Erection Methodologyof Tower Crane Zoomlion

W450-25HC
目 录 01 Tower Crane Specification

02 Tools , Tackles & Telescopic Crane requirements

03 Safety Precautions

04 Protective Earthing

05 Erection Steps

Safety Device’s
06

Climbing Operation & Commissioning


07
of Tower Crane
5.11 Installing a 3.9t counter ballast

• Lift the counter ballast using Mobile Crane & Install a counter
ballast of 3.9 t in to the first (jib side)
counter ballast slot of rear counter-jib referring attached picture,

 Counter weight lifting height 29 mtr


Page 18
5 Installing the counter-ballast

The counter-ballast block according to chapter 4.11. And the other counter-ballast, as shown in Table 4-8 Installing the
counter-ballast
Page 24
5.19:Installing the rest counter ballasts & Winding the trolley & Hoist wire rope

• Install the rest counter ballasts using Mobile Crane .

• After installing the rest counter ballast need to do trolley wire &
Hoisting rope winding according to the picture .
6: Safety device’s

• The safety devices of tower crane include: moment cutouts, load limiters, traveling limiter (include
hoisting limiter, trolley limiter, slewing limiter) and weathervane. The safety device of this tower crane,
besides the above mechanical limiter, also has electronic safety device in the auxiliary safety monitor
system. The installation position of the safety devices shows in Figure.