3.6.

Wiring backup connector plugs, cable connection between backup connector plugs

QUICK INSTALLATION GUIDE of hybrid inverters and backup combiner cabinet have finished.
Backup disconnection between hybrid inverter and backup combiner cabinet, at
this moment only switching off the backup breaker are not enough yet, please must
System Wiring and Commissioning for all theInverter Operation in Parallel
unplug the backup connector plug from the backup connector socket for all hybrid
inverter.
3.7. Disconnect the meter communication cable to hybrid inverter.
01 SCOPE OF DELIVERY
Don’t install the PARA modules to hybrid inverters.
3.8. Switch on the battery breakers of hybrid inverter.
Switch on the battery breakers of the batteries directly below the hybrid inverter.
Short press the battery power buttons of the above mentioned batteries.
3.9. At this moment, the hybrid inverters will enter UPS state.
Parallel communication Configure the network and put the hybrid inverter online.
PARA Board Communication cover Battery power cables M3 ×10 Screws SC16-6 OT Terminal
cables 3.10. Contact service to upgrade the EMS and DSP firmware supporting parallel operation of all hybrid inverter. Check
the LCD of all hybrid inverter to see whether the firmware upgrading has been finished successfully.
3.11. Switch off all battery breakers of hybrid inverters and batteries.

04 SET MODE OF HYBRID INVERTERS


Label 4.1. Unplug the battery communication cable between hybrid inverter
and the first battery (directly below hybrid inverter).
02 SYSTEM AC WIRING TO GRID AND BACKUP COMBINER CABINET 4.2. Switch on the battery breakers of hybrid inverter.
Switch on the battery breakers of the batteries directly below the hybrid inverter.
Short press the battery power buttons of the above mentioned batteries.
Wiring sequence From Cable type To
4.3. At this moment, the hybrid inverters will enter WAITING state.
Three-core (L, N and PE) 4.4. Installer must execute parallel setting on the LCD of the hybrid inverter.
1 Mains grid or generator Grid combiner cabinet
outdoor copper cable, 25~35 mm2 Click menu “Setting”,“Function”,“Parallel”,“AC Parallel”,and set the “Host” for host hybrid inverter, set the
2 Grid combiner cabinet
Three-core (L, N and PE) Grid connection port of the host “Follow” for other two hybrid inverters.
outdoor copper cable, 10 mm2 hybrid inverter
Click menu “Setting”,“Function”,“Parallel”,“DC Parallel”,and set the “Host” for all hybrid inverters.
Three-core (L, N and PE) Grid connection port of the follow
3 Grid combiner cabinet
outdoor copper cable, 10 mm2 hybrid inverter
AC parallel DC Parallel Check the LCD of all hybrid inverters to see
Three-core (L, N and PE)
4 Loads of backup side Backup combiner cabinet whether the parallel setting have been set
outdoor copper cable, 10~16 mm2 Only one of Hybrid inverters Host Single
Three-core (L, N and PE) Backup connection port of successfully.
5 Backup combiner cabinet Other Hybrid inverters Follow Single
outdoor copper cable, 4~6 mm2 the host inverter

Three-core (L, N and PE) Backup connection port of the


6 Backup combiner cabinet 4.5. Switch off all battery breakers of hybrid inverters and batteries.
outdoor copper cable, 4~6 mm2 follow hybrid inverter
4.6. Switch off the AC breakers between AC connection port of the hybrid inverters and
03 UPGRADE FIRMWARE OF THE HYBRID INVERTER the mains grid or generator.
Insert the grid connector plugs into the sockets for the grid connection of the hybrid
Please comfirm the following connection inverters, make sure to align the key on the grid socket with the key way on the grid
3.1. Electrical Connection Between the Batteries have finished. connector bush insert.
3.2. Communication Connection between the Batteries have finished. 4.7. Switch off the AC breakers between backup connection port of the hybrid inverters and the loads.
3.3. BAT Power Connection Between the Battery and Hybird Inverter have finished. Insert the backup connector plugs into the sockets for the backup connection of the hybrid inverters and screw
3.4. BMS communication cable connection between the host hybrid inverter and the first battery (directly below tight. When doing so, make sure to align the key on the backup socket with the key way on the backup connector
hybrid inverter) have finished. bush insert.
3.5. Wiring grid connector plugs, cable connection between grid connector plugs of hybrid inverters and grid combin-
er cabinet have finished.
Grid disconnection between hybrid inverter and grid combiner cabinet, at
this moment only switching off the grid breaker are not enough yet, please
must unplug the grid connector plug from the grid connector socket for all
hybrid inverter.

4.8. Other communication connection of host hybrid inverter.

01 02
Please finish BMS communication cable connection between the host hybrid inverter and the first battery.
Parallel connection diagram for three inverters

Please finish meter communication cable connection between the host hybrid inverter and meter.

05 COMMUNICATION CONNECTION OF PARA BOARDS


Plug in the PARA boards and do communication connections between the inverters in parallel, steps as follows. Then
do communication connections between all the batteries in parallel, refer to the relative system wiring diagram of paral-
lel installation.
Parallel connection diagram for two inverters
Warning:When plug in or take out the PARA board, the system must be power off.

a. Disassemble the communication cover A A


B B
C C

4
D D
1

3 2

TX10×150mm
0.6-0.7Nm e. Secure the communication cover

b. Plug in the PARA board


1 4

2
TX10×150mm 3
0.6-0.7Nm

06 POWER ON AND OFF THE SINGLE PHASE PARALLEL SYSTEM


6.1. Detailed steps for power on the single phase parallel system
Ensure a reliable and correct installation and electical connection before power on.
c. Install the parallel communication cable
a. Switch on the AC breakers between backup connection port of the hybrid inverter and the loads.
b. Switch on the battery breakers of all hybrid inverters.
2 c. Switch on the battery breakers on all batteries.
1
2
d. Short press the battery power buttons. All power buttons should be short pressed within 30 seconds.
e. Switch on the AC breaker between AC connection port of the hybrid inverter and the mains grid or generator.
f. Switch on the PV switches all hybrid inverters.
1
2
6.2. Detailed steps for power off the single phase parallel system
a. Switch off the AC breakers between backup connection port of the hybrid inverter and the loads.
b. Switch off the PV switches of all hybrid inverters.
c. Switch off the AC breaker between AC connection port of the hybrid inverter and the mains grid or generator.
d. Power off all the batteries by long pressing the power buttons of the batteries about 5 seconds which is near
d. Wire the communication connection of inverters in parallel the battery breaker.
NOTE:Attach two identical labels to both ends of one communication cable, to distinguish between different e. Switch off the battery breakers of all batteries.
communication cables. f. Switch off the battery breakers inside the battery combiner cabinet.
g. Switch off the battery breakers on all hybrid inverters.