIPLINE
ENGINEER C. Bolted Clamps: Heavy-duty units listed for the application.
ANP
01/21/2016
DATE: D. Exothermic Welded Connections: Provided in kit form and selected for the specific
PROJECT
ENGINEER types, sizes, and combinations of conductors and other items to be connected.
LSS
01/21/2016
DATE: 2.05 GROUNDING ELECTRODES
CERTIFIED
YAA
A. Ground Rods: Comply with the following:
01/21/2016
DATE:
CONSTRUCTION
AGENCY 1. Shall be copper, copper-jacketed steel (“Copperweld” or equivalent) or
YAA
galvanized steel. Copper-clad or jacketed steel rod shall be steel with high-
01/21/2016
DATE: strength steel core and electrolytic-grade copper outer sheath, molten
OPERATIONS
welded to core and shall meet the requirements of UL467.
ASZ
DATE:
01/21/2016
2. Minimum Size:
CONTROL NUMBER
VERIFICATION
long.
b. Galvanized steel: 19mm (3/4inch) diameter by 2.44m (8 ft) long.
DATE:
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
3 of 8
least every other structural steel column on the perimeter of the building to a
LSS
concrete-encased electrode or a ground ring installed per the NEC and SAES-P-
111. If a concrete-encased electrode is used, the conductor must be bare copper.
PART 3 - EXECUTION
ISSUED FOR IFC
DESCRIPTION
3.01 APPLICATION
A. Equipment Grounding Conductor for Feeder and Branch Circuits: Install separate
insulated equipment grounding conductors with circuit conductors as indicated.
Comply with SBC 401 for sizes and quantities of equipment grounding conductors,
except where larger sizes or more conductors are indicated.
same conduit, cable tray, cable, or cord or shall otherwise accompany the
power conductors.
DATE
00
with the power conductors as required by the NEC, supplementary grounding per
NEC 250-91 as required by SAES-P-111 shall be provided in outdoor plant areas,
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
4 of 8
process plant areas and in substations. Refer to SAES-P-111 Paragraph 7.2 for
the requirements.
LSS
1. Structural steel supports for process equipment and piping and structural
steel columns for buildings.
ISSUED FOR IFC
DESCRIPTION
minimum.
NO.
REV
00
01/21/2016
conductors shall be insulated or covered.
DATE:
CONSTRUCTION
AGENCY E. Grounding conductors which do not accompany associated power conductors in
YAA
the same conduit shall not be installed in metallic conduit except where PVC is not
01/21/2016
DATE: suitable and it is necessary to protect the conductor against mechanical damage.
OPERATIONS
Grounding conductors installed in metallic conduit and which do not accompany
ASZ
associated power conductors shall be bonded to both ends of the conduit.
01/21/2016
DATE:
CONTROL NUMBER
square (#4 AWG) minimum green insulated copper conductor in raceway from the
grounding electrode system to each terminal cabinet or central equipment location.
DATE:
BY:
3.02 INSTALLATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
A. General: Ground electrical systems and equipment in accordance with SBC 401,
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
5 of 8
B. Electrical Room Ground Bus: Size, location, and arrangement as indicated. Space
1 inch from wall and support from wall 6 inches above finished floor, except as
LSS
otherwise indicated.
C. Ground Rods: Locate a minimum of one-rod length from each other and buried at
least 460mm below grade. Connect ground conductors to ground rods by means
of exothermic welds, brazing, or approved compression grounding connectors
(Burndy “Hyground” system or equivalent). Make these connections without
ISSUED FOR IFC
DESCRIPTION
damaging the copper coating or exposing the steel. Drive rods until tops are
150mm (6 inches) below finished floor or final grade except as otherwise indicated.
E. Route grounding conductors along the shortest and straightest paths possible
without obstructing access or placing conductors where they may be subjected to
strain, impact, or damage, except as indicated.
JO/EWO
01/21/2016 BI-01382
G. Ground the shields and armor of power cable at both ends. Maintain continuity of
splice by bonding across the splice. On long runs of single core cables where
NO.
REV
00
circulating currents are a problem, ground one end of the cable shield. Install a
DISCIPLINE
ENGINEER cable protection device on the open end.
ANP
01/21/2016
DATE: H. Ground metallic raceway conduit at both end points. Grounding with locknuts
PROJECT
ENGINEER alone is not acceptable. Conduit grounding may be accomplished by:
LSS
01/21/2016
DATE: 1. Externally installing approved grounding clamps and conductors. For PVC-
CERTIFIED
YAA
coated conduits, do not scrape the coating to install grounding clamps. Use
other methods explained below.
01/21/2016
DATE:
CONSTRUCTION
AGENCY 2. Using grounded enclosures having integral threaded bushings or using a
YAA
conduit hub (such as Myers hub) which is approved for grounding
01/21/2016
DATE: purposes.
OPERATIONS
ASZ
3. Using an approved grounding bushing.
01/21/2016
DATE:
I Bond metallic cable trays at both end points and a minimum of every 25 meters to
CONTROL NUMBER
VERIFICATION
the local ground grid or ground electrode or to structural steel which is bonded to
EDSD
J. Ground busses of motor control centers shall have two connections to the main
ground electrode.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
6 of 8
3.03 CONNECTIONS
LSS
C. Exothermic Welded Connections: Use for connections to structural steel and for
underground connections to ground rods except those at ground test stations.
Comply with manufacturer's written recommendations. Welds that are puffed up or
that show convex surfaces indicating improper cleaning are not acceptable.
E. Tighten grounding and bonding connectors and terminals, including screws and
bolts, in accordance with manufacturer's published torque tightening values for
NO.
REV
00
01/21/2016
G. Compression-Type Connections: Use hydraulic compression tools to provide the
DATE: correct circumferential pressure for compression connectors. Use tools and dies
CONSTRUCTION
AGENCY recommended by the manufacturer of the connectors. Provide embossing die
YAA
code or other standard method to make a visible indication that a connector has
01/21/2016
DATE: been adequately compressed on the ground conductor.
OPERATIONS
ASZ
H. Moisture Protection: Where insulated ground conductors are connected to ground
01/21/2016
DATE: rods or ground buses, insulate the entire area of the connection and seal against
CONTROL NUMBER
A. Independent Testing Organization: Arrange and pay for the services of a qualified
DATE:
BY:
B. Tests: Subject the completed grounding system to a megger test at each location
(DCC) NO. _____________________
10-01382-0008-0001
SECTION 16452
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
7 of 8
YAA
ENGG CERT
enclosure ground terminal, and at ground test stations. Measure ground resistance
without the soil being moistened by any means other than natural precipitation or
natural drainage or seepage and without chemical treatment or other artificial
means of reducing natural ground resistance. Perform tests by the 2- point method
in accordance with Section 9.03 of IEEE 81, "Guide for Measuring Earth
Resistivity, Ground Impedance and Earth Surface Potentials of a Grounding
System."
ISSUED FOR IFC
DESCRIPTION
E. Report: Prepare test reports, certified by the testing organization, of the ground
DATE
00
DISCIPLINE
ENGINEER 3.05 CLEANING AND ADJUSTING
ANP
01/21/2016
DATE: A. Restore surface features at areas disturbed by excavation and re-establish original
PROJECT
ENGINEER grades except as otherwise indicated.
LSS
01/21/2016
DATE: B. Where sod has been removed, replace it as soon as possible after backfilling is
CERTIFIED
YAA completed. Restore areas disturbed by trenching, storing of dirt, cable laying, and
01/21/2016 other Work to their original condition.
DATE:
CONSTRUCTION
AGENCY
YAA
C. Include necessary topsoiling, fertilizing, liming, seeding, sodding, sprigging, or
01/21/2016
mulching. Restore disturbed paving as indicated.
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
END OF SECTION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16452
YAA
ENGG CERT
8 of 8
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. This Section includes lighting and power circuit breaker type panelboards and
associated auxiliary equipment rated 600V or less.
A. Applicable Codes and Standards: Conform to the Codes and Standards listed, but
not limited to:
1. Provide products that are listed and labeled by UL, NEMA, or other
internationally recognized testing laboratory.
JO/EWO
01/21/2016 BI-01382
comply with SBC 401 (Saudi Building Code Volume 4) and ANSI/NFPA 70
"National Electrical Code," with the SBC 401 requirements prevailing over
the NFPA 70 provisions.
NO.
REV
00
DISCIPLINE
ENGINEER 3. NEMA Standard: Comply with NEMA PB1, “Panelboards.”
ANP
01/21/2016
DATE:
4. UL Standards: Comply with UL 61, “Panelboards,” and UL 50, “Cabinets
PROJECT
ENGINEER and Boxes.”
LSS
01/21/2016
DATE: 1.03 SUBMITTALS
CERTIFIED
YAA
01/21/2016 A. General: Submit the following in accordance with Conditions of Contract and
DATE:
CONSTRUCTION
Division 1 Specification Sections.
AGENCY
YAA
01/21/2016
1. Product data for each type panelboard, accessory item, and component
DATE:
specified.
OPERATIONS
ASZ
01/21/2016
2. Shop drawings from manufacturers of panelboards including dimensioned
DATE: plans, sections, and elevations. Show tabulations of installed devices,
CONTROL NUMBER
a. Enclosure type with details for types other than NEMA Type 1.
DATE:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
1 of 7
4. Qualification data for field-testing organization certificates, signed by the
Contractor, certifying that the organization complies with the requirements
LSS
load balancing.
A. Keys: Furnish six spares of each type for panelboard cabinet locks.
PART 2 - PRODUCTS
NO.
REV
00
DATE:
01/21/2016 A. Available Manufacturers: Subject to compliance with requirements, manufacturers
PROJECT offering products that may be incorporated in the Work include, but are not limited
ENGINEER
LSS
to, the following:
01/21/2016
DATE:
CERTIFIED B. Manufacturers: Subject to compliance with requirements, provide products by the
YAA following:
01/21/2016
DATE:
CONSTRUCTION 1. ABB Power Distribution, Inc.
AGENCY
YAA 2. Asco Electrical Products Co., Inc.
01/21/2016 3. Challenger Electrical Equipment Corp. Crouse-Hinds Distribution
DATE:
OPERATIONS
Equipment.
ASZ 4. General Electric Co.
01/21/2016 5. Square D Co.
DATE:
6. Westinghouse Electric Corp.
CONTROL NUMBER
VERIFICATION
DATE:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
2 of 7
B. Enclosures: Cabinets, flush or surface mounted as indicted. NEMA Type 1
enclosure, except where the following enclosure requirements are indicated.
LSS
C. Front: Secured to box with concealed trim clamps except as indicated. Front for
surface-mounted panels shall be same dimensions as box. Fronts for flush panels
shall overlap box except as otherwise specified.
ISSUED FOR IFC
DESCRIPTION
G. Equipment Ground Bus: Adequate for feeder and branch-circuit equipment ground
conductors. Bonded to box.
JO/EWO
01/21/2016 BI-01382
H. Service Equipment Approval: Listed for use as service equipment for panelboards
having main service disconnect.
DATE
I. Provision for Future Devices: Equip with mounting brackets, bus connections, and
necessary appurtenances, for the OCPD ampere ratings indicated for future
NO.
REV
00
installation of devices.
DISCIPLINE
ENGINEER
ANP
J. Special Features: Provide the following features for panelboards as indicated.
01/21/2016
DATE:
PROJECT
ENGINEER 1. Isolated Equipment Ground Bus: Adequate for branch-circuit equipment
LSS ground conductors; insulated from box.
01/21/2016
DATE:
CERTIFIED 2. Hinged Front Cover: Entire front trim hinged to box with standard door
YAA
01/21/2016
within hinged trim cover.
DATE:
CONSTRUCTION
AGENCY 3. Skirt For Surface-Mounted Panels: Same gage and finish as panel front
YAA
with flanges for attachment to panel, wall, and floor.
01/21/2016
DATE:
OPERATIONS
4. Extra Gutter Space: Dimensions and arrangement as indicated.
ASZ
01/21/2016
DATE: 5. Gutter Barrier: Arranged to isolate section of gutter as indicated.
CONTROL NUMBER
VERIFICATION
way to overhead junction box equipped with ground and neutral terminal
buses.
DATE:
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
3 of 7
2.03 LIGHTING AND APPLIANCE BRANCH CIRCUIT PANELBOARDS
LSS
A. Doors: In panel front, with concealed hinges. Secure with flush catch and tumbler
lock, all keyed alike.
A. Doors: In panel front, omit single panelboard door in cabinet front for fusible switch
ISSUED FOR IFC
panelboards except as indicated. Secure with vault-type with tumbler lock, all keyed
DESCRIPTION
alike.
B. Branch-Circuit Breakers: Where OCPDs are indicated to be circuit breakers, use bolt-
on breakers except circuit breakers 225-ampere frame size and greater may be plug-in
type where individual positive locking device requires mechanical release for removal.
2.05 IDENTIFICATION
materials.
00
PART 3 - EXECUTION
DISCIPLINE
ENGINEER
ANP
3.01 INSTALLATION
01/21/2016
DATE:
PROJECT
ENGINEER A. General: Install panelboards and accessory items in accordance with NEMA PB
LSS 1.1, "General Instructions for Proper Installation, Operation and Maintenance of
01/21/2016
DATE: Panelboards Rated 600 Volts or Less" and manufacturers' written installation
CERTIFIED
YAA
instructions.
01/21/2016
DATE: B. Ground Fault Protection: Install panelboard ground fault circuit interrupter devices
CONSTRUCTION
AGENCY in accordance with installation guidelines of NEMA 289, "Application Guide for
YAA
Ground Fault Circuit Interrupters."
01/21/2016
DATE:
OPERATIONS
C. Mounting Heights: Top of trim 6'-2" above finished floor, except as indicated.
ASZ
01/21/2016
DATE: D. Mounting: Plumb and rigid without distortion of box. Mount flush panels uniformly
CONTROL NUMBER
E. Circuit Directory: Typed and reflective of final circuit changes required to balance
DATE:
G. Provision for Future Circuits at Flush Panelboards: Stub four 1- inch empty
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
4 of 7
conduits from panel into accessible ceiling space or space designated to be ceiling
space in future. Stub four 1-inch empty conduits into raised floor space or below
LSS
I. Wiring in Panel Gutters: Train conductors neatly in groups, bundle, and wrap with
ISSUED FOR IFC
DESCRIPTION
3.02 IDENTIFICATION
3.03 GROUNDING
indicated.
3.04 CONNECTIONS
NO.
REV
00
DISCIPLINE
ENGINEER A. Tighten electrical connectors and terminals, including grounding connections, in
ANP
accordance with manufacturer's published torque- tightening values. Where
01/21/2016
DATE: manufacturer's torque values are not indicated, use those specified in UL 486A and
PROJECT
ENGINEER UL 486B.
LSS
01/21/2016
DATE: 3.05 FIELD QUALITY CONTROL
CERTIFIED
YAA
01/21/2016
A. Independent Testing Organization: Arrange and pay for the services of an
DATE:
independent electrical testing organization in to perform tests on low-voltage power
CONSTRUCTION
AGENCY
YAA
panelboards and accessories.
01/21/2016
DATE: B. Pretesting: Upon completing installation of the system, perform the following
OPERATIONS
preparations for independent tests:
ASZ
01/21/2016
DATE: 1. Make insulation resistance tests of panelboard buses, components, and
CONTROL NUMBER
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
5 of 7
C. Quality Control Program: Conform to the following:
LSS
D. Procedures: Make field tests and inspections and prepare panelboard for
satisfactory operation in accordance with manufacturer's recommendations and
these specifications.
and settings. Use accepted ratings or settings to make the final system
adjustments.
NO.
REV
00
DISCIPLINE
ENGINEER E. Visual and Mechanical Inspection: Include the following inspections and related
ANP
work:
01/21/2016
DATE:
PROJECT
ENGINEER 1. Inspect for defects and physical damage, labeling, and nameplate
LSS compliance with requirements of up-to-date drawings and panelboard
01/21/2016
DATE: schedules.
CERTIFIED
YAA
01/21/2016
2. Exercise and perform of operational tests of all mechanical components
DATE: and other operable devices in accordance with manufacturer's instruction
CONSTRUCTION
AGENCY manual.
YAA
01/21/2016
DATE: 3. Check panelboard mounting, area clearances, and alignment and fit of
OPERATIONS
components.
ASZ
01/21/2016
DATE: 4. Check tightness of bolted electrical connections with calibrated torque
CONTROL NUMBER
5. Perform visual and mechanical inspection and related work for over current
protective devices as specified in Division 16 Section "Overcurrent
DATE:
BY:
Protective Devices."
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
manufacturer's instruction:
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
6 of 7
1. Insulation resistance test of buses and portions of control wiring that
disconnected from solid-state devices. Insulation resistance less than 100
LSS
3. Test main and subfeed over current protective devices in accordance with
Section "Overcurrent Protective Devices."
ISSUED FOR IFC
DESCRIPTION
3.06 CLEANING
3.07 COMMISSIONING
DATE
A. Balancing Loads: After Substantial Completion, but not more than two months
after Final Acceptance, conduct load-balancing measurements and circuit changes
NO.
REV
00
as follows:
DISCIPLINE
ENGINEER
ANP
1. Perform measurements during period of normal working load as advised by
01/21/2016
DATE: the SAUDI ARAMCO Representative.
PROJECT
ENGINEER
LSS
2. Perform load-balancing circuit changes outside the normal
01/21/2016
DATE: occupancy/working schedule of the facility. Make special arrangements
CERTIFIED
YAA with SAUDI ARAMCO Representative to avoid disrupting critical 24-hour
01/21/2016
services such as FAX machines and on-line data processing, computing,
DATE:
transmitting, and receiving equipment.
CONSTRUCTION
AGENCY
YAA
01/21/2016
3. Recheck loads after circuit changes during normal load period. Record all
DATE: load readings before and after changes and submit test records.
OPERATIONS
ASZ
4. Tolerance: Difference between phase loads exceeding 20 percent at any
01/21/2016
DATE: one panelboard is not acceptable. Rebalance and recheck as required to
CONTROL NUMBER
DATE:
END OF SECTION
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16470
YAA
ENGG CERT
7 of 7
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. This Section includes over current protective devices (OCPDs) rated 600V and
below and switching devices commonly used with them.
SBC 401 (Saudi Building Code Volume 4) and ANSI/NFPA 70 "National Electrical
Code," with the SBC 401 requirements prevailing over the NFPA 70 provisions.
DATE
B. Listing and Labeling: Provide products specified in this Section that are listed and
labeled.
NO.
REV
00
DISCIPLINE
ENGINEER 1. The terms "listed" and "labeled" shall be defined as they are in the National
ANP
01/21/2016
Electrical Code, Article 100.
DATE:
PROJECT
ENGINEER C. Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing
LSS
Laboratory" (NRTL) as defined in OSHA Regulation 1910.7.
01/21/2016
DATE:
CERTIFIED
YAA D. Single-Source Responsibility: Obtain similar OCPDs from a single manufacturer.
01/21/2016
DATE:
CONSTRUCTION
1.03 SUBMITTALS
AGENCY
YAA
01/21/2016
A. General: Submit the following in accordance with Conditions of Contract and
DATE:
Division 1 Specification Sections.
OPERATIONS
ASZ
01/21/2016
B. Product data for fuses, fusible switches, circuit breakers, and OCPD accessories
DATE: specified in this Section, including descriptive data and time-current curves for all
CONTROL NUMBER
protective devices and let- through current curves for those with current limiting
VERIFICATION
DATE:
A. Maintenance Stock Fuses: For types and ratings required, furnish spare fuses,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
amounting to one unit for every 5 installed units, but not less than one set of 3 of
(DCC) NO. _____________________
each kind.
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16475
YAA
ENGG CERT
1 of 6
PART 2 - PRODUCTS
LSS
2.01 MANUFACTURERS
00
rating is indicated.
VERIFICATION
EDSD
delay and instantaneous over current trip protection for each pole.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
values.
(DCC) NO. _____________________
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16475
YAA
ENGG CERT
2 of 6
F. Enclosure Panelboard Mounting: Suitable for panel mounting in panelboards
where indicated.
LSS
G. Enclosure for motor control center mounting: Provide individual mounting where
indicated.
I. Circuit Breakers with Solid-State Trip Devices: Provide indicated circuit breakers
with solid-state trip devices having the following features:
00
PART 3 - EXECUTION
DISCIPLINE
ENGINEER
ANP
3.01 INSTALLATION
01/21/2016
DATE:
PROJECT
ENGINEER A. Independently Mounted OCPDs: Locate as indicated and install in accordance
LSS
with manufacturer's written installation instructions.
01/21/2016
DATE:
CERTIFIED
YAA B. OCPDs in distribution equipment shall be factory installed.
01/21/2016
DATE:
3.02 IDENTIFICATION
CONSTRUCTION
AGENCY
YAA
01/21/2016
Identify components in accordance with Division 16 Section "Electrical Identification."
DATE: 3.03 CONTROL WIRING INSTALLATION
OPERATIONS
ASZ
A. Install wiring between OCPDs and control/indication devices as specified in
01/21/2016
DATE: Division 16 Section "Wires and Cables" for hard wired connections.
CONTROL NUMBER
VERIFICATION
3.04 CONNECTIONS
EDSD
DATE:
A. Check connectors, terminals, bus joints, and mountings for tightness. Tighten field-
BY:
SECTION 16475
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
3 of 6
YAA
ENGG CERT
3.05 GROUNDING
C. Labeling: Upon satisfactory completion of tests and related effort, apply a label to
tested components indicating test results, date, and responsible organization and
DATE
person.
NO.
REV
00
D. Schedule visual and mechanical inspections and electrical tests with at least one
DISCIPLINE
ENGINEER
week's advance notification.
ANP
01/21/2016
DATE: E. Pretesting: Upon completing installation of the system, perform the following
PROJECT
ENGINEER preparations for independent tests:
LSS
01/21/2016
DATE: 1. Make insulation resistance tests of OCPD buses, components, and
CERTIFIED
YAA
connecting supply, feeder, and control circuits.
01/21/2016
DATE: 2. Make continuity tests of circuits.
CONSTRUCTION
AGENCY
YAA
3. Provide set of Contract Documents to test personnel. Include full updating
01/21/2016
DATE: on final system configuration and parameters where they supplement or
OPERATIONS
differ from those indicated in original Contract Documents.
ASZ
01/21/2016
DATE: 4. Provide manufacturer's instructions for installation and testing of OCPDs to
CONTROL NUMBER
test personnel.
VERIFICATION
EDSD
F. Visual and mechanical inspection: Include the following inspections and related
work.
DATE:
BY:
discrepancies are found, test organization shall recommend final protective device
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16475
YAA
ENGG CERT
4 of 6
ratings and settings. Use accepted revised ratings or settings to make the final
system adjustments.
LSS
1. Inspect for defects and physical damage, NRTL labeling, and nameplate
compliance with current single line diagram.
manual.
manufacturer's instructions:
00
01/21/2016
phase. Insulation resistance less than 100 megohms is not acceptable.
DATE:
CONSTRUCTION
AGENCY 4. Use primary current injection to check performance characteristics of trip
YAA
units of insulated-case circuit breakers and molded-case breakers over
01/21/2016
DATE: 600-ampere frame size. Trip characteristics not falling within
OPERATIONS
manufacturer’s published time-current characteristic tolerance bands when
ASZ
adjusted to approved parameters are not acceptable. Perform the following
01/21/2016
DATE: tests:
CONTROL NUMBER
VERIFICATION
instructions.
b. Determine long – time delay at 300 percent pickup current.
DATE:
BY:
time.
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16475
YAA
ENGG CERT
5 of 6
5. Verify trip unit reset characteristics for insulated-case circuit breakers.
LSS
10. Check key and other interlock and safety devices for operation and
sequence. Make closing attempts on locked-open and opening attempts on
locked-closed devices including moveable barriers and shutters.
3.07 CLEANING
NO.
REV
00
Upon completion of installation, inspect OCPDs. Remove paint splatters and other spots,
DISCIPLINE
ENGINEER dirt, and debris. Touch up scratches and mars of finish to match original finish.
ANP
01/21/2016
DATE: 3.08 DEMONSTRATION
PROJECT
ENGINEER
LSS
A. Training: Arrange and pay for the services of factory-authorized service
01/21/2016
DATE: representatives to demonstrate OCPDs and train Owner's maintenance personnel.
CERTIFIED
YAA
01/21/2016
B. Conduct a minimum of one half day of training in operation and maintenance as
DATE:
specified under "Instructions to Owner Employees" in the "Project Closeout"
CONSTRUCTION
AGENCY
YAA
Section of these specifications. Include both classroom training and hands-on
01/21/2016
equipment operation and maintenance procedures.
DATE:
OPERATIONS
C. Schedule training with at least seven days' advance notification.
ASZ
01/21/2016
DATE:
CONTROL NUMBER
END OF SECTION
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16475
YAA
ENGG CERT
6 of 6
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
1. Low-voltage power.
2. Current-limiting.
3. Molded-case.
4. Solid-state trip.
5. Insulated case.
JO/EWO
01/21/2016 BI-01382
C. Refer to other Division-16 sections for wires/cables and connector work required in
conjunction with CB protective devices; not work of this section.
DATE
00
A. Codes and Standards: Comply with all applicable Codes and Standards including,
DISCIPLINE
ENGINEER but not limited to, those listed below:
ANP
01/21/2016
DATE:
1. Electrical Code Compliance: Comply with SBC 401 (Saudi Building Code
PROJECT
ENGINEER Volume 4), and the NEC, with the SBC 401 requirements prevailing over
LSS
the NEC provisions, as applicable to construction and installation of circuit
01/21/2016
DATE: breakers.
CERTIFIED
YAA
01/21/2016
3. NEMA Compliance: Comply with applicable requirements of NEMA
DATE:
Standard Publication No.'s AB 1, 2 and 3, SG 3 and 250.
OPERATIONS
ASZ
01/21/2016
4. ANSI/IEEE Compliance: Comply with applicable requirements of
DATE: ANSI/IEEE C37.13, C97.1 pertaining to low-voltage AC power circuit
CONTROL NUMBER
breakers.
VERIFICATION
EDSD
breakers of types, ratings, and capacities required, whose products have been in
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
1 of 7
C. Installer's Qualifications: Firm with at least 3 years of successful installation
experience on projects utilizing circuit- breaker devices similar to those required for
LSS
this project.
1.03 SUBMITTALS
A. Product Data: Submit manufacturer's product data and installation instructions for
circuit breakers.
ISSUED FOR IFC
DESCRIPTION
B. Wiring Diagrams: Submit wiring diagrams for circuit breakers and accessories
showing connections to electrical power feeders and associated equipment.
Differentiate between portions of wiring which are manufacturer-installed and
portions which are field- installed.
B. Store circuit breakers in original packaging and protect from weather and
NO.
REV
00
01/21/2016
A. Available Manufacturers: Subject to compliance with requirements, manufacturers
DATE: offering circuit-breaker products which may be incorporated in the work include, but
OPERATIONS
are not limited to, the following:
ASZ
01/21/2016
DATE: 1. Manufacturers: Subject to compliance with requirements, provide circuit-
CONTROL NUMBER
breaker devices of one of the following (for each type and rating of circuit
VERIFICATION
breaker):
EDSD
DATE:
Airpax Corporation.
APPROVAL/CERTIFICATION REQUIREMENTS,
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
2 of 7
Crouse-Hinds Div; Cooper Industries Co.
Cutler-Hammer Div; Eaton Corp.
LSS
Square D Company.
Westinghouse Electric Corp.
envelope size rating 800 amperes; frame size rating of 800, 100 percent equipment
rated, continuous current rating of 400 amperes, 50,000 RMS symmetrical
NO.
REV
00
amperes interrupting capacity rating; and with 24-volts closing relays for operating
DISCIPLINE
ENGINEER breakers. Provide bolted type stationary-mounted breaker elements with NEMA
ANP
Type 3R raintight enclosures. Construct with ground-fault protection devices as
01/21/2016
DATE: integral part of breakers, with delay of 0.21 seconds at 225 amperes. Construct
PROJECT
ENGINEER breaker with solid-state over current trip devices; and equip circuit breakers with
LSS
solid-state controls and programming units possessing the following operating
01/21/2016
DATE: features:
CERTIFIED
YAA
01/21/2016
1. Adjustable current setting.
DATE:
CONSTRUCTION
AGENCY
YAA
2. Adjustable long-time pickup and delay.
01/21/2016
DATE: 3. Adjustable short-time pickup and delay.
OPERATIONS
ASZ
4. Adjustable instantaneous pickup.
01/21/2016
DATE:
CONTROL NUMBER
C. Circuit Breaker Accessories: Provide the following air circuit breaker accessories:
(DCC) NO. _____________________
10-01382-0008-0001
1. Shunt trip.
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
3 of 7
2. Undervoltage release.
LSS
4. Auxiliary contacts.
5. Enclosure-mounted interlock.
ISSUED FOR IFC
DESCRIPTION
Calibrate trip elements for 40 deg C ambient temperature. Select circuit breakers
with mechanical screw type lugs for use with copper conductors.
DATE
00
01/21/2016
DATE: 1. Shunt trip.
OPERATIONS
ASZ
2. Auxiliary contacts.
01/21/2016
DATE:
CONTROL NUMBER
3. Alarm switch.
VERIFICATION
EDSD
4. Undervoltage trip.
DATE:
BY:
F. Solid-State Trip Circuit Breakers: Provide solid-state trip circuit breakers rated 800
amperes, 480-volts, 60 Hz, 3-poles, with 100,000 RMS symmetrical ampere
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
interrupting ratings. Construct breakers with ampere setting adjustment knobs for
(DCC) NO. _____________________
changing current carrying capability of units, and with ground- fault protection
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
4 of 7
components with external neutral current transformer (CT). Provide electronic
components for timing and monitoring internal currents and for initiating automatic
LSS
tripping action. Construct with trip-free mechanisms, and with positive handle
indication. Provide push-to-trip button on cover for mechanical tripping circuit
breakers. Construct breakers for mounting in any physical position and operating
in an ambient temperature of 40 deg C. Select breakers with mechanical screw
type removable connectors, AL/CU rated, and with NEMA Type 1 general purpose
enclosures.
ISSUED FOR IFC
DESCRIPTION
00
01/21/2016
7. Local and remote target indication.
DATE:
CONSTRUCTION
AGENCY
YAA
H. Circuit Breaker Accessories: Provide the following insulated case circuit-breaker
01/21/2016
accessories.
DATE:
OPERATIONS
1. Shunt trip.
ASZ
01/21/2016
DATE: 2. Undervoltage release.
CONTROL NUMBER
VERIFICATION
DATE:
4. Auxiliary contacts.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
5. Enclosure-mounted interlock.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
5 of 7
PART 3 - EXECUTION
LSS
3.01 EXAMINATION
Examine areas and conditions under which circuit breakers are to be installed and notify
Contractor in writing of conditions detrimental to proper completion of the Work. Do not
proceed with the Work until unsatisfactory conditions have been corrected in a manner
acceptable to the Installer.
ISSUED FOR IFC
DESCRIPTION
00
01/21/2016
Inspect circuit-breaker operating mechanisms for malfunctioning and, where necessary,
DATE: clean and adjust units for free mechanical movement.
OPERATIONS
ASZ
3.04 GROUNDING
01/21/2016
DATE:
CONTROL NUMBER
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
6 of 7
3.05 FIELD QUALITY CONTROL
LSS
Upon completion of installation and after circuitry has been energized, demonstrate
capability and compliance of system with requirements. Where possible, correct
malfunctioning units at site, then retest to demonstrate compliance; otherwise, remove and
replace with new units, and proceed with retesting. Testing and retesting at no cost to
Owner.
ISSUED FOR IFC
DESCRIPTION
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16476
YAA
ENGG CERT
7 of 7
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. Extent, location, and details of electrical poles and standards work are indicated on
drawings and in schedules.
B. Applications of lighting poles and standards specified in this section include the
following:
3. Promenades/plazas.
DATE
4. Parks.
5. Pedestrian walkways.
NO.
REV
00
DISCIPLINE
ENGINEER 6. Building entrances.
ANP
01/21/2016
DATE: C. Excavation and backfilling for poles, standards, and foundations are specified in
PROJECT
ENGINEER Division 2.
LSS
01/21/2016
DATE: D. Concrete for embedding poles, and for pole foundations and footings is specified in
CERTIFIED
YAA Division 3.
01/21/2016
DATE:
CONSTRUCTION
E. Wire/cables, raceways, and electrical boxes and fittings which are required in
AGENCY
YAA
connection with electrical poles and standards are specified in Division-16 Basic
01/21/2016
Materials and Methods sections, "Wires and Cables," "Raceways," and "Electrical
DATE:
Boxes and Fittings." Transformers are specified in another Division 16 section.
OPERATIONS
ASZ
01/21/2016
Refer to other Division-16 sections for cables/wires, raceways, transformers, and
DATE: electrical boxes and fittings work which are required in connection with electrical
CONTROL NUMBER
F. Exterior lighting fixtures (luminaries) and brackets which are required in connection
DATE:
with electrical poles and standards are specified in another Division-16 section,
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
1 of 8
1.02 QUALITY ASSURANCE
LSS
00
01/21/2016
DATE: 7. NEMA Compliance: Comply with NEMA Stds Pub/No's. LE 2 and TT 1
CONTROL NUMBER
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
2 of 8
1.03 SUBMITTALS
LSS
B. Shop Drawings: Submit shop drawings of electrical poles and standards, including
mast arms and wire/cable connections which are custom work.
ISSUED FOR IFC
DESCRIPTION
C. Wiring Diagrams: Submit wiring diagrams for electrical poles and standards
showing connections to electrical power panel feeders, switches, dimmers, and
controllers. Differentiate between portions of electrical wiring which are
manufacturer-installed and portions which are field-installed.
D. Samples: Submit one complete unit and component for each type of electrical pole
and standard specified.
B. Store electrical pole and standard products, and fittings in original cartons in well-
NO.
REV
00
PART 2 - PRODUCTS
VERIFICATION
EDSD
2.01 MANUFACTURERS
DATE:
BY:
offering electrical poles and standards which may be incorporated in the work
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
3 of 8
B. Manufacturers: Subject to compliance with requirements, provide products of one
of the following (for each type of pole or standard).
LSS
1. Standards
Koppers Company.
DESCRIPTION
2. Metal Poles
JO/EWO
01/21/2016 BI-01382
DATE:
01/21/2016 4. Reinforced Concrete Poles
CONSTRUCTION
AGENCY
YAA Ameron Pole Products Co.
01/21/2016 Centrecon, Inc.
DATE:
OPERATIONS
Dura-Stress Inc. Raymond International Inc.
ASZ Union Metal Mfg Co.
01/21/2016 Utility Vault Co.
DATE:
CONTROL NUMBER
VERIFICATION
5. Pole Hardware
EDSD
Hercules, Inc.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
4 of 8
Lithonia Lighting Div; National Services Industries, Inc.
McGraw-Edison Co.
LSS
B. Utility-Type Wood Lighting Poles: Provide utility-type tapered solid wood lighting
poles, with single crossarms, of sizes and type materials indicated; pressure-treat
JO/EWO
01/21/2016 BI-01382
including guy-wires, anchors, and eye bolts, of types recommended by wood pole
manufacturer, of sizes and materials needed to fulfill loading erection application
NO.
REV
00
requirements.
DISCIPLINE
ENGINEER
ANP
D. Prestressed Concrete Lighting Standards: Provide prestressed concrete, raceway-
01/21/2016
DATE: type, lighting poles and standards, of sizes and types indicated, comprised of
PROJECT
ENGINEER shafts and brackets, and construct with the following construction features:
LSS
01/21/2016
DATE: 1. Configuration: Embedded type base and reinforcing sleeve with hand and
CERTIFIED
YAA cable entrance holes where indicated.
01/21/2016
DATE:
2. Configuration: Anchor base type with hand hole and cover where indicated.
CONSTRUCTION
AGENCY
YAA
01/21/2016
3. Configuration: Transformer base type with access door and cover.
DATE:
OPERATIONS
E. Prestressed Concrete Lighting Standard Accessories: Provide accessories for
ASZ
prestressed concrete lighting standards, including anchor bolts, as recommended
01/21/2016
DATE: by lighting standard manufacturer, of sizes and materials needed to fulfill loading
CONTROL NUMBER
standards, of sizes and types indicated, comprised of shafts and tenon joints.
BY:
base access doors; and construct of the following materials and additional
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
5 of 8
construction features:
LSS
5. Material: Bronze.
8. Configuration: Embedded type base and reinforcing sleeve with hand and
cable entrance holes where indicated.
JO/EWO
01/21/2016 BI-01382
9. Configuration: Anchor base type with hand hole and cover where indicated.
DATE
10. Configuration: Transformer base type with access door and cover.
NO.
REV
00
I. Metal Pole Accessories: Provide accessories for metal poles, including crossarms,
EDSD
bolts, lifting eyes, and nuts as recommended by pole manufacturer, of sizes and
materials needed to meet erection and loading application requirements.
DATE:
BY:
sizes and types indicated. Design poles to withstand loads developed by 100 MPH
(DCC) NO. _____________________
wind pressure, as adjusted for height above ground level, structural shapes and
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
6 of 8
cable/wire loading. Centrifugally spin concrete to attain 28-day strength of 7000
psi. Fasten galvanized steel base plates to pole by using both the prestressing
LSS
and reinforcing steel to transfer load on pole to anchor bolts. Embed base plate in
concrete and cast as integral part of pole. Provide adequately sized cable
entrance holes and handholes, where indicated, and with matching plate to cover
above-ground access hole.
concrete poles, including anchor bolts and nuts, crossarms, climbing rungs, and
pole tops as recommended by pole manufacturer, of sizes and materials needed to
meet erection and loading application requirements.
PART 3 - EXECUTION
3.01 EXAMINATION
Examine areas and conditions under which pole and standard equipment and components
are to be installed, and substrate which will support equipment. Notify Contractor in
JO/EWO
01/21/2016 BI-01382
writing of conditions detrimental to proper completion of the Work. Do not proceed with
the Work until unsatisfactory conditions have been corrected in a manner acceptable to
the Installer.
DATE
00
DISCIPLINE
ENGINEER A. Install pole and standard units and products as indicated, in accordance with
ANP
manufacturer's written instructions, applicable requirements of SBC 401, the NEC,
01/21/2016
DATE: NESC and NEMA Standards, and with recognized Industry practices to ensure that
PROJECT
ENGINEER roadway and parking area lighting equipment fulfill requirements.
LSS
01/21/2016
DATE: B. Utilize belt slings or rope (not chain or cable) to protect finishes when raising and
CERTIFIED
YAA setting finished poles and standards.
01/21/2016
DATE:
C. Where poles and standards are indicated to be embedded in soil, set to depth
CONSTRUCTION
AGENCY
YAA
required for adequate structural support, but not less than minimum 5'-6" below
01/21/2016
finish grade.
DATE:
OPERATIONS
D. Set poles and standards plumb. Support adequately during backfilling, or when
ASZ
anchoring them to the foundations.
01/21/2016
DATE:
CONTROL NUMBER
E. Provide sufficient space encompassing hand access and cable entrance holes for
VERIFICATION
DATE:
supports, including poles/standards; and ensure that installed fixtures are plumb
APPROVAL/CERTIFICATION REQUIREMENTS,
and level.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
G. Tighten connectors and terminals, including screws and bolts, in accordance with
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
7 of 8
equipment manufacturer's published torque tightening values for equipment
connectors. Where manufacturer's torquing requirements are not indicated, tighten
LSS
3.03 GROUNDING
Provide equipment grounding connections for poles and standard as indicated. Tighten
ISSUED FOR IFC
DESCRIPTION
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16503
YAA
ENGG CERT
8 of 8
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
C. High-intensity-discharge (HID)
2. Metal Halide
JO/EWO
01/21/2016 BI-01382
3. LED
DATE
D. Applications of exterior lighting fixtures required for this project include the
following:
NO.
REV
00
DISCIPLINE
ENGINEER 1. Outdoor flood lighting
ANP
01/21/2016
DATE: 2. Outdoor Alley Lighting
PROJECT
ENGINEER
LSS 3. Landscape Pollard Lights
01/21/2016
DATE:
CERTIFIED
YAA
1.02 QUALITY ASSURANCE
01/21/2016
DATE:
A. Manufacturer's Qualifications: Firms regularly engaged in manufacture of exterior
CONSTRUCTION
AGENCY building lighting fixtures of types and ratings required, whose products have been
YAA
01/21/2016
in satisfactory use in similar service for not less than 5 years.
DATE:
OPERATIONS
B. Installer's Qualifications: Firm with at least 3 years of successful installation
ASZ
experience on projects with exterior lighting fixture work similar to that required for
01/21/2016
DATE: project.
CONTROL NUMBER
VERIFICATION
DATE:
401 (Saudi Building Code Volume 4) and NEC Articles 225, 250, 410, and
APPROVAL/CERTIFICATION REQUIREMENTS,
lighting fixtures, with SBC 401 requirements prevailing over the NEC
(DCC) NO. _____________________
provisions.
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16512
YAA
ENGG CERT
1 of 5
2. NEMA Compliance: Comply with applicable requirements of NEMA Stds
Pub/No. LE 2 pertaining lighting equipment.
LSS
3. IES Compliance: Comply with IES RP-8, 19, 20 and PB-15 pertaining to
exterior, parking, and roadway lighting practices and fixtures.
1.03 SUBMITTALS
B. Shop Drawings: Submit fixture shop drawings in booklet form with separate sheet
for each fixture, assembled in "luminaire type" alphabetical or numerical order, with
DATE
00
C. Wiring Diagrams: Submit wiring diagrams for exterior lighting fixtures showing
DISCIPLINE
ENGINEER connections to electrical power panels, switches, dimmers, controllers, and
ANP
feeders. Differentiate between portions of wiring which are manufacturer-installed
01/21/2016
DATE: and portions which are field-installed.
PROJECT
ENGINEER
LSS
D. Samples: Submit one complete operating unit for each type of exterior lighting
01/21/2016
DATE: fixture specified.
CERTIFIED
YAA
01/21/2016
E. Illumination Data: Provide isofootcandle (isolux) plot diagram of footcandles on
DATE:
horizontal pavement surface which shows composite values of luminance projected
CONSTRUCTION
AGENCY
YAA
from the arrangement of light sources from indicated fixture locations and heights.
01/21/2016
Show on the graphic plots the locations, spacings and heights of luminaries.
DATE:
OPERATIONS
1.04 DELIVERY, STORAGE, AND HANDLING
ASZ
01/21/2016
DATE: A. Deliver exterior lighting fixtures in factory-fabricated containers or wrappings, which
CONTROL NUMBER
B. Store exterior lighting fixtures in original wrappings in a clean dry place. Protect
from weather, dirt, fumes, water, construction debris, and damage.
DATE:
BY:
C. Handle exterior lighting fixtures carefully to prevent damage, breaking, and scoring.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
Do not install damaged fixtures or components; remove units from site and replace
(DCC) NO. _____________________
with new.
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16512
YAA
ENGG CERT
2 of 5
1.05 SEQUENCING AND SCHEDULING
LSS
A. Coordinate with other electrical work including wires/cables, electrical boxes and
fittings, and raceways, to properly interface installation of exterior lighting fixtures
with other work.
1.06 MAINTENANCE
A. Maintenance Data: Submit maintenance data and parts list for each exterior
lighting fixture and accessory; including "trouble- shooting" maintenance guide.
Include that data, product data, and shop drawings in a maintenance manual; in
accordance with requirements of Division 1.
B. Extra Stock:
JO/EWO
01/21/2016 BI-01382
Furnish stock or replacement lamps amounting to 15 percent (but not less than one
lamp in each case) of each type and size lamp used in each type fixture. Deliver
replacement stock as directed to SAUDI ARAMCO storage space, and obtain
DATE
receipt.
NO.
REV
00
PART 2 - PRODUCTS
DISCIPLINE
ENGINEER
ANP
2.01 MANUFACTURERS
01/21/2016
DATE:
PROJECT
ENGINEER A. Available Manufacturers: Subject to compliance with requirements, manufacturers
LSS
offering products which may be incorporated in the work include, but are not limited
01/21/2016
DATE: to, the following:
CERTIFIED
YAA
01/21/2016
B. Manufacturers: Subject to compliance with requirements, provide products of one
DATE:
of the following (for each type of exterior lighting fixture).
CONSTRUCTION
AGENCY
YAA
1. Exterior Lighting Fixtures:
01/21/2016
DATE:
OPERATIONS
Appleton Electric Co.
ASZ
Crouse-Hinds Lighting Products Div; Cooper Industries Inc.
01/21/2016
DATE: Devoe Lighting Corp.
CONTROL NUMBER
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16512
YAA
ENGG CERT
3 of 5
2. High-Intensity Ballasts:
LSS
A. General: Provide lighting fixtures, of sizes, types and ratings indicated; complete
with, but not limited to, housings, energy efficient ballasts, starters and wiring.
B. Wiring: Provide electrical wiring within fixtures which are suitable for connection to
branch circuit wiring as follows:
00
D. Lamps:
DISCIPLINE
ENGINEER
ANP
1. Provide high pressure sodium lamps in wattages indicated.
01/21/2016
DATE:
PROJECT
ENGINEER 2. Provide metal halide lamps in wattages indicated.
LSS
01/21/2016
DATE: PART 3 - EXECUTION
CERTIFIED
YAA
01/21/2016
3.01 EXAMINATION
DATE:
CONSTRUCTION
AGENCY A. Examine areas and conditions under which lighting fixtures are to be installed, and
YAA
substrate which will support lighting fixtures. Notify CONTRACTOR in writing of
01/21/2016
DATE: conditions detrimental to proper completion of the Work. Do not proceed with the
OPERATIONS
Work until unsatisfactory conditions have been corrected in a manner acceptable to
ASZ
Installer.
01/21/2016
DATE:
CONTROL NUMBER
and the NEC, NECA's "Standard of Installation", NEMA standards, and with
recognized Industry practices to ensure that lighting fixtures fulfill requirements.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B. Tighten connectors and terminals, including screws and bolts, in accordance with
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16512
YAA
ENGG CERT
4 of 5
equipment manufacturer's published torque tightening values for equipment
LSS
3.03 GROUNDING
A. Replace defective and burned out lamps for a period of one year following the Date
JO/EWO
01/21/2016 BI-01382
of Substantial Completion.
which are observed to be noticeably dimmed after Contractor's use and testing, as
judged by the Company Representative.
NO.
REV
00
DISCIPLINE
ENGINEER C. Refer to Division-1 sections for the replacement/restoration of lamps in exterior
ANP
lighting fixtures, where used for temporary lighting prior to Date of Substantial
01/21/2016
DATE: Completion.
PROJECT
ENGINEER
LSS 3.05 ADJUSTING AND CLEANING
01/21/2016
DATE:
CERTIFIED A. Aim adjustable lighting fixtures and lamps in night test of system. Verify that
YAA
01/21/2016
measured illuminance values comply with isolux plot diagram values.
DATE:
CONSTRUCTION
AGENCY B. Clean lighting fixtures of dirt and debris upon completion of installation.
YAA
01/21/2016
DATE: C. Protect installed fixtures from damage during construction period.
OPERATIONS
ASZ
3.06 DEMONSTRATION
01/21/2016
DATE:
CONTROL NUMBER
END OF SECTION
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16512
YAA
ENGG CERT
5 of 5
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. Extent, location, and details of interior lighting fixture work are indicated on
drawings and in schedules.
1. High-intensity-discharge (HID)
2. High-Pressure Sodium.
4. Fluorescent.
DATE
5. Incandescent.
NO.
REV
00
6. LED
DISCIPLINE
ENGINEER
ANP
01/21/2016
1.02 QUALITY ASSURANCE
DATE:
PROJECT
ENGINEER A. Manufacturer's Qualifications: Firms regularly engaged in manufacture of interior
LSS
lighting fixtures of sizes, types and ratings required, whose products have been in
01/21/2016
DATE: satisfactory use in similar service for not less than 5 years.
CERTIFIED
YAA
01/21/2016
1. Electrical Code Compliance: Comply with applicable requirements of SBC
DATE: 401 (Saudi Building Code Volume 4) and NEC Articles 220, 410, and 510
CONTROL NUMBER
fixtures, with the requirements of SBC 401 prevailing over the NEC
EDSD
provisions.
DATE:
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
1 of 7
selection of illuminance values for interior and exterior residential lighting;
IES RP-1 pertaining to office lighting practices, and RP-15 regarding
LSS
5. CBM Labels: Provide fluorescent lamp ballasts which comply with Certified
Ballast Manufacturers Association standards and carry the CBM label.
1.03 SUBMITTALS
B. Shop Drawings: Submit layout drawings of interior lighting fixtures and their spatial
relationship to each other. In addition, submit fixture shop drawings in booklet form
JO/EWO
01/21/2016 BI-01382
with separate sheet for each fixture, assembled in "luminaire type" alphabetical or
numerical order, with proposed fixture and accessories clearly indicated on each
sheet. Submit details indicating compatibility with ceiling grid system.
DATE
C. Wiring Diagrams: Submit wiring diagrams for interior lighting fixtures showing
NO.
REV
00
soiling, extreme temperatures, humidity, laid flat and blocked off ground.
EDSD
DATE:
B. Handle interior lighting fixtures carefully to prevent damage, breaking, and scoring
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
2 of 7
1.05 SEQUENCING AND SCHEDULING
LSS
A. Coordinate with other work including wires/cables, electrical boxes and fittings, and
raceways, to properly interface installation of interior lighting fixtures with other
Work.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
00
DATE:
01/21/2016 2.02 FIXTURES
CONTROL NUMBER
VERIFICATION
A. General: Provide lighting fixtures, of sizes, types and ratings indicated; complete
EDSD
with, but not limited to, housings, energy- efficient lamps, lamp holders, reflectors,
energy efficient ballasts, starters and wiring. Ship fixtures factory-assembled, with
DATE:
BY:
parts required for a complete installation. Design fixtures with concealed hinges
and catches, with metal parts grounded as common unit, and so constructed as to
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
3 of 7
B. Wiring: Provide electrical wiring within fixture suitable for connecting to branch
circuit wiring as follows:
LSS
F. Lamps:
DATE
00
DATE:
01/21/2016 3. Provide Metal halide lamp in wattages indicated.
PROJECT
ENGINEER
LSS 4. Provide LED lamp in wattages indicated.
01/21/2016
DATE:
CERTIFIED G. Interior Lighting Fixture Types:
YAA
01/21/2016
DATE: General: Various fixture types required are indicated below. Fixtures must comply
CONSTRUCTION
AGENCY
with minimum requirements as stated herein. Review architectural drawings and
YAA specifications to verify ceiling types, modules, suspension systems appropriate to
DATE:
01/21/2016
installation.
OPERATIONS
ASZ 1. Fluorescent Fixture:
01/21/2016
DATE:
a. Recessed Mounted: 600 x 600 mm and 600 x 2300 mm fully
CONTROL NUMBER
VERIFICATION
for use with four-18watt and four-36 watt respectively energy saving,
cool white lamps for operation on 230 volts, and proper trim for
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
4 of 7
direct type fixtures with pre-treated CRS sheet steel painted stove
enamelled in white with overall efficiency of not less than 70% of
LSS
PART 3 - EXECUTION
DATE
3.01 EXAMINATION
NO.
REV
00
DISCIPLINE
ENGINEER A. Examine areas and conditions under which lighting fixtures are to be installed, and
ANP
substrate for supporting lighting fixtures. Notify Saudi Aramco Representative in
01/21/2016
DATE: writing of conditions detrimental to proper completion of the work. Do not proceed
PROJECT
ENGINEER with work until unsatisfactory conditions have been corrected in manner acceptable
LSS
to Installer.
01/21/2016
DATE:
CERTIFIED
YAA 3.02 INSTALLATION OF INTERIOR LIGHTING FIXTURES
01/21/2016
DATE:
A. Install interior lighting fixtures at locations and heights as indicated, in accordance
CONSTRUCTION
AGENCY
YAA
with fixture manufacturer's written instructions, applicable requirements of NEC,
01/21/2016
NECA's "Standard of Installation", NEMA standards, and with recognized industry
DATE: practices to ensure that lighting fixtures fulfill requirements.
OPERATIONS
ASZ
B. Provide fixtures and/or fixture outlet boxes with hangers to properly support fixture
01/21/2016
DATE: weight. Submit design of hangers, method of fastening, other than indicated or
CONTROL NUMBER
C. Install flush mounted fixtures to eliminate light leakage between fixture frame and
finished surface.
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
D. Provide plaster frames for recessed fixtures installed in other than suspended grid
type acoustical ceiling systems. Brace frames temporarily to prevent distortion
(DCC) NO. _____________________
10-01382-0008-0001
during handling.
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
5 of 7
E. For air supply type fixtures, retain side slot closures in place for adjustment by
Balancing Contractor.
LSS
F. Fasten fixtures securely to indicated structural supports; and ensure that pendant
fixtures are plumb and level. Provide individually mounted pendant fixtures longer
than 2 feet with twin stem hangers. Provide stem hanger with ball aligners and
provisions for minimum 1" vertical adjustment. Mount continuous rows of fixtures
with an additional stem hanger greater than number of fixtures in the row.
ISSUED FOR IFC
DESCRIPTION
G. Tighten connectors and terminals, including screws and bolts, in accordance with
equipment manufacturer's published torque tightening values for equipment
connectors. Where manufacturer's torquing requirements are not indicated, tighten
connectors and terminals to comply with tightening torques specified in UL
Standards 486A and B, and the National Electrical Code.
H. Support surface mounted fixtures greater than 2 feet in length at a point in addition
to the outlet box fixture stud.
JO/EWO
01/21/2016 BI-01382
A. Replace defective and burned out lamps for a period of one year following the Date
DATE
of Substantial Completion.
NO.
REV
00
01/21/2016
C. Furnish stock or replacement lamps amounting to 15%, but not less than 4 lamps
DATE:
in each case, of each type and size lamp used in each type fixture. Deliver
CONSTRUCTION
AGENCY
YAA
replacement stock as directed to Owner's storage space.
01/21/2016
DATE: 3.04 ADJUSTING AND CLEANING
OPERATIONS
ASZ
A. Clean interior lighting fixtures of dirt and construction debris upon completion of
01/21/2016
DATE: installation. Clean fingerprints and smudges from lenses.
CONTROL NUMBER
VERIFICATION
3.05 GROUNDING
DATE:
BY:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
6 of 7
3.06 DEMONSTRATION
LSS
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16515
YAA
ENGG CERT
7 of 7
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. This Section includes emergency light sets, exit fixtures with integral emergency
battery backup, and emergency fluorescent fixture power supplies with integral
battery backup.
B. Related Sections: The following Section contain requirements that relate to this
Section:
Division 16 Section "Interior Lighting Fixtures" for regular fixtures that may be
connected to emergency circuits to provide emergency lighting.
JO/EWO
01/21/2016 BI-01382
00
DISCIPLINE
ENGINEER B. UL Compliance: Emergency lighting fixtures shall be UL listed and labeled.
ANP
01/21/2016
DATE: C. NFPA Compliance: Comply with applicable requirements of NFPA 99, "Health
PROJECT
ENGINEER Care Facilities" and NFPA 101, "Life Safety Code."
LSS
01/21/2016
DATE: D. Local Code Compliance: Comply with applicable local codes and regulations for
CERTIFIED
YAA emergency lighting and exit signage including, but not limited to, colors and letter
01/21/2016 heights for exit signs.
DATE:
CONSTRUCTION
AGENCY
YAA
1.03 SUBMITTALS
01/21/2016
DATE:
A. Product data for each type of emergency lighting unit specified. Assemble in
OPERATIONS
ASZ
booklet form with separate sheet for each fixture, arranged in unit "type,"
01/21/2016
alphabetical, or numerical order, with proposed fixture and accessories clearly
DATE: indicated on each sheet.
CONTROL NUMBER
VERIFICATION
DATE:
C. Maintenance data for units specified, for inclusion in Operating and Maintenance
BY:
submittal and updated final versions of manuals with closeout procedures specified
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16535
YAA
ENGG CERT
1 of 5
D. Installation instructions written by manufacturers for all specified products.
LSS
A. Furnish stock of replacement lamps amounting to 15 percent (but not less than one
lamp in each case) of each type and size lamp used in each type unit.
PART 2 - PRODUCTS
2.01 MANUFACTURERS
to the following:
following:
NO.
REV
00
1. Chloride Systems
DISCIPLINE
ENGINEER
ANP
Cooper Industries, Inc.
01/21/2016
DATE: Dual-Lite, Inc.
PROJECT
ENGINEER Holophane Lighting
LSS
Hubbell, Inc. Legion Lighting Co., Inc.
01/21/2016
DATE: Lithonia Lighting
CERTIFIED
YAA Thomas Industries, Inc.
01/21/2016
Saudi Lighting Co.
DATE:
Philips
CONSTRUCTION
AGENCY
YAA
National Lighting Company
01/21/2016
DATE: 2.02 EMERGENCY LIGHT SET, EXIT SIGN
OPERATIONS
ASZ
A. Self-contained, a.c. battery-illuminated exit sign unit, universal mounting with
01/21/2016
DATE: downlight.
CONTROL NUMBER
VERIFICATION
DATE:
indicated.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
2. Faceplate: High-impact, UL 94 V-O rated, plastic with snap- out arrows and
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16535
YAA
ENGG CERT
2 of 5
3. Mounting provisions shall suit individual installation conditions. Battery:
LSS
00
DISCIPLINE
ENGINEER 1. Arrange unit with test switch and LED indicator light, visible and accessible
ANP
without opening fixture or entering ceiling space.
01/21/2016
DATE:
PROJECT
ENGINEER 2. Battery: Sealed, maintenance-free, nickel-cadmium type, with normal 10-
LSS year life, minimum.
01/21/2016
DATE:
CERTIFIED 3. Charger: Fully automatic, solid-state, constant-current type.
YAA
01/21/2016
DATE: 4. Operation: Relay turns two lamps on automatically when supply circuit
CONSTRUCTION
AGENCY voltage drops to 80 percent of nominal or below. Lamps operate for
YAA
duration of outage, up to 1.5 hours. When normal voltage is restored,
01/21/2016
DATE: battery is automatically recharged.
OPERATIONS
ASZ
B. External Type: For designated fluorescent fixtures, provided under Division 16
01/21/2016
DATE: Section "Lighting Fixtures," provide external self-contained, modular, battery-
CONTROL NUMBER
inverter unit.
VERIFICATION
EDSD
1. Arrange unit with test switch and LED indicator light, visible and accessible
without entering ceiling space.
DATE:
BY:
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16535
YAA
ENGG CERT
3 of 5
4. Operation: Relay turns two lamps of associate fixture on automatically
when supply circuit voltage drops to 80 percent of nominal or below.
LSS
PART 3 - EXECUTION
3.01 INSTALLATION
ISSUED FOR IFC
DESCRIPTION
A. Setting and Securing: Set units plumb, square, and level with ceiling and walls and
secure in accordance with manufacturer's written instructions and approved shop
drawings. Conform to the requirements of NFPA 70.
minimum of four rods or wires per fixture and located not more than 6 inches from
fixture corners. For fixtures smaller than the ceiling grid, install a minimum of four
rods or wires per fixture and locate at corner of the ceiling grid in which the fixture
DATE
00
support fixtures independently with at least two 3/4-inch metal channels spanning
DISCIPLINE
ENGINEER and secured to the ceiling tees. Rods or wires for Section "Acoustical Treatment."
ANP
Install support clips for recessed fixtures, securely fastened to ceiling grid
01/21/2016
DATE: members, at or near each fixture corner.
PROJECT
ENGINEER
LSS D. Lamping and Connection: Lamp units in accordance with manufacturer's
01/21/2016
DATE: instructions. Make external wiring connections required for proper functioning.
CERTIFIED
YAA
01/21/2016
E. Coordinate with other electrical installations as appropriate for proper installation of
DATE: emergency lighting fixtures.
CONSTRUCTION
AGENCY
YAA
3.02 ADJUSTING AND CLEANING
01/21/2016
DATE:
OPERATIONS A. Clean emergency units light set upon completion of installation.
ASZ
DATE:
01/21/2016
B. Adjust aimable fixtures to provide light intensities in egress paths.
CONTROL NUMBER
VERIFICATION
3.03 GROUNDING
EDSD
Standard 486A.
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16535
YAA
ENGG CERT
4 of 5
3.04 FIELD QUALITY CONTROL
LSS
A. Tests: After emergency lighting units have been installed and building circuits have
been energized with normal power source, apply and interrupt electrical energy to
demonstrate proper operation. Remove and replace malfunctioning units with new
units and proceed with retesting. Give the Company Representative advance
notice of dates and times for all field tests. Provide instruments as required to
make positive observation of test results. Include the following in tests:
ISSUED FOR IFC
DESCRIPTION
1. Duration of supply.
Cables."
NO.
REV
D. Lamp Replacement: Prior to tests, install new lamps in emergency lighting units.
00
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16535
YAA
ENGG CERT
5 of 5
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
1.03 SUBMITTALS
JO/EWO
01/21/2016 BI-01382
associated components including, but not limited to, types, sizes, basic ampere
ratings, and control voltages.
NO.
REV
00
labeled.
EDSD
DATE:
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16660
YAA
ENGG CERT
1 of 5
3. NEMA Compliance: Comply with NEMA Stds Pub No.'s PB 2.2 and AB 1,
pertaining to construction and installation of ground- fault protection devices
LSS
provisions.
containers.
NO.
REV
00
B. Store ground-fault protection units indoors in clean, dry space. Retain units, until
DISCIPLINE
ENGINEER installed, in original cartons and protect from dirt, weather, construction debris and
ANP
traffic.
01/21/2016
DATE:
PROJECT
ENGINEER C. Handle ground-fault protection units properly to avoid abrasing, cracking, and
LSS
breaking.
01/21/2016
DATE:
CERTIFIED
YAA PART 2 - PRODUCTS
01/21/2016
DATE:
2.01 MANUFACTURERS:
CONSTRUCTION
AGENCY
YAA
01/21/2016
A. Available Manufacturers: Subject to compliance with requirements, manufacturers
DATE: offering ground-fault protection units which may be incorporated in the work
OPERATIONS
include, but are not limited to, the following:
ASZ
01/21/2016
DATE: 1. Manufacturers: Subject to compliance with requirements, provide ground-
CONTROL NUMBER
fault protection units of one of the following (for each type of unit):
VERIFICATION
EDSD
Allen-Bradley Co.
DATE:
Gould Inc.
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
Square D Co.
(DCC) NO. _____________________
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16660
YAA
ENGG CERT
2 of 5
2.02 GROUND-FAULT PROTECTION SYSTEMS AND DEVICES:
LSS
DISCIPLINE panels, and low-voltage power circuit-breakers; select units which function
ENGINEER
ANP properly in conjunction with other elements of GFP system. Provide
DATE:
01/21/2016 ground-fault current sensitivity and time- current response characteristics as
PROJECT indicated. Construct system components and devices with the following
ENGINEER
LSS
features:
01/21/2016
DATE:
CERTIFIED D. Current Sensors: Provide zero-sequence current sensors with rectangular
YAA windows for feeder and branch devices and ground return sensors for main service
DATE:
01/21/2016 device; inputs compatible to relay. Construct sensor of split-core construction which
CONSTRUCTION can be opened to expedite its installation or removal without disturbing the
AGENCY
YAA electrical conductors being encompassed. Provide test windings in sensor for
01/21/2016 testing the operation of ground-fault protection unit including sensor pick-up, relay
DATE:
OPERATIONS
and circuit protection devices.
ASZ
01/21/2016 E. Ground-Fault Relay: Provide solid-state ground-fault signaling relay with silicon
DATE:
controlled rectifier (SCR) output, to be used with electric or shunt trip, which
CONTROL NUMBER
VERIFICATION
capable of sensing ground currents which causes the interruptor to open after
DATE:
current reaches a magnitude value for time period indicated. Provide relay with
BY:
currents from 100 to 2300 amperes, with calibrated dial to show pick-up point
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
15-seconds and which also prevents tampering with setting after installation.
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16660
YAA
ENGG CERT
3 of 5
F. Circuit Breakers: Provide molded-case circuit breakers of sizes and ratings
indicated. Construct with thermal and magnetic elements for conventional overload
LSS
and fault-current protection; and with ground-fault trip mechanism capable of being
activated by ground-fault relay which causes opening of circuit when ground-fault
occurs of the magnitude indicated.
G. Monitor Panels: Provide monitor panels with ground-fault indicators, control power
indicators and TEST and RESET buttons, and with control circuitry capable of
ISSUED FOR IFC
DESCRIPTION
PART 3 - EXECUTION
3.01 EXAMINATION
Examine areas and conditions under which ground-fault protection systems and devices
are to be installed, and notify Contractor in writing of conditions detrimental to proper
completion of work. Do not proceed with work until unsatisfactory conditions have been
JO/EWO
01/21/2016 BI-01382
00
3.03 GROUNDING
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
Provide grounding connections for ground-fault systems and units as indicated. Tighten
(DCC) NO. _____________________
connectors and terminals, including screws and bolts, in accordance with equipment
10-01382-0008-0001
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16660
YAA
ENGG CERT
4 of 5
manufacturer's published torque tightening values for equipment connectors. Where
manufacturer's torquing requirements are not indicated, tighten connectors and terminals
LSS
3.04 ADJUSTING
Set field-adjustable GFP devices for pickup and time sensitivity ranges as indicated by
shunt circuit and overcurrent study, subsequent to installation of devices.
ISSUED FOR IFC
DESCRIPTION
END OF SECTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
SECTION 16660
YAA
ENGG CERT
5 of 5
DIVISION 16 - ELECTRICAL
LSS
PART 1 - GENERAL
A. Extent of fire alarm systems work is indicated by drawings, schedules, and riser
diagrams.
B. The National Fire Alarm Code NFPA 72 shall be followed to establish the
requirement for buildings. Local Fire Alarm Panels (LFAP) shall be installed in all
buildings such as to which in-building addressable smoke detectors, heat sensors
and manual call points are installed and connected.
boxes.
DATE
To maintain the integrity of the Fire Alarm System design all LFAPs shall be of the
indicating and audible type to ensure that a status of each field device loop is
available locally.
NO.
REV
00
DISCIPLINE
ENGINEER C. Provide system suitable for type occupancy as defined by local Building Code and
ANP
01/21/2016
as approved by local Fire Marshal.
DATE:
PROJECT
ENGINEER D. Fire protection where required shall be provided by passive fire protection methods
LSS
such as physical isolation or fire insulation.
01/21/2016
DATE:
CERTIFIED
YAA Mitigating actions against Fire events such as the operation of fire suppression or
01/21/2016 closure of air dampers are safety actions subject to Safety Review by Company.
DATE:
CONSTRUCTION
AGENCY
YAA
1.01.1 SCOPE
01/21/2016
DATE:
The Scope of Supply shall include all the necessary hardware, software, manufacture,
OPERATIONS
ASZ
assembly and testing to meet the requirements of the Fire Detection System (FDS) as
01/21/2016
specified in this document and on the requisition but not limited to the following:
DATE:
CONTROL NUMBER
• Fire Detectors
EDSD
• Smoke Detectors
DATE:
• Fire Panels
BY:
• Special Tools
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
• Commissioning Spares
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
1 of 10
YAA
ENGG CERT
Testing
LSS
Site Supervision
To facilitate material control at site, the Vendor shall package the fire alarm panel and
components (detectors, horns etc;) associated with each building to allow easier control at
site.
ISSUED FOR IFC
DESCRIPTION
00
DATE:
01/21/2016
A. Manufacturer's Qualifications: Firms regularly engaged in manufacture of fire
CERTIFIED alarm systems, of types, sizes, and electrical characteristics required, and whose
YAA
products have been in satisfactory use in similar service for not less than 5 years.
01/21/2016
DATE:
CONSTRUCTION
AGENCY B. Installer's Qualifications: Factory trained technicians qualified with at least 5 years
YAA
of successful installation experience on projects with fire alarm systems installation
01/21/2016
DATE: work similar to that required for this project.
OPERATIONS
ASZ
C. Contractor shall be responsible for detailing the basis of quantifying the types,
01/21/2016
DATE: quantities and locations of all fire devices for approval by Company.
CONTROL NUMBER
VERIFICATION
Firm with factory authorized service organization and spare parts stock.
EDSD
SECTION 16721
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
2 of 10
YAA
ENGG CERT
1.03 SUBMITTALS
ISSUED FOR IFC
DESCRIPTION
C. Maintenance Data: Submit maintenance data and parts lists for each type of fire
alarm equipment installed, including furnished specialties and accessories. Include
JO/EWO
01/21/2016 BI-01382
this data, product data, and shop drawings in maintenance manual; in accordance
with requirements of Division 1.
DATE
D. Fire layout drawings detailing fire zones, alarm zones and all fire devices shall be
provided by Contractor for approval by Company.
NO.
REV
00
DISCIPLINE
ENGINEER 1.04 DELIVERY, STORAGE, AND HANDLING
ANP
01/21/2016
DATE: A. Handle fire alarm equipment carefully to prevent damage, breaking, and scoring.
PROJECT
ENGINEER Do not install damaged equipment or components; replace with new.
LSS
01/21/2016
DATE: B. Store fire alarm equipment in clean, dry place. Protect from weather, dirt, fumes,
CERTIFIED
YAA water, construction debris, and physical damage.
01/21/2016
DATE:
CONSTRUCTION
PART 2 - PRODUCTS
AGENCY
YAA
01/21/2016
2.01 ACCEPTABLE MANUFACTURERS
DATE:
OPERATIONS
ASZ
A. Available Manufacturers: Subject to compliance with requirements, manufacturers
01/21/2016
offering fire alarm systems which may be incorporated in the work include, but are
DATE: not limited to, the following:
CONTROL NUMBER
VERIFICATION
Tyco
Notifier
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
GE Security
(DCC) NO. _____________________
10-01382-0008-0001
SECTION 16721
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
3 of 10
YAA
ENGG CERT
EST
Honeywell
Detronics
LSS
Protecto-Wire
Simplex Grinnell
Hochiki
A. SYSTEM REQUIREMENTS
ISSUED FOR IFC
DESCRIPTION
1. Standards
In addition, the Vendor shall be fully responsible for ensuring that any fire or
smoke devices offered shall meet national and local standards in addition to
the international standards and the documents referenced herein. The
Vendor shall have all appropriate documentation in place as a pre-requisite
requirement.
JO/EWO
01/21/2016 BI-01382
National and local standards at the site location may take precedence over
the International codes and the COMPANY standards. It shall be the
Vendors responsibility to confirm all these standards and requirements are
DATE
met and provide the necessary documentation to obtain certification for the
system approval.
NO.
REV
00
DISCIPLINE This is in addition to the international certification that shall be provided with
ENGINEER
ANP the equipment before procurement and installation of the devices.
01/21/2016
DATE:
PROJECT 2. Fire Detection and Alarm Systems
ENGINEER
LSS
01/21/2016 Fire detection system consisting of smoke detector, carbon monoxide alarm, horn
DATE:
CERTIFIED and strobe lights.
YAA
DATE:
01/21/2016 3. Fire Detection Audible Alarms
CONSTRUCTION
AGENCY
YAA The smoke alarm and carbon monoxide (CO) shall receive primary power
DATE:
01/21/2016 from the building 230VAC power and a secondary power supply from an
OPERATIONS individual 9VDC battery inside each smoke alarm unit.
ASZ
DATE:
01/21/2016 All fire alarm tones and patterns shall be distinct and recognisable from all
other audible alarms. This shall be engineered by CONTRACTOR and be
CONTROL NUMBER
VERIFICATION
subject to review and approval by the COMPANY. Process unit and site
EDSD
wide alarms shall also be distinguishable from the site evacuation alarm
tone and pattern.
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
4 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
4. Automatic Actuation
YAA
ENGG CERT
5. Manual Initiation
ISSUED FOR IFC
DESCRIPTION
B. Design system for alarm sounding continuously on each building zone in alarm
only and will activate the Sprinkler System through Flow Switch.
1. Provide Class A initiating and alarm circuits with electrical supervision for
01/21/2016 BI-01382
2. Power Supplies: Provide system for operation on 230 VAC power supply.
Arrange control system for operation of primary power supply and trouble
power supply to operate from opposite legs of three wire system.
NO.
REV
00
DISCIPLINE
ENGINEER
ANP
3. Provide battery back-up as secondary power supply. Design battery back-
01/21/2016 up to take over supply to system within 30 seconds of loss of primary
DATE:
PROJECT system to 85% voltage. Provide battery system capable of operation of
ENGINEER
LSS
system for 24-hours under normal conditions and then for five minutes
01/21/2016 under alarm conditions.
DATE:
CERTIFIED
YAA D. Remote Station Systems
01/21/2016
DATE:
CONSTRUCTION E. Control of auxiliary services:
AGENCY
YAA
G. Wiring System Materials: Provide basic wiring materials which comply with
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
SECTION 16721
5 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
3. Provide multiconductor cables for wire sizes smaller than AWG #16.
4. Provide conductors which are listed and approved for fire alarm usage.
ISSUED FOR IFC
DESCRIPTION
H. Control Panels: Provide fire alarm control panel enclosures for housing devices
and circuits necessary to perform required functions, and to service as test points,
and trouble-signal points.
1. Provide control panel for operation on 230-volts AC supply and for 24-volts
DC system operation with battery stand-by power source.
JO/EWO
01/21/2016 BI-01382
2. Equip control panel for number of initiating zones indicated. Provide tone
generator, with redundant unit, supervised, producing the sound pattern
DATE
J. Alarm Lights: Provide manufacturer's standard construction alarm lights with the
NO.
REV
00
DISCIPLINE
following features:
ENGINEER
ANP
01/21/2016
1. Red lens, plain or lettered white "FIRE".
DATE:
PROJECT
ENGINEER 2. White lens, plain or lettered red "FIRE".
LSS
01/21/2016
DATE: 3. 24-volt DC incandescent.
CERTIFIED
YAA
3. Direct current
EDSD
DATE:
L. Junction Boxes and Floor Terminal Panels: Provide fire alarm junction boxes and
BY:
floor terminal panels painted red enamel. Provide each box with suitable number
APPROVAL/CERTIFICATION REQUIREMENTS,
of terminals and of proper size to hold wiring, both for immediate floor and floors
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
10-01382-0008-0001
6 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
above.
YAA
ENGG CERT
M. Fire Alarm Sign: Provide 8” x 8” sign, “FIRE ALARM BOX”, over each fire alsrm
LSS
pull station mounted perpendicular to wall, red with 2-1/2” high white letters.
N. Test Chart Instructions: Provide fire alarm system test instructions chart mounted in
lexan enclosed frame assembly on control cabinet hinged door.
1. 24-volts AC or DC
2. Single door
3. Flush mounted
All equipment supplied shall meet the requirements of this specification using
JO/EWO
01/21/2016 BI-01382
equipment listed by UL and FM, suitable for Fire Detection application. To ensure
consistency throughout the Project, the selection of all fire detection equipment
DATE
All Fire Alarm System equipments shall be given the requirement in SAES-M-100 for
NO.
REV
00
DISCIPLINE
UL Listing or FM Approval for fire alarm equipment approved for the application
ENGINEER
ANP
specified all components of the Fire Alarm System shall carry a full 1 year warranty
01/21/2016
for any manufacturing defect.
DATE:
PROJECT
ENGINEER
All initiating and signalling devices shall be approved for use with fire alarm control
LSS
01/21/2016
panel unless specifically instructed otherwise by this Specification or unless the
DATE:
CERTIFIED
type of device required is not made by the fire alarm control panel manufacturer. All
YAA controls and annunciation lights shall be identified with a permanent label.
01/21/2016
DATE:
CONSTRUCTION The systems shall be designed to meet the Project operational requirements and
AGENCY
YAA arranged to comply with the plant protection philosophy.
01/21/2016
DATE:
OPERATIONS
All equipment provided under this Project shall be capable of expansion to meet
ASZ the future requirements without requiring changes to equipment provided under
01/21/2016 this specification.
DATE:
CONTROL NUMBER
VERIFICATION
The Fire equipment supplied shall not be affected in any way by the use of
Standard commercial UHF and VHF band, handheld, telecommunications
EDSD
equipment operating with a normal output power of 5 Watts. These transmitters will
DATE:
be used within close proximity of the detectors that are installed within the building.
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
7 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
Environmental Conditions:
ISSUED FOR IFC
DESCRIPTION
Although some equipment shall be supplied and installed for use in an indoor, air-
conditioned environment they shall include protection against traces of sand and
dust.
00
DISCIPLINE
Appendix shall not be permitted unless approved by the COMPANY.
ENGINEER
ANP
01/21/2016 PART 3 - EXECUTION
DATE:
PROJECT
ENGINEER
3.01 EXAMINATION
LSS
01/21/2016
DATE:
CERTIFIED
A. Examine areas and conditions under which fire alarm systems are to be installed.
YAA Do not proceed with work until unsatisfactory conditions have been corrected in
01/21/2016 manner acceptable to Installer.
DATE:
CONSTRUCTION
AGENCY
YAA 3.02 INSTALLATION OF BASIC IDENTIFICATION
01/21/2016
DATE:
OPERATIONS A. Install electrical identification in accordance with Division-16 Basic Electrical
ASZ Materials and Methods section "Electrical Identification."
01/21/2016
DATE:
3.03 INSTALLATION OF BASIC WIRING SYSTEM MATERIALS
CONTROL NUMBER
VERIFICATION
A. Install wiring, raceways, and electrical boxes and fittings in accordance with
EDSD
and Cables", and "Electrical Boxes and Fittings" for wiring of non-power limited
BY:
circuits.
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
8 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
where properly protected. Use conduit for runs through floors or in shaftways to
height of 7' above floor. Provide cables in plenum spaces in metallic raceways or
LSS
B. Wiring: Wiring of fire alarm system is work of this section, but is not specifically
detailed on drawings.
1. Complete wiring in accordance with manufacturer's requirements. Color
code wiring and install per manufacturer's point-to-point wiring diagram.
Determine exact number of wires for each fire area zone from number and
types of devices installed. Connect each device with sufficient wiring to
JO/EWO
01/21/2016 BI-01382
detectors, fan relays, door holders and smoke damper operators installed in
a circuit, group in numbers so power required does not exceed 80% of
manufacturer's power supply rating. Provide extra wiring, or extra power
NO.
REV
00
DISCIPLINE
supplies required to fulfill that requirement. In addition, provide extra or
ENGINEER larger size wiring to alleviate voltage drops which makes device operate
ANP
01/21/2016
beyond voltage limits for which it was designed. Determine above with
DATE:
PROJECT
manufacturer's representative while equipment is being installed.
ENGINEER
LSS
01/21/2016
3.05 FIELD QUALITY CONTROL
DATE:
CERTIFIED
YAA A. Connection and Supervision: Make connections to panel under manufacturer's
01/21/2016 supervision.
DATE:
CONSTRUCTION
B. Where work consists of additions or extensions to existing system, prior to starting
AGENCY
YAA
work, establish that system is in proper working order. If condition exists which
01/21/2016 prevents normal operation of specified additions and extensions, bring this fact to
DATE:
OPERATIONS
Company Representative attention prior to doing work affecting existing system.
ASZ
Where work is done without such notification, it is assumed that connections have
01/21/2016
been made to a working system, and performance requirements and guarantee will
DATE:
apply to entire system.
CONTROL NUMBER
VERIFICATION
C. System Test and Approval: Submit shop drawings for function and operation only,
EDSD
SECTION 16721
10-01382-0008-0001
9 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
ASZ
SAUDI ARABIAN OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
YAA
END OF SECTION
ISSUED FOR IFC
DESCRIPTION
JO/EWO
01/21/2016 BI-01382
NO. DATE
REV
00
DISCIPLINE
ENGINEER
ANP
01/21/2016
DATE:
PROJECT
ENGINEER
LSS
01/21/2016
DATE:
CERTIFIED
YAA
01/21/2016
DATE:
CONSTRUCTION
AGENCY
YAA
01/21/2016
DATE:
OPERATIONS
ASZ
01/21/2016
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
REVISION CERTIFICATE
00
OF THIS DRAWING IS COVERED, FOR ALL
SECTION 16721
10-01382-0008-0001
10 of 10
B CONSTRUCTION SPECIFICATIONS - ELECTRICAL DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.