Professional Documents
Culture Documents
M4 - Environmental Impact Assessment - Part 1
M4 - Environmental Impact Assessment - Part 1
Screening
The EIA process begins from the very start of a project.
Once a developer has identified a need and assessed all the possible
alternatives of project design and sites to select a preferred alternative, two
important questions must be asked:
What will be the effects of this development on the environment?
Are those effects significant?
If the answer to the second question is 'yes', an EIA may be required.
Answering this question is a process known as screening and can be an
essential first step into a formal EIA.
The EIA process is, and it must be stressed, iterative. The developer would
need to reassess the project design with the view of reducing the significant
impacts to a level where an EIA is not legally required (Nielsen et al 2005).
Scoping
Where it is decided that a formal EIA is required, the next stage is to define
the issues that need to be addressed, that is, those impacts that have a
significant effect on the environment.
Scoping is essential for focusing the available resources on the relevant issues.
Baseline study
Collecting all relevant information on the current status of the environment.
This provides a baseline against which change due to a development can be
measured.
Impact prediction
Impact prediction involves forecasting the likely changes in the environment
that will occur as a result of the development.
Impact assessment
Impact assessment requires interpretation of the importance or significance
of the impacts to provide a conclusion, which can ultimately be used by
decision‐makers in determining the fate of the project application.
Mitigation
Frequently, the assessment of impacts will reveal damaging effects upon the
environment. These may be alleviated by mitigation measures.
Mitigation involves taking measures to reduce or remove environmental
impacts.
Successful design of mitigation measures could possibly result in the removal
of all significant impacts; hence a new screening exercise would reveal that
there might have been no need to carry out a formal EIA had the mitigation
measures been included from the start.
EIS review
Once the EIA is complete, the EIS is submitted to the competent to permit or
refuse development applications. It is essential, therefore, that the EIS must
be reviewed.
Basically, the review process should enable the decision‐maker to decide
whether the EIS is adequate (e.g. whether it is legally compliant), whether
the information is correct, and whether it is unbiased.
If it is, they are then in a position to use the EIS as information to be
considered in determining whether the project should receive consent.
Follow up
Follow up relates to the post‐approval phase of EIA.
It includes monitoring of impacts, the continued environmental
management of a project, and impact auditing.
Follow up presents an opportunity both to control environmental effects
and to learn from the process, and cause‐effect relationships. Ideally, data
generated by monitoring and other aspects of follow up should be compared
with the original predictions and mitigation measures in the EIS to determine
the accuracy of the original predictions
the degree of the deviation from the predictions
the possible reasons for any deviation
whether mitigation measures have achieved their objective of reducing or eliminating
impacts
Information generated by this process can contribute to the improvement of
future EIA practice, for example, by enabling more accurate predictions to be
made.