M/s.

SAGE Automation (Australia)


& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

Project Office:
142-H Model Town, Lahore – Pakistan.
Phone: +92-42-35442443, 38931663

Ref: No. P-2057/SCADA-III/GM/20231218_RTU 12 January 2024

Attn: Chief Engineer / PD (PMU), SCADA-III Project


625 WAPDA House, Lahore.
SUBJECT: CONTRACT NO. ADB-202R-2019: PROCUREMENT OF PLANT - DESIGN, SUPPLY,
INSTALLATION, TESTING AND COMMISSIONING OF SCADA PHASE-3 AND REVENUE
METERING SYSTEM (RMS) FOR NTDCL -
Consultant Letter to Employer- RTU Site Report Week 2

Dear Sir,
Please find the site issues and observations as stated below:

1. 220kV Grid Station Bund Road (SR-027):

As per approved proposed method, the cables from marshalling box laid up to SIC panel have a
core size of 0.75mm² is terminated in new terminal box (TB) whereas the cable of 0.6mm² core
size for termination at other end has been ordered for purchase.

Below images are from SIC panel showing the termination of cables at TB and LR switch:

As it was agreed that due to excess of tangled cables in existing control panel the spare panel will
be used. However, SE(GSO) has not allowed for the same proposal, emphasizing that CMEC
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

should provide approved design drawings before the start of the said works. Moreover, the
scheduled shutdown for the testing of said works on Jan 15, 16 & 17, 2024 is also delayed due to
inconclusive matter at NTDC’s local staff end.

Below images are from 220kV existing Control panels showing the current condition:

Multiple telephonic discussion with XEN P&I has been made in order to resolve the matter with
SE(GSO). However, no meeting has been scheduled as SE(GSO) had not been available.

Below mentioned is a summary of RTU site activities from Jan 08 – Jan 14, 2024:

1. Termination box has been installed for the termination of 0.75mm² core cable at one end
and 0.6mm² core cable on the other end.

2. Termination of cables in SIC panel has been completed.

3. Installation of local remote switches in SIC panel has also been completed.
M/s. SAGE Automation (Australia)
& M/s. BARQAAB Consulting
Services (Pvt.) Ltd. (Pakistan)
Joint Venture
BARQAAB

Below mentioned works are percentage progress of the works related to the LDS-II missing RTU
signals:

220kV Substation Bund Road (SR-027)

Cable Termination BOQ Items Installation


Cable Continuity
Date Local
Laying Marshalling Check TAP Intermediate Marshalling
SIC Panel Remote
Box Transducer Relay Box
Switch
Jan 08, 2023 - - ≈ 0% - - - - -

Jan 09, 2023 - - ≈ 0% - - - - -

Jan 10, 2023 - - ≈ 0% - - - - -

Jan 11, 2023 - - ≈ 3% - - - - -

Jan 12, 2023 - - ≈ 2% - ≈ 5% - - -

Jan 13, 2023 - - 0% - 0% - - -

Jan 14, 2023 - - 0% - 0% - - -


Previous
≈ 100% ≈ 100% ≈ 33% 0% 0% 0% ≈ 100% 100%
Progress

Total ≈ 100% ≈ 100% ≈ 38% 0% ≈ 5% 0% ≈ 100% 100%

Sincerely,

Gibran Malik

LDPIII Consultant – Testing & Commissioning Manager


Ph: +61 407281998, 03062165858
Email: LDPIIIConsultant@sageautomation.com, Gibran.malik@sageautomation.com