1. General
1.1 Site Preparation and Mobilization- demobilization of All equipment related to drilling, well construction and well testing on Site
The contractor shall visit the site and make all investigations deemed necessary to ascertain him with all site conditions, and
1.2
nature of works.
The contractor shall deploy on-site a full time civil engineer and if possible with some experience in hydrogeology and borehole
1.3
drilling.
The contractor shall make full coordination with the popular committee, local community, and UNRWA Engineer before and
1.4 during the drilling execution in order to discuss and anticipate any future problems such as roads closure and accessibility,
existing infrastructure design in the camp etc...
The contractor sall be deemed responsible for any damages that results from the drilling, mobilization and demobilization
1.5
activities. .
1.6 The contractor must coordinate with the archeology team prior to execution of the works.
The contractor will be paid by UNRWA based on the activities executed in reference to the BOQ. However, if not all the activities
1.7 in the BOQ were implemented due to certain conditions during drilling, the non-implemented activities shall be omitted from the
invoice(s) by the contractor and only the executed activities shall be invoiced.
Only extension of time with no extra cost will be granted in case of any lockdown, closures, restrictions due to COVID-19 crisis or
1.8
other reasons.
The contractor will be responsible to coordinate with the army and ISF to obtain permissions for the entry of drilling machine,
1.9
machinery, equipment and building materials.
The contractor is requested to comply with safety rules and regulations, COVID-19 regulations of social distancing, wearing PPEs,
1.10
Hygiene practices, etc…. to ensure the works are implemented in safe environment for residents, labor force and equipment.
1.11 Upon completion of works, all installations to be tested, commissioned, and all works are to be handed over in good conditions.
The contractor has to submit in advance before purchasing: catalogues, manuals or samples if possible to get prior agreements
1.12
specially for the important components of the pumps, panel and control boards.
Serial Description Unit Quantities Unit price (USD) Total price (USD)
2. Drilling
It is required that the contractor uses mud/bentonite while drilling the well and provide/acquire a rotary drilling machine that can reach
a minimum depth of 950-1000 m bgl.
Supply and Install 8-inch Carbon Steel Casing API- 5L grade B (or
equivalent) Inside Diameter Bridge Slotted of 6.4 mm wall
4.5 Lm 75 $0
thickness,, slot opening of 3-4 mm, and 12 % open slot area.
(SCENARIO 1)
Supply and Install 6-inch Carbon Steel Casing API- 5L grade B (or
equivalent) Inside Diameter Bridge Slotted of 6.4 mm wall
4.9 thickness,, slot opening of 3-4 mm, and 12 % open slot area, Lm 200 $0
along with a casing reducer/adapter to connect the 8-inch ID
casing and the 6-inch casing (SCENARIO 2)
5. Annular Sealing
Grouting the annular space between the inner casing of 18 inch
5.1 and the borehole wall of 22- inch diameter; using tremie Lm 50 $0
grouting technique
Grouting the annular space between the inner casing of 12 inch
5.2 Lm 200 $0
and the borehole wall of 15 1/2- inch diameter
7. Reporting
Preparation of Well Completion Report (including borehole
7.1 LS 1 $0
testing and Pumping test data)
Supply and install 4" non-return Valve for the wells including
bend, double flanged pipe, flanges, adaptors Ductile iron non
return valve assembly; assemblies to BS or ISO standard
complete including flange spigots, flange sockets, flange
8.6 adaptors, dismantling joints, double flanged pipes, socket/spigot LS 1 $0
pieces, bends, reducers, flap valves, accessories, concrete
supports, corrosion protection, connecting, testing and all other
related works, all as specified and to the satisfaction of the
Engineer.
Supply and install complete chlorination system deep well
including complete sodium hypo chlorine dosing system
comprising of solenoid adjustable dosing and injection pump of
prominent type or equivalent approved type with dosing
capacity range 0-4 liter /hour at 16 bar back pressure. 50 liter
polyethylene white chlorination tank with built in factory made
manual stainless steel mixer ,the works and installations should
include for all fittings and accessories required to accommodate
8.7 LS 1 $0
and connect the desired tank feeding point through
underground 1/2" stainless steel pipe all according to the
specifications and instruction by Eng. programmable residual
chlorine analyzer of Dulcometer type or equivalent approved
type complete with its associated accessories and printer
including all required connection and automatically operate and
control the dosing pump to cope with the desire concentration
of the residual chlorine at the tank.
Provide and fix electric sensor with its cable (3x2.5mm solid
black cable) (cable du Liban) with sensors for the temperature
control (three different leveled electrodes, the lowest electrode
9.1.2 is 2m above the pump and the other 2 electrodes are 1m apart LM 350
for each one)to secure protection for the pump motor.
Complete with proper connection to the controlling panel board
and special (IP67 and above )isolation material.
Provide and fix water supply pipes HDPE with internal diameter
9.1.4 2 " for the Piezometer measurements. The last 60 cm of the pipe LS 1
is porous (holes with 2.5 mm in diameter).
Supply and install a high quality European made piezometer with
its cable (up to 350 meters)of type Cobalt and to the satisfaction
of work supervisor. Unit rate shall include the connection to the
9.1.5 LS 1
panel board and reprogramming of the piezometer. The
Piezometer shall be fixed to a depth 2-3m above the water
pump.
9.2 STEEL PLATE
Manufacture, provide and fix 2000 liters Diesel tank, the tank is
of overall size of 100cm length*100cm wide* 200cm height with
metal supports, and is made up of 3mm thick black metal sheets
with internal supports and accessories needed, including 4Ø1/2"
9.5 joints for filling and emptying the tank, 2Ø1/2 joints for LS 2
connecting the tanks to the generator, 8mm level tube with top
and bottom fixtures with lockable steel cover to protect the
level indicator tube, Ø1/2 black steel pipes for tank connections
to the generator , testing and commissioning .
Total(USD): $0
Please refer to the Technical Specifications Document for detailed information about the drilling, borehole testing, casing/screen installation, well
development and pumping test activities.