Calibrating gas custody

transfer flow computers


Application Note

Gas custody transfer flow computers that calculate flow by measuring the
differential pressure across a flow restriction, such as an orifice plate or other
differential pressure flow device, require special calibration to perform at
optimum accuracy. In custody transfer applications where the buying and selling
of commodities like natural gas is involved, calibration checks are performed
frequently as a matter of fiduciary responsibility. For the purpose of this application
note, the use of gas custody transfer flow computers in the natural gas
transmission industry is referenced.
Flow computers need multiple measurements to calibrate each device. In the
normal application, three measurements are made: volumetric flow, static (line)
pressure and temperature. A calculation is performed using this data to determine
the actual mass of the gas flowing through the pipeline.

The Fluke 721 Precision Pressure Calibrator has


special features that support the complete calibration
721 PRESSURE
CALIBRATOR

of natural gas multi-variable electronic flowmeters F1 F2 F3

and other types of flow computers. With two internal


ZERO

V
mA

7.21psi
30V
24mA
MAX

pressure ranges, external Fluke 750P pressure mod-


COM

ules and an optional precision RTD probe, all of the


calibrations required for the flow computer can be
performed with just one instrument. Pump

The Fluke 721 is available with two built-in PRT Probe

pressure ranges from from 16 psi/1 bar up to Close Close


5000 psi/345 bar. For this application, the valves valves

configuration with the low pressure sensor (P1)


16 psi/1 bar and high pressure sensor (P2) of
1500 psi/100 bar is frequently the best fit. Since the
Fluke 721 has an accuracy specification as a percent Fluid Fluid
of full scale, it is important to closely match the full stream stream

scale of the calibrator to the scale of the application


in order to get the best performance. (See sidebar
on system accuracy calculation and importance of
Figure 1. Sample flow transmitter with calibration equipment attached.
maintaining an adequate accuracy ratio).
In addition to the calibrator itself, a high and
low pressure calibration pressure source will be
needed. An accessory RTD probe is also required
for measuring temperature. An appropriate low Gas custody transfer flow computer
pressure source with 0.01 inH2O of resolution is operational theory
needed for the low pressure test, and a high pres- Custody transfer flow computers are called by a
sure source such as a regulated nitrogen bottle or variety of names including electronic flowmeters
hydraulic hand pump are required. One pump style (EFMs) and multi-variable flow computers, but they
typically does not work well for both tests or exten- all feature some common principles of operation.
sive cleaning is required to switch from hydraulic 1. Volumetric flow measurement uses some type of
(oil or water) to pneumatic testing. High pressure flow restriction such as an orifice plate or other
pumps typically do not have the desired resolution differential pressure flow device to generate a
for the low pressure test. pressure drop. The differential pressure created

F ro m t h e F l u k e D i g i t a l L i b r a r y @ w w w. f l u k e . c o m / l i b r a r y
across this pressure drop is measured by the Industrial applications use either the analog
flow computer as the primary measurement. It output of the flowmeter (4 to 20 mA) or a digital
is based on the principle that flow velocity is output like the HART signal to get data from the
proportional to the square root of the pressure flowmeter to a control system or data acquisition
drop. The volumetric rate is then calculated from system.
the velocity by knowing the diameter of the pipe This analog output is generally not used in
in which the gas is flowing. gas pipeline applications. Instead, the flowmeter
The measured pressure drop (differential) is is a specialized device that operates standalone
typically around 200 inches of water column to measure and record the total mass flow
(“WC) or 8 to 10 psi. through the pipeline. The total is periodically
2. To convert volumetric flow to mass flow you “downloaded” from the flowmeter to be used in
also need to know the density of the mass per an accounting of gas flow and custody transfer.
volume of the flowing media. The flow com- This information is also often sent through wire-
puter makes this calculation using 2 additional lessly to a central control point in operations.
measurements, plus a range of factors/constants The flowmeter may be packaged with other
based on the flowing media. The two additional electronic devices to be able to perform this
measurements are the static pressure of the gas function or it may be purpose manufactured,
in the pipeline and the temperature of the gas in which is the most common type.
the pipeline.
The static pressure in these applications How to calibrate the flow computer
ranges widely from a low of about 300 psi/
20 bar to a high of about 2000 psi/138 bar. Each flow computer manufacturer has created
The temperature of the gas is usually at a proprietary method of calibration, but they all
ambient, so it is within the range of normal use the same general technique, which will be
environmental conditions. described here.
3. A final consideration about flow computers is In these proprietary calibrations, the manufac-
how they are typically installed and used. turer has provided a software application, which
runs on a notebook computer (PC). The PC is

System accuracy determination


In order to effectively calibrate an instrument, the therefore generally be disregarded. As an alterna-
calibrator used must be more accurate than the tive to having a calibrator with the appropriate
instrument by some factor. The factor will vary ratio, users may elect to de-rate the performance
according to the application, but it should be as of the instrument to a value four times that of the
large as is practical. The minimum factor is gener- calibrator.
ally considered to be 3 to 4 times. The common For example, using a calibrator with ± 0.05 %
term for expressing this factor is Test Uncertainty accuracy would have a TUR of 4:1 testing an
Ratio or TUR. If the calibrator is 4 times more accu- instrument with an accuracy of ± 0.2 %. Due to
rate than the device being tested it is referred to as the continual advances in instrument technol-
having a TUR of 4:1. ogy, calibration technology may, from time to time,
The rationale behind this comes from a tech- fail to provide the necessary TUR to calibrate to
nique for the statistical analysis of the error in a the instrument manufacturer’s rated specification.
system. This technique is called Root Square Sum Alternately you can tighten the test tolerance to
or RSS. To determine the error in a system you take 80 % of the desired specification to gain the same
the square root of the sum of the errors squared confidence using a technique called guardbanding.
for all elements in the system. Note that this is not The fundamental concept of guardbanding is to
the maximum possible error in a system, but is the restrict the Pass/Fail limits applied to a calibration
largest error which is statistically likely. test based on a defined criterion. The purpose of
This formula describes the calculation, where Et guardbanding is to control the risk of accepting an
is the total error and E1, etc. are the errors of the out-of-tolerance unit, or rejecting an in-tolerance
individual components of the system. unit. Without guardbanding the result of a test will
be Pass or Fail. With guardbanding the result of a
2 2 2 test will be Pass, Fail, or Indeterminate. A Pass or
Et =2 E + E + ... + E Fail test result without guardbanding may change
1 2 n to a result of Indeterminate with guardbanding.
For more information on guardbanding refer to the
By using a TUR of 4:1, the effect of the error application note “Guardbanding with Confidence”
in the calibrator is reduced to a small percentage at www.fluke.com/guardbanding.
of the error of the instrument under test and can

2 Fluke Corporation Calibrating gas custody transfer flow computers


connected to the serial port or USB port of the flow 2. Differential pressure calibration
computer. In this way, the software both instructs a. The differential pressure calibration is
the user to connect appropriate signals to the flow performed using atmospheric pressure as a
computer (either pressure or temperature) and com- reference, so the low pressure connection of
municates that information to the flow computer so the flow computer or pressure transmitter is
that calibration errors can be corrected. vented and the high pressure connection on
Note: This procedure is a generic description of the calibration pro- the flow computer or transmitter is connected
cess using the Fluke-721-1615 as an example. The actual procedure to the low pressure port on the calibrator.
will vary based on the original equipment manufacturer’s design and b. Connect the notebook computer (PC) to the
instructions, test equipment used and on local process and policy.
flow computer serial or USB port. Use the PC
Detailed Procedure to initiate the calibration process.
c. The PC will instruct the user to apply one or
1. Setup more test pressures to the flow computer or
a. Turn on the calibrator and make sure that you transmitter. For example, on a device with a
see three measurements, usually [P1], [P2], full scale differential measurement of 200”
and [RTD]. If you only see two measurements, WC, the test pressures may be 0, 100 and
press F1 [P1/P2] until three measurements 200” WC. In each case, it is not necessary to
appear. If you see three measurements, but provide the exact pressure called for since the
not [RTD], press F2 [mA/V/RTD] until [RTD] user will also be prompted to enter the actual
appears. Refer to the user guide for more pressure applied at each test point.
information about calibrator setups. d. Set the hand pump pressure/vacuum con-
b. If needed, set the upper display (P1) to use trol to the pressure mode and close the vent
inches of water column (in H2O 60 °F) as the valve. Squeeze the pump handles until the
engineering unit, the middle display (p2) desired pressure is generated. The vernier or
to use psi as the engineering unit and the fine pressure control of the pump can be used
bottom display (RTD) to use °F as the engi- to adjust the pressure up or down in small
neering unit. Refer to the user guide for more amounts.
information about setting engineering units.
Note: 200” WC is approximately 7.2 psi. Since the pump can
Note: Once the calibrator has been configured to use these easily exceed this pressure, it may be best to apply repeated
settings, they become the default unless subsequently changed short squeezes of the pump to allow for better control. The rate
by the user. of pressure increase will be affected by the volume of the test
system with faster increases when the volume is lower.
c. If necessary, zero both pressure displays
while vented to atmosphere. Refer to the user e. When the differential calibration is complete,
guide for information about zeroing the pres- open the pump vent control and discon-
sure displays. nect the calibrator from the flow computer or
d. Isolate the flow computer from the process. (It transmitter.
is normally installed with a 5 valve manifold. 3. Static pressure calibration
Closing the valves on the process side of a. For the static pressure calibration, the test
the manifold will isolate it from the process). pressure will normally be applied to either
Be sure to follow local policy and procedure the same high pressure port or both the
when performing this step. high and low pressure ports simultaneously.
Refer to the manufacturer’s instructions for
details on the exact method of connection
+
TEST DC PWR
– ++ –
to perform this test. Connect the high pres-
721 PRESSURE
CALIBRATOR

sure sensor input (p2) to the appropriate port


on the flow computer or transmitter and to
the high pressure test source such as hand
pump or nitrogen bottle. NOTE: if the source
F1 F2 F3

ZERO

V
mA
30V
24mA
has 2 ports, one can be connected to the (p2)
input and the other to the port on the flow
MAX

COM

computer/transmitter.
b. The PC will instruct the user to apply one or
more test pressures to the flow computer/
transmitter. For example, on a device with
Figure 2. Sample set-up for Fluke 721 to low pressure side of
flow transmitter.

3 Fluke Corporation Calibrating gas custody transfer flow computers


a full scale static pressure measurement of c. This calibration is based on the concept that
1500 psi, the test pressures may be 0, 750 the same temperature is measured at both
and 1500 psi. In each case, it is not neces- thermowells and, therefore, the measured
sary to provide the exact pressure called for values should be identical. The PC will prompt
since the user will be prompted to enter the the user to enter the value observed on the
actual pressure applied at each test point. calibrator.
c. Use the high pressure test source to generate d. Remove the RTD from the test thermowell.
the called for pressures and enter observed The calibration is complete.
data when prompted. 5. Wrap up
d. When the calibration is complete, carefully a. Follow local policy and procedures and manu-
vent the system and disconnect the and facturer’s instructions for returning the flow
pressure source. computer to service.
4. Temperature calibration b. If the flow computer has transmitters for
a. Calibration of the temperature measurement measurement of differential pressure, static
on the flow computer is done with a single pressure and temperature the flow computer
temperature point at the pipeline operating interprets the transmitters scaled mA output
temperature. via its mA analog inputs. In this instance, if
b. A test thermowell is provided adjacent to the the calibration is unsuccessful, the individual
in service measuring RTD connected to the transmitters may need calibration and adjust-
flow computer or temperature transmitter. ment to remove errors. One last source of
Insert the calibrator probe into the test ther- errors to consider in this configuration, which,
mowell and allow time for the measurement is often overlooked is the mA input A/D of the
to reach a stable value. flow computer which typically has an offset
Note: Inserting the probe can be done prior to the pressure and gain adjustment.
calibrations if local conditions permit. That allows sufficient
time to reach stability.

Fluke. Keeping your world


up and running.®

Fluke Corporation
PO Box 9090, Everett, WA 98206 U.S.A.
Fluke Europe B.V.
PO Box 1186, 5602 BD
Eindhoven, The Netherlands
For more information call:
In the U.S.A. (800) 443-5853 or
Fax (425) 446-5116
In Europe/M-East/Africa +31 (0)40 267 5100 or
Fax +31 (0)40 267 5222
In Canada (800)-36-FLUKE or
Fax (905) 890-6866
From other countries +1 (425) 446-5500 or
Fax +1 (425) 446-5116
Web access: http://www.fluke.com
©2014 Fluke Corporation.
Specifications subject to change without notice.
Printed in U.S.A. 4/2014 6002276B_EN

Modification of this document is not permitted


without written permission from Fluke Corporation.

4 Fluke Corporation Calibrating gas custody transfer flow computers

You might also like