Download as pdf
Download as pdf
You are on page 1of 41
DRAWINGS, BOQ and STATEMENT OF WORKS FOR LOT6 A. Equipment Bidders must demonstrate that they would have access to the key Contractor's equipment listed hereafter: No, Equipment Type and Characteristics [rs Number required 1 | Tettameter/ Geophysical Equipment forsting the | One(h boreholes 2 _| Drilling Rig and drilling tools One (iy 3 _[ Compressor One (1) 47 [Mud pump ‘One (1) 3 __| Support Trucks ‘One (1) §_ | Pumping Test Equipment One set 7 | Mand tool set (mechanical, efectvieal, masoniy & | One Ch) cer oF plumbing hand tools) each type 8 _| Land Surveying Instrument ‘One (1) set 9 | Pick-up Van One (1 10 | First aid kit (@ssontedy One set Is of proposed items of equipment BILL OF QUANTITIES FOR THE DRILLING OF BOREHOLES AND CONSTRUCTION OF SOLAR POWERED WATER DISTRIBUTION SYSTEM (All the quantities in the Bill of Quantities are provisional, subject to measurement for purposes of payment. The Contractor shall be paid for actual quantities used) Unit lem Price Amount No. Description Units | Quantity | (000) | de’ 000) ‘Activity 1 Insurance of the Works and Site 1 Preparation Provide insurance cover for the works, in the amount of 20% of the total bid price (GCC. Clause 1.21).The insurance to be obtained from a reputable Insurance Company as approved by 1.1 _| the Client, Ls 1 Mobilization and Demobilization at borehole sites of all equipment and maintain drill rigs for the complete construction of boreholes with all accessories, associated arrangement, auxiliary works, personnel as well as withdrawal afler completion and move to next drill site including 1.2 | setting up and moving after successful drilling | Nos, i Site Preparation of the drill sites and clearing of all drill sites of all trees, brush, undergrowth and any other vegetation obstructing the 13 | execution of all contractual works Nos. 1 Supply and erect project name boards (overall dimension 3m high x 1.2 wide) with painted steel supports and sawn hard wood boards for each borehole water supply system in 1.4 | accordance with drawing no, O11 Nos. 1 Sub Total Activity 1 Activity 2 Borehole Siting and Drilling 2 _| Works Item No. Description Units Quantity Unit Price (000) Amount (Le? 000) Identify drilling point capable of providing the sequired discharge and drill with a drilling diameter large enough to allow the installation of a temporary casing and a final drilling diameter of at least 152.4 mm. Commissioning of all necessary plant, equipment and accessories for the duration of the works, taking of soil samples, keeping of drilling logs including supply, installation and dismantling of temporary casing as specified, Drilling Method (TH and/or Mud Rotary Drilling) must be appropriate t0 the underground conditions and has to be approved by the Engineer. Geophysical surveys/siting of dtilling sites to locate" boreholes using vertical electrical sounding (VES) method or otherwise and design of boreholes. The surveys should provide information to assess amount of water present, soil porosity and degree of saturation of 2.1 | soil/rock Nos 2.2 [Pipe network profile surveys Ls Drilling through overburden; unconsolidated and consolidated formation, to a minimum depth of 60m, for instailation of 150mm diameter casing and screen, taking soil samples 2.3_| and logging the borehole. 63.33 Suppiy, install and withdraw temporary casing 24 | 194mm, (average 5 m) Supply and install 150 mm threaded joint uPVC 25 | slotted screen, 525 Supply and install 150 mm threaded joint uPVC 2.6 _| Solid/Plain casing. 157.5 Supply and installation of 150 mm’ threaded Joint uPVC Sump Pipes in length of 2.0 m with bottom plug, Pes Supply and installation of Filter Gravel pack, (average depth 12m and standard thickness 50mm), Filter gravel, siliceous, ronaded with diameter of 2.0-4.0 mm depending on screen 28 | slot size. [tem No. Description Units Quantity Unit Price | Amount (000) (ue* 000) 29 Supply and installation of a Clay Bridge on top of the filter gravel consisting of 1 m depth of sand (0.2 - 1.0 mm) and 2m depth of clay (Quellon pellets of simitar). No. Supply and insertion of Back Fill Materials into the annular space on the tap of the clay sealing up to the base of the top cement grout (average 17m), 7 Supply and insertion of Sm Cement Grout on {op of the backfill material up to the surface 2.) Development of Drilled Well with AimLift Method; including measurements, records, and Gisposal of water (minimum 3 hours per well) Hrs, 2.12 ‘Temporary protection cap on successful Borehole Nos 2.13 Backfill and sea! abortive borehole as specified Nos 2.14 Construct well-head casing as specified Nos Sub Total Activity 2 Activity 3 Pumping Tests Lau Execution of Step Test to determine the hydrautic performance of the well (min. § hours) with 4 steps of inereasing yields followed by a Constant Test (min. 12 hous) to determine the tong term sustainability yield of the borehole including measurement of gw-level and yieid, reeording of EC, pH, and temperature of the groundwater every hour during pumping, A pump with minimum capacity of 2.5 m3/he and hydraulic head of 65m must be available with all equipments (generators, cables discharged hose of 100m to ensure safe disposal of water from borehole and other ancilliary materials). Submission of data in digital form (RW Disks) and printouts (data sheet and graphs). hours Unit Item Price | Amount No. Description Units | Quantity | (000) | (Le? 000) Recovery Test (min. 6 hours); including measurements and records of water [evel, submission of data in digital form (RW Disks) 3.9. | atd printouts (data sheet and graphs) hours 6 2 ur Sub Total Activity 3 4 _| Activity 4 Water Quality Analyses Water quality tests to be done by the water quality monitoring unit of the Water Directorate, Tests “will include Laboratory Analyses of physico-chemical and Bacteriological parameters. (WHO standard).(The Contractor will be invoiced by the service provider} Nos. 1 Sub Total Activity 4 5__| Activity 5 Borehole Reports Borehole, “pumping test and waler quality reports and borehole log reports for all well sites, one set of each comprising files in soft 5.1_| Copies (Mash disk) in bound form. Nos 1 Sub Total Activity 5 6 | Activity Works Construetion of Tower and Stand posts Excavation and Earthworks Excavate “topsoil average 150mm deep, to remove any vegetable matter and dispose of 6.1_| &Xcavated materials off site Me 333 Excavating starting af site sirip Tevel maximum 6.2. | depth not exceeding 300mm we 194 Excavate pits for colamns commencing Tom 6.3_| #fOund level not exceeding 1.0m deep mM |o63 Concrete Works 64 Reinforced ~ in-situ concrete agaregate including reinforcement and formwork in Unit Tem Price | Amount No. Description Units | Quantity | (v0) | (Le? 000) 6.41 | Foundation MP 3.56 G4 | Column we 5.08 (6.43 | Suspended floor slab (lower) uM 176 6.4.4 | Suspended floor slab (solar control room) Mw 173 6.45 | Ring beam (solar control room) M 028 Plain in-situ conorete 1:3:6-12mm aggregate for 6.5 _| floor siab concrete in Solar control room, Mt 0.82 Reinforced in-situ concrete 1:24-6mm aggregate including reinforcement and 5.6 _| formwork for concrete standposts, M 0.82 Provide roof structure for conttol, including approved quality roof members and corrugated iron roofing sheet (as shown on dwgs.) 61 Nos 1 Provide and install 10 complete standposts per borehole, with galvanized pipe and vandal-proof 6.7_{ lockable tap of approved robust qualit Nos 10 Scaffold Erecling and dismantling of timber scaffolding 6.11 | for 8m 10 10m high tower construction Ls 1 Blockwork Precast sanderete solid block 150mm thick in 6.12 | cement mortar 1:6 in superstructure, Me 17.95 Finishing 12mm thick cement and sand (1:4) plain face rendered control room block walls internally 6.13 | and externally M 43.18 PROTECTION GUIDE TO SOLAR PANEL Provide and install fabricated steei casement frame 50mm x S0mm angle iron welded together, and with holdfast fixed on concrate base all finish with 614 || antirust paint, overall size, {600mm x 500mm} ttem 1 Painting/Decoratin; Prepare and apply one coat sealer and two coats 6.13 | of oil paint to rendered surface, doors and M? 43.48 Unit Item Price | Amount No. Deseription Units_| Quantity | (000) | Le’ 00) windows as approved by the Engineer, Doors Provide and fix steel door 600mm x 150mm hhigh complete with frames, vandal proof 6.16 | itonmongery. Nos. 4 Sub Total Activity6 1_| Activity 7 Distribution Network Supply and install the following pipes and accessories, depth not less than 0.6m, for ransmitting water from borehole to storage tank and distribution to stand posts 7.1_| PE Pipe 3” M 450 7.2_| PE Elbow 3" Nos. 22 7.3 | PiTee 3” Nos. 2 7.4 _| PE Socket 3" Nos. 313 7.5_| PE Adaptor 3" Nos. 21 7.6 | PE Pipe 2” M 3 7.1_| PE Elbow 2" Nos. 6 7.8 [PE Tee piece 2” Nos. 4 7.9 | PE Stop cork 2” Nos. 2 7.10 | PE Adaptor 2" Nos. 6 7.11 | PE Tank Connector 2" Nos. 4 7.12 | PE Reducer 2" x1" Nos. 2 Supply, transport & Tift to tower slab 10,000 7.13 | titves water tank (Vertical), two on each tower Nos. 2 Provide precast concrete peg. positioned at 10m 7.14 | interval to show pipe route Ls 2 7.15 | PE Pipe i" M 209.79 7.16 | PE Elbow 1* Nos. 20 7.17 | PE Tee piece 1” Nos, 20 7.18 | PE Adaptor 1” Nos. 15 7.19 | PE Gate Valve 1* Nos, 10 7.20 { PE Tank Connector 1" Nos. 6 7.21 [PE Reducer 1" 3/4" Nos. 20 Unit Item Price | Amount No, Description Units _| Quantity | (000) | (Le? 000) 7.22 | PE Pipe 3/4" Roll 15 7.23 | PE Elbow 34" Nos. 20 7.24 | PE Tee piece 3/4" Nos. 25 7.25 | PE Adaptor 3/4" Nos. 30 7.26 | PE Gate Valve 3/4" Nos. 10 7.27 | PE Nipple 3/4” Nos. 20 7.28 | PE Socket 3/4” Nos. 20 7.29 | Tap head 3/4" Nos. 10, 7.30_| Solvent cement Nos. 6 731 | Thread Tape Nos. 10 7,32 | Supply and fix 4” Di gully tap Nos 10 Construct 3° x 3” stand pipe splash apron in stone masonry with a 200-300mm boulders such 7.33 | as granite Nos 10 Construct stone masonry lined drainage channel 2.0m long and 0.15m wide, depth 0.1m from 7.34 { splash apron to soakaway pit Nos 10 Construct soakaway pit, depih 15m, diameter 2.35 | 0.7m, filled with medium hard rock (sandstone} | Nos 10 Sub Total Activity 7 ‘Activity 8: ining of Borehole Operators; 8_| Plumbers (2) ‘Training of borehole attendants in basic 8.1 | plumbing works Nos. 2 8.2 | Provide training manuals and maintenance tools | set 1 Sub Total Activity 8 Unie Item Price | Amount No. Description Units | Quantity | (00) | (Le? 000) SUMMARY, Amount Activity 1 Insurance of the Works and Sie Preparation Activity 2 Borehole Siting and Drilling Works Activity 3 Pumping Tests Aetivity 4 Water Quality Analyses Activity 5 Borehole Reports Activity 6 Civil Works Activity 7 Distribution Network Activity 8 Training of Plumbers and Borchole Operators Total Activity Cost ‘Total Activity Cost for x No, of well Add 10% of total activity Cost for Contingenciss GRAND TOTAL 200. for SPRING BOX for LOT 6 tem Description JUnit fo —|reate Amount sua, Le The Contractor shall accept the yment provided for ithe eantract ana| [presented by the rates bid by him in lhe Bit of Quantities, as payenent in fall for executing and campieting the work 8 apecilie. for precuring, furnishing, lacing and installing ai rateriats, for procuring and providing labour, ['apervision, constructional plant, tools nd equipment, for wastage, anspost, loading and offloading, hansiing, juainienunee, temporary work, testing, jt form meerararion “enol clear site Fall vepeation = 1.1 _jfhoubs and undergrowsths lst 41 [CTear and cart anay at Te Top SOT RE 1.2 exceeding 200mm y 82) Sub Total 2 [kart works 2.4 [lexeavation = IExeavate 3.7 ms wide by 4m devs R ta foundation fo 134.45 Hxeavate 3m wide hy 3 deep 2.tb foundation trench for cable pipes ls ig.39 [Evtr-over excavation fn tack as 2.4¢ [Mivected by the Engineer, hn 35] [Lovet and compact Bont of excavation ing suitable eampactor 19 95% nasimem diy density (MDD) to 2d jz oy 41 3 | foes eet an er cern pith ita earth meri Stn td £0 95% maximus dy desis (MDD) 0 22a jpsi37> n 280 sith nun thick Hard tained of sitesmasin excoading 75% of backs 2.30 [881377 acifil Level and compact excavation sore material tan sie not fill thickness to p27] JBACKIl Level end compact seound pl with 20mm crushed stone/geavet 2.26 [material obtained off site Int #136 224 fsite JCA anvay excess excavated materia of? ‘Sub-Total Earthworks 2 ETE WORKS BS 81 3.la [Concrete Provide and place 5mm thick grade 15/20 vonerete with 30mm-60hnm proofing, hump as blinding water admixture ie 0.5% oF cement weighs Gs 135] Givedge 6.56 base 1.54] Provide and piace grad jeonerete with 0,59% of 3.1b jPsdmixture 30m-60mm slump in ie C25/30 ment weight, (O swwin wall the spring sources I> 1735 ieenerete (0 sleeve pipes in? 07| | b2 floc. fis armor or casing Provide and fix 25mm thick hardwood i slab niga cides 129] 3.3 |einforcomen Feintoccemers $60N i! [95449 in edge beams Provide cut Jbond and fi ix high tensite Conforming to (210m diameter reinforcement fag oal (i) [ram diemetee reinforcement fag 0.75] 1s fewer | [Provide and fis eonerote joint und filling pith AQUAMAT-ELAS'TIC, brushable Sealing story. io 343 | 346 _|Water Supply Systems t [Construction Water points according to details in drawing items | Supply and install 3 uPVE to water pm 568] [Supply and install PE tank 5000 Titres |Ne 2 [TOTAL | Prclininary | —[eieamcsiog PRING BOK 2irower [FENCE (Tora [586 PRELIMINARIES 10%6 CONTINGENCIES [GRAND TOTALS Co Bo@ for civil works - Water Tank Support for spring box anti 7 Rate | Amount Description Qty Unit (Le) (Le) PRELIINATTE | Mebitzation’ Demobiization 4] tem [TOTAL FOR PRELIMINARIES CARRIED TO PROJECT summary EXCAVATION sTHWORK tear ste ofall bushes, sus, undergrowth and debris and tem 4arteway trom site Excavating ver ste to remove top sol average TeOmm deen. | ao] yg 2 [seposted a distance rom foundations Beeman Frcavatna: pts to receive bases ofiostod coumne stating at) 45 | site strip level; maximum depth not exceeding 1500mm (anny ™ 3 Suave teat |Level ang compact botiom of excavations: 17.4) mt A IEXCAVATION AND EARTHWORK CARRIE! many IGONGRETE won BLINDING (1:96 - 3mm syne 75m tek in y 2081-20 column bases pis 4 nr 7206) WCONGRETE (Concrete 1.24 12mm aynhe acnrecate) F 3|Bases 0.6x1.26x1.20-4nr 10.37) om 4;Columns: 0.3x0.3x4.8- nr 9.50| im 5|Braces 4.32] om? 6ibeams 3.45] om 7|siab_ 40.58] im? Form Wo limber pizwoad as formwork i)|Bases | 34.55] im? 2{columns. 126.72[ om? 3}braces 37.44) mi 4[siabs 42.12) im sit Ns and batons to formwork 1299) Description Qty | Unit Rate Le| Amount ile) REINFORCEMENT ght tensile steel bars - BS 4449 4 2 Siraight and bent bars~ lbases 16mm diam, 0.54) Tonnes: .3[columa 16min diam, af tonnes 4[ column Bram diam: 027] tonnes Slbraces 1émm diam 0341 tenes: S|braces Tamm diam, 0.099] tonnes 7)eraces Emm diam, (0.089 tonnes: [beams 18mm diam 02) tonnes ‘9|bases &mmn glam 0.18] tonnes 30]slab 18m diam. O5| tonnes -ONGRETE WORK CARRIED TO SUMMARY ING IN-SITU FINISHES | 1277" thick plastering ; trowelied to smooth finish 203.4) pre [Cer id sand (1:6) bed on concrete 13] 50mm thick sereeded; trowelted ta smooth fnish 52.09] PROTECTION OF SOLAR PANEL 22 /Provide and instal fabricated steel casement frame [50mm x SOmm angle iron welded together, and ifitem with holdtast fixed on concrete tase all finish with jantiust pains, overall size: (600mm x 500mm} Water Tank Brought to SUMMARY ~ Ny LOT 6 BOQ FOR FENCING FOR SPRING BOX Ten DESCRIPTION ary UNIT RATE SLL, [amount soc ‘SITE CLEARANCE [Carefully clear the whole site off lunwanted material and cart away all {debris from site |EXCAVATION AND EARTHWORKS JExcavate trench for foundation lcommencing from ground leve! depth not exceeding 1200mm deep. Excavate pit for column base lcommencing from site strip level not lexceeding 300mm deep Ditto Extra excavation in rock Disposed excavated materials in spoil heap for re-use IoTAL FORMWORK AND ISUPPORT Formwork and support to vertical aces of ‘Columns [Retaining wall lrora. 25 10 145 455 161 Trem DESCRIPTION ‘ary UNIT RATE SLL ‘AMOUNT SLL TEWORK Invsitu concrete in normal mix 1:2:4- 20mm/ager. Pour in base 25 [Cotumns: coping TOTAL re 7 }12mm dia, Rod in: [Column bases and columns Coping l6mm diameter steel rod as stirrup in columas HroTaL |suockwork Jcement and sand mortar average mix: 1:5 150mm thick TOTAL ANCILLARY WORKS [Provide and installation camplete with hinges, locks and tower baits steel gate Provide and fix razor wire and Y-bars on perimeter fence jrovat, |SATEHOUSE SUPPLY GATE [TOTAL 05 08 03 200 120 Ton Ton Ton nr Stem ISPRING BOX [Tower \FENCE [BOREOLES [536 PRELIMINARIES 110% CONTIGENCIES [GRAND TOTAL FOR SPRING BOX OVERALL SUMMARY. DESCRIPTION [SPRING BOX Puc to Adapter to pdaptoe Stand Post Section Stand Post Plan Pepa Te Te ‘Sierra Leone Spring Box isn |GBele Dang Chefdom saeerey a ee ‘Spring Bax Pan - Ginle Ding Chior pera ane B= BNE on axe Saring Box Layout 2 ~ Genie Dizon Ciieféom © ae Climate Smart Infrastructure And Low ‘Cost Water Soply tn Serr Laone ca ‘aT Spring Box Section « Gini Ging Crier SECTION S-S a sounbne| = Drainage Channel Sections Jy ane Pe Section C-C Section B-B FE TRopicst water Proce Bonale fami nee” __ Kambia,Kono, [ae Moisty of Water Resources ot Reference me |Org.ttie: BORE HOLE PDeanage Channel Sections Designed by Water Directorate Drawn by|ing Sam Goba ] RC Concrete Apron ae ale Reinforcement plan Borehole with concrete Apron,Wall and Drainage channel (vertical section) VERTICAL SECTION OF A BOREHOLE( SCHEMATIC) — _—e 150mm Block work 100mmThick Conerete :3:6 20mm agg SOmm Hard core .) / 4 ¢ Section D-D Foundation Section of wall Tc KoinaduguKambia,Keno, Bonthe & Pujehun District, NOTES Al dimensions aren mllemotere ‘and camjorm ta BS standards ‘and mi rato Beatin: ients S.A LAW. A, C.O. ——— Refienee organi: ELEVATED STORAGE, ‘TANK WITHSOLAR Feunatin Section Desi ignes by J.H. KAMAKDA, Drawn by 2.8, KAMARA Approved by] DK KAMANDA. ‘Seale 1:50 Date Pury, 2015 NOTES 600mm Extension First Slab "SE ERomroest water Poet {> Se conga st tea Soka Powered Netware a ) acetone [tesem — ,Kambia,Kono, & Pujehun District. Venti. Space o} 600mm x Son i } Reference No fa ra ttle: BLEVATED STORAGE oe ‘TANK WITH SOLAR, ‘Coaat Room floor lan Designed by Mater Doctorate Brown by Ing Sem Gone poproved nye Seale 1:50 Date [october 2076 brg No, GEFTUNDPICeStLO08 7 a _ NOTES “Al domensons aren llemeters and corjorm to BS standards ond mera eles pte ip ef mre ecg a | Project: ‘GEFTUNDPIGoSL [este Aea Kambia,Kono, & Pojehun District. Client: eter Directorate Misty of Water Resources Reference Drg.tti: ELEVATED STORAGE TANK WITH SOLAR = Frown Side Elevation = | Designed by Jr Directors = i | Drawn by lng Som Gata : ae i approved by| a = ‘7 = Scale 1:50 Front View Side View Date [October 2016 ra No. Gernnomsesiou7 100mm «fe I Column footing na 2am rad i ac Geom grad eray Section x-x mm Ls | Columns and Reinforcement Details NOTES ll dimonsans ara wlometore ‘and eoraform to 85 senders ‘ond mir role Projects RURAL WATER SUPPLY AND] SANITATION PROJECT CConstrstion of Bore Hole & Soler Powered Network scseone Koinadugu.Kambia.Kono, Bonthe & Pujehun District, Client: S.A. LAW. C.O. Tot we [1 Reference Dro.tites ELEVATED STORAGE ‘TANK WITHSOLAR, ‘Couns & Relnforcemeat Designed by 1. KAMANDA Drawn by AE, KAMARA ean] ‘scale Bate puy2008 | SECTION T-T Ieee ciate smart inastuctre and Low cost water Supply tn Sierra Loane Seneca L____se@__] SECTION X-X Spring Bex Pan “Gbine Ong ar Cte Smart Tnfraseucture And Low ot Water Suply tn ‘Stara Leone ate —- Wate: Tower = ‘Ginle Dining Chiettom at! New rr y ste ie Lor EXCAVATION AND EARTHWORK 1 Datum and Nature of Excavation The Contractor shali be responsible for setting up and maintaining a site datum level, ‘Zero’ datum shall be given on the site by the Engineer, unless otherwise noted an the Drawings. Information pertaining to the nature of the ground may be given to the contractor, when available, but without any guarantee of correctness or accuracy. 2 Setting Out Each Benchmark (B.M.] or centerline for the butlding anc/or other constructions tobe under this contract, shall be properly set out by the Contractor as shown on the Drawings and inspected and approved by the Engineer prior to commencing excavations. 3 Surface Leveling All earth works on Site shall be completed before any fill is deposited. Excavations over areas Of Site or filling with approved material shall be carried out where required to the levels shown on the Drawings or to such ather levets as may be directed by the Engineer, 4 Size and Depth of Excavation Excavation shall be cut to the size of the foundation shown on the Drawings and taken down to the foundation levels shown on the Drawings. If, without the Engineer's written instructions, the Contractor goes down below the foundation level specified, he shall fil up the part so excavated with concrete of the same type and grade as that required for the piles as defined in Concrete Works and the Bill of Quantities at his own expense. 5 Shoring Excavations and Dewatering ‘the sides of excavations shall be supported as necessary te maintain a vertical face and/or to prevent caving-in of any nature, especially during subsequent operations. The Contractor shall be responsibie for the design, supply, fixing, safety and removal af all planking, strutting and shoring required to the side of the excavation. The Contractor is responsible on the type and nature or soil to be excavated; also he is to use any equipment, including dewatering equipment, to carry out the work required by this Contract, 6 Types of Excavations Excavations shall be classified according to the nature of the materials to be removed either as excavation in rock ar as excavation in earth, Excavation in rock shall be classified as including all excavations in hard and consolidated materials which cannot 8 removed by normal excavation tools and equipment, and which require drilling er other special meens for their removal, All excavation which is not in rock shall be defined as excavation in earth, 7 Required Bearing Capacity ‘The Contractor shall notify the Engineer and obtain instructions if the required bearing capacity: ale (2) is obtained at a lesser depth than that shown on the drawings. (2) is not abtained at the deoth shown on the drawings. Excavation bottoms are to be aparoved before new work is laid on them. The Contractor is to infortn the Engineer when excavations are ready for inspection. if, after approval, surfaces become unsuitable due to flooding or other causes, the Contracter shall excavate further, backfill with approved filing material and compact to approval at no extra cost to the owner Should the soll condition, after the Engineer has been informed the excavations are ready for inspection, be such that the Engineer deems it necessary to carry out tests, the Contractor shall perform such tests to the satisfaction of the Engineer. Any expenses incurred in the performance of such tests are deemed to be included by the Contractor in his tender. 8 Preparation and Inspection of Excavation All excavations shall be kept free of water arising from whatever source, and shall be properly cleaned out of all loose and foreign matter, leveled and rammed. The Contractor is to report to the Engineer when excavations are ready for inspection and all excavations are to be approved before any further work is done. Filling Allfilling materials shall be approved by the Engineer before beingpplaced in position. Approved earth, sand, or any other suitable material free from rubbish shall be used to make up levels as shown on the Drawings. ‘The material shall be placed in successive layers each having 2 finished thickness not exceeding 250mm before compaction, watered and compacted to at least 98% compaction ratio of the maximum dry density of the Modified Proctor test ( ASTIM D-1557} prior to the placement of the succeeding layer. Any exposed side or edge of fill shall be properly and evenly graded toa slope as directed or specified. When the required quantities of approved fill are not found on Site the Contractor shall, at his ‘own expense, obtain them from locations approved by the Engineer. Filling to make up levels under building shal! be executed with approved sultable material fram existing ground levels, Up to underside of ground floor slab, and shall be be olaced in successive layers each having a finished thickness not exceeding 250mm, watered and compacted to at least $8% compaction ratio of the maximum dry density of the Modified Proctor test { ASTM D-1557) prior to the placement of the succeeding layer. The ground surrounding the butlding and pavernents shall be filled with approved material, fine sand and coarse materials, free of foreign materials, debris, clay ‘umps, organic and vegetation. a) Coarse materials: Such as sandy gravel, gravelly sand, ..etc., which is the material retained ‘on sieve no. 4, and consists of crushed rock, It shall be clean, hard, tough and free from deleterious substance. b} Fine Sand Materials Shall consist of thet portion of the total aggregate/fines passes no.4 sieve, such as sand, silty sand, etc, 10 Disposal of Surplus Material All surplus excavated material not used in backfilling oF levelling shall be loaded and transported elsewhere on the Site as required by the Engineer or, if not required on the Site, shall be loaded and carted away from the Site ta a dump to be selected by the Contractor and approved by the Municipality at the Contractor's own expense. All rubbish arising from the Works shall be cleared away and removed from the Site as it accumulates per the Engineer's instructions and on completion of the Works ue CONCRETE WORK General All materials shall be subject to such tests as the Engineer may direct and provision for such tests shall be included in the price for such materials inserted in the Bill of Quantities or Schedule of Rates unless otherwise provided for. [n case such tests required by the Engineer, an independent and officially authorized lab shall carry out such tests and sampling. Properly representative samples of all materials to be used in the works shall be submitted by the Contractor for the Engineer's approval when required. Where tests are required by the Engineer, the Contractor shall take samples and send to @ firm experienced In analysis of the material. Reports shall be submitted to the Engineer. The Contractor shall bear all expenses consequent to the provisian, taking and cartage, etc. of samples, in additlon to the costs of performing the tests and reporting the results. The Engineer reserves the right to reject any material which, in his opinion is objectionable in any respect, not withstanding its apparent compliance with the relevant Standards. Any such rejected material shall be removed from the site at the Contrector’s expense at once. 2 Formwork for Concrete The Contractor shall supply, design, erect, strike end remove the formwork and be entirely responsible for Its stability and safety so that it will cerry the fresh concrete and all incidental loadings and preserve it from damage and distortion during its placing, vibration, ramming, setting and curing, Itshall be so constructed as to leave the finished concrete to the dimensions shown on the Drawings and of 2 material capable of providing the surface finish specified. In ‘any avent, the maximum permissible deflection under all loads shall not exceed 2mm or 4/600 ofthe free span, whichever is lass. Formwork shalll be of timber and / or metal and shall include ail temporary concrete moulds and their supports. Bolts to be used for fixing the formwork shall be approved by the Engineer before staring the work For concrete surfaces, which are to remain, exposed wrought formwork shall be used. Wrought formwork shall be of timber or steel framing lined with 12mm thick smooth-faced plywood or ‘an equal lining approved by the Engineer, or of metal , suitable to obtain a falr face finish on the concrete. All external angles or fair faced in-site concrate shall have chamfers formed with 15x15mm {(5/8"x5/8"} wrought hardwood angle fillets planted in the angles of the formwork , unless iarger chamfers are shown on the drawings. Formwork ready to receive concrete shall be thoroughly clean and the internal faces properly painted with approved shutter oil or other preparation. Joints shall be tight to prevent leskage, Wherever required and prior to placing of the reinforcement the internal surfaces of all formwork shall be treated with an approved mould oil, All formwork shall be inspected end approved by the Engineer prior to concreting, gly ‘This approval, however, does not relieve the Contractor of any of his responsibilities, The striking of all formwork shall be carried out with the greatest of care to avoid damege to concrete 42 The formwork to vertical surfaces such 25 walls, columns and sides of beams may be removed in accordance with the table below although care must be taken to avoid damage to the concrete, escecially to arrases and features . Minimum periods in days for striking other formwork should be in accordance with the following table, or as directed by the Engineer Ordinary Portland Cement Concrete Slabs 3 (props left under} Beam soffits 7 (props left under) Props to slabs 7 Props to beams 16 Vertical surfaces as walls, columns and sides of beams 3 Formwork, shuttering, props, or any other means of temporary or semi-permanent support shall not be removed from the concrete until the concrete is sufficiently strong to carry safely the load (dead and temporary}, The Contractor shall inform the Engineer when he is ready to strike the formwork , or remove any form of temporary support , and shall obtain his written consent before proceeding . The times given for the removal of props are based on the assumotion that the total live plus dead weight to be supported at the time of removal is not more than one half of the total design load . For horizontal members where the loading is to be @ higher proportion of the total design load these times may need to be increased, The Contractor shall be responsible for any damage to the concrete work caused by or arising from the removal and striking of the forms and supports Any advice , permission or approval by the Engineer relative to the removal and striking of forms and supports shall not relieve the Contractor from this responsibility . Any work showing signs of damage through premature loading is to be entirely reconstructed at the Contractor's expense ‘The Contractor shall confirm positions and details of atl {a} permanent fixings (b) pipes and conduit (c} holes and chases to ensure thet alterations are not made without the knowledge and approval of the Engineer. The Contractor shall fix inserts or box out as required to correct positions before plecing concrete, and shall form all holes and chases. He shall nor cut hardened concrete without approval, 3 Reinforcement for Concrete Steel reinforcement shall generally be hot rolled mild, medium or high yield steel smooth sound of deformed bars complying with 8S 4449 or similar approved standard. In case any other type of reinforcement is required, itshall comply with the requirements of the Particular Specification . 13 All reinforcement shall be free from rust and mill scale and any coating such as cil, clay, paint ete which might impair the bond with the concrete. Manufacturer's test certificates for all classes of reinforcement shall be supplied when required. Specimens sufficient for three tensile tests and three cold-bending tests per ten tons of bars of fractlon ls thereof and for each different size of bar shall be sempled under the supervision of the Engineer. Testing shall be in accardance with BS 4449 or other approved standard and batches shall be rejected if the average results for each batch are not in accordance with the specification. All tests should be made on the Contractor's expense. All steel is to be totally iree from dirt, paint, loose rust or scale when in position ready for concreting. The Contractor shall cut and bend bars to BS 4466 and to schedule provided unless otherwise instructed by ‘the Engineer. Straight sections of bars must be kept out of winding, The internat radius of bends shall in no case be less than four times the diameter of the bar, except for stirrups, column binders, and wall sheer bars which are to be bent to fit closely around the main bars, Great cares to be taken to bend stirrups and columns binders separately and to the sizes shown. All bars will be cut and bent cold using approved machines. Lengthening of bars by welding, and rebinding of incorrectly bent bars will not be permitted, except where requested by the Engineer. The Contractor shall provide on-site facilities for hand bending to deal with minor adjustments. Unless otherwise allowed for in the specification splices in reinforcing bars shall be formed by lapping. Such laps in bars in any member shall be staggered. Except es otherwise indicated on the drawings the minimum overlap of lapped splices shall be 50 bar diameters or 400mm whichever Is greater. ‘The steel is to be fixed in position exactly as indicated, and the bars are to be securely wired together with 1.6 of 1.4mm soft iron wire or appraved spring steet clips wherever necessary to prevent any displacement during concreting, Spacers, chairs and the like, temporary or permanent, are to be used as required to ensure that the stee! has the exact amount of cover Indicated. No permanent spacers, may show on a surface where a fair faced concrete finish or a brushed aggregate finish are required. Type of spacers shall be approved by the Engineer before starting the work. Unless otherwise indicated, the minimum cover to the reinforcing bars is to be as listed below, or equal ta the diameter of the bar, whichever is greater. Position ‘Minimum cover - mm Main bars in internal faces of columns and beams 25 Main bars in external faces of columns and beams 30 Main bars in floor slabs and soffits of roof slabs. Handling Aggregates ‘The choice and preparation of sites for stockpiling of aggregates, the number and sizes of stockpiles and the methods adopted to prevent segregation of component sizes shall be agreed with the Engineer. Coarse aggregate shall be stockpiled in three separate gradings: 38- 19mm, 19-10mm, 10-Smm. When aggregates of different gradings are stockpiled close together the stockpiles shalf be separated by bulkheads. Stockpites are to be on concrete or ‘other hard surface sufficiently sloped so that water is not retained in the base of the stockpiles. All agaregates are to be hendled frorn the stockpile in such a manner as to secure a typical grading of the meterial, care being taken to avoid crushing the aggregates and contamination with extraneous matter. Aggregates need not be stockpiled when a crushing-screening plant is used in tandem with a batching plant properly equipped with several bins for different sized aggregates heving the appropriate weighing scales at such bin such that 2 mix of the desired gradation is obtained consistently and the whole operation Is conducted to the satisfaction of the Engineer. Water Unless otherwise authorized in writing by the Engineer, only water from potable supply system may be used for mixing concrete and other products containing cement. Similarly, only potatle water may be used for curing conerete and cement products during the first 24 hours after pouring. Later, fresh water, or other water containing not more than 4750 ppm dissolved solids of which not more than 1000 ppm may be chlorides, may be used for curing. No additives of any kind shail be used in the concrete without the express approval In writing of the Engineer. Batching And Mixing Of Concrete All concrete shall be batched by weight and mixed mechanically. Hand mixing shall not be allowed except only upon the written permission of the Engineer. Concrete may either be batched and mixed on site or outside the site and transported thereto When mixed outside the site and transported to it, batching and mixing shall be in accordance with ASTM Specification C94, ‘Standard Specification for Ready-Mixed Concrete’ . When mixed on site, batching and mixing shall be as follows: BATCHING BY WEIGHT: The cement and each size of aggregate shall be measured by weight. The water may be measured by weight or volume. The weight-batching machines used shail be of a type approved by the Engineer and shal be kept in good condition while In use on the Works. Checks are to be made as required by the Engineer to determine that the welghing devices are registering comrectly. BATCHING AGGREGATE BY VOLUME: When batching aggregates by volume is allowed as and when required, the cement shall be batched by weight and the water by weight or volume, Each size of ageregete shall be measured in metallic containers the depth of which is at least equal to their greatest width, The containers shall be of such shape that thelr volume can be easily checked by measurement. MIXING CONCRETE: the location of the batching and mixing plant shall be agreed with the Engineer. The amount of concrete mixed in any one batch is not to exceed the rated capacity of the mixer. The whole of the batch is to be removed before materials for @ fresh batch enter the drum. On cessation of work, including all stopnages exceeding 20 minuites, the mixers and all handling plant shall be washed with clean mixing water. If ald concrete deposits remain in the mixer drum, they shall be rotated with clean aggregate and water prior to production of new concrete. 20 Concrete mixed as above is not to be modified by the addition of water or in any other manner to facilitate handling or for any other reason. oli Admixtures No admixtures of any type shall be used in the preparation of concrete or concrete products Unless s0 required by the Particuler Specification or unless so directed by the Engineer. In case any such admixtures are used the rates and methods of application shall be strictly in accordance with the manufacturer's instructions which must be approved by the Engineer before using it.

You might also like