Professional Documents
Culture Documents
Evaluation Report
Evaluation Report
Evaluation Report
TRANSFORMER
MATERIALS
22 150mm2 Cable lugs 10 pcs 10 pcs 10pce -
23 70mm2Cable Lug 12pcs 5pcs 7pce -
24 70mm2 cupper wire 100mtr 50 mts 50mts 50mts
25 Galvanized earth rod 22pcs 11 pcs 11pcs 11pcs
26 Earthen materials 1 set 2set
Evaluation report 23rd November 2023
PROJECTION Akesan Relocation of Electrical Facility
CHALLENGES
MATERIAL Shortage of materials, some materials as been
exalted and some are very little.
40feet poles 40feet poles are needed, for the dual line and
cross over.
Tree obstruction There are trees which are obstructing the transfer
of lines across the road.
=277,000
4 I. Relocation of 16 lines 160,000 One
transformer 8 ladders 32,000 /10/23 transformer, 10
II. Transfer of HT lines 4 Grounding 20,000 span is
III. Remover of old labor 15,000 expected to be
poles. Hiab 35,000 transfer.
Digging 30,000
=287,000
5 16 lines 160,000 /10/23 To completion
I. Transfer of lines 8 ladders 32,000
II. Work on the 33kv on 2 Grounding 20,000
both junction of Hiab 35,000
Akesan and Ignodo. Digging 30,000
III. Remover of old poles
and replanting =277,000