Jsa Steel Erection

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

HEALTH SAFETY AND ENVIRONMENTAL

King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

JOB SAFETY ANALYSIS


Job Safety Analysis Reference No: 22/JSA/038 Revision No: 00 Date: 11/June/2022

WORK TITLE: JSA for Steel Erection Plan

GENERAL JOB REQUIREMENT


1. Sino hydro Internal Permit to Work
2. Sino hydro HSE orientation for all employees
3. PPE as per Project Standard.
4. MDSD for Materials (cement and insulation materials)
5. Daily TBT before starting the activities.
6. Adequate supervision and HSSE coverage.
7. Strictly no smoking. Smoking only in designated area.
8. For Emergency – First Aiders at Site and Emergency Number Displayed.
9. Welfare - Drinking Water, Food & Rest & Smoking Shelter, and Porta Toilet & Transport available.
10. SAUDI ARAMCO REQUIREMENT/STANDARD AND PROCEDURES.
• GI 2.100 Work Permit System
• GI 7.025 Heavy Equipment Operator & Rigger testing/ Certification
• G1 7.026 Crane & Heavy Equipment Incident Reporting Procedure
• GI 7.028 Crane Lift Types and Procedure
• GI 7.029 Rigging Hardware and Requirements
• GI 2.714 Environnemental Protection Policy Implémentation
• GI 430.001 Waste Management
• GI 8.001 (Safety Requirement for Scaffold)
• Saudi Aramco Safety Handbook
SA Construction Safety Manual
Stop Work Trigger if defective lifting tools / equipment not inspected and adverse weather condition during lifting (Sand storm / Rain / Fog) and if
notice any unsafe act and unsafe condition at work site. Stop Work Trigger if any emergency such as fire, explosion, gas release, severe weather
condition, unsafe act and unsafe condition that leads to serious injuries, terrorist and bomb treat.
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

DESCRIPTION OF TASK: Erection of Structural Steel


Work Location: TCF, LAYDOWN AREA
SCOPE OF WORK:
This method statement defines the scope of work for erection of steel structure required the following equipment’s:
• Torque wrench.
• crane
• Man lift.
• Hammers and wrenches.
• Ladders, guy wires and tagline.
• Forklift.
• Truck
• Boom Truck
• Welding Machines
• Air Compressor
• Tower Lights
• Magnetic Drill
• Surveying Instrument.
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

SEQUENCE/ BASIC
Item POTENTIAL HAZARDS RESPONSIBILITY
STEPS HAZARD CONTROLS

• Conduct a joint inspection with SA Issuer. Foreman/Supervi


Obtain appropriate Miscommunication / • Highlight potential hazard. sor/
1
Work Permit Misunderstanding • Highlight precaution required. Site engineers

• All equipment and material shall be arranged to allow good access


ways all the time of performing the job.
• Tool Box Talk and pre-job meetings to be held to ensure all employees
are aware about the job and their roles.
Poor Working site preparation • Visually identify existing services in the area that may be affected
• No work before issuing the required permit(S) to work
• Protect the existing services that may be affected by means of
coverage and barricades.

• Prior to start the job all equipment and tools shall be inspected and
make sure that all equipment and tools are in good condition and
colour coded (if required).
Improper, damaged equipment
Work site • Make sure that all tools are the suitable tool for the job and the Foreman/Supervi
2 and tools
preparation correspondence employee is trained to use it. sor/
.
• make sure that all equipment is inspected by trained and certified Site engineers
inspectors

• Gas test to be done periodically per the working day.


Presence of toxic or flammable
• Tool box talk for all the employees about the hazards of the job
gases
• The chosen working site shall be shaded and ventilated.
• Ensure the supply of drinking water is enough.
Bad weather condition at the • Providing a good shaded ventilated resting area.
working site
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

• Emergency/ incident reporting and touching of any switches and


Lack of knowledge and skills alarms shall be included and discussed during TBT.
• All personnel shall have adequate training for their job.

• Use hand tools/equipment’s which inspected and color coded


• Make sure that all tools are the suitable tool for the job and the
correspondence employee is trained to use it.
Uninspected tools/equipment’s
• Make sure that all equipment is inspected by trained and certified
inspectors

Lack of knowledge in case of


• Emergency/ incident reporting shall be discussed during TBT.
emergency.
• Gas test shall be performed by authorized gas tester to ensure there is
no presence of toxic gases in the work area.
• Emergency/ incident, fire reporting and fire protection shall be Foreman/Supervi
discussed during TBT. sor/
Cutting & welding of Site engineers
• Adequate fire extinguisher available and provide for equipment in
steel structure (hot
3 ground level and in the work location
work) Presence of toxic and flammable
• Wear appropriate PPE
gases and Fire
• Ensure the hot work location is covered with fire blanket or fire proof
tarpaulin.
• Fire watch man available all the time
• Fire blanket to be laid on wooden plank and/or to protect
electrical/Instrument cable and/or sensible material around installed.

• Work area ground level shall be barricaded with signage to avoid entry
of unauthorized personnel.
Work area not barricaded • Standby man shall be in place

• Prior to start the job all equipment and tools shall be inspected and
make sure that all equipment and tools are in good condition and
colour coded (if required).
Defective welding machine and no
• Make sure that all tools are the suitable tool for the job and the
spark arrestor
correspondence employee is trained to use it.
• make sure that all equipment is inspected by trained and certified
inspectors
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

• Use slag containers with welders and grinders.


• Adequate fire extinguisher available and provide for equipment in
ground level and in the work location
• Wear appropriate PPE
Grinding slag not contained • Ensure the hot work location is covered with fire blanket or fire proof
tarpaulin.
• Fire watch man available all the time
• Fire blanket to be laid on wooden plank and/or to protect
electrical/Instrument cable and/or sensible material around installed.
• TBT about the hazard of noise.
Presence of high noise • Wear ear plugs.

• TBT about the hazard of inhalation of fumes.


Inhalation of fumes • The working site to be properly ventilated.
• Wear dust mask.
• Position the crane on well compacted and level ground.
• Keep sufficient distance from any obstacle structures to avoid Foreman/Supervi
4 Positioning of crane improper position of the crane unexpected occurrence. sor/
• barricade the lifting area and posting the warring signs. Site engineers

• Don’t bypass the crane safety program during lifting.


• Lift the load as per approved lifting plan.
Improper lifting practice
• The rigging of the load must be done only by qualified rigger.
• Suspend all lifting activities if wind speed exceeds the limit value.
• Riggers and Crane operator shall be competent.
• The outriggers of crane must be fully extended prior to the lift, and the
rubber tires must be off the ground
• Cranes shall have a valid Crane Safety inspection sticker. Foreman/Supervi
Loading and off- • When wind speed is above 32 km/h or according to crane sor/
5 manufacture, the work shall be stopped.
loading of materials Site engineers
Failure of Lifting Operation • lifting zone shall be barricaded by warning taps and warning signs to
prevent unauthorized personnel from entering lifting zone
• Slings and other rigging equipment must be constructed according to a
recognized standard. the load shall never be exceeding the Save
working load
• Safe working load and serial number shall be clearly marked on the
sling and the lifting gear, either by tagging or stamping
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

• Toolbox talk regarding work at heights to be conducted prior star of


work.
• No person shall be engaged in any work activity where that do not
Fall of person possess the technical knowledge and experience, unless they are
Foreman/Supervi
under direct supervision of authorized person or supervisor.
sor/
Fall of person • Working area to be checked for hazards before works commence. Site engineers
Waste materials to be removed from scaffolds immediately.
• Ensure that scaffold was inspected and tagged by Aramco approved
scaffolding supervisor / Inspector.
• Only work at heights trained personnel to do the job.
• To ensure that full body harness was inspected and color coded prior
start of activity. Foreman/Supervi
Injuries • To ensure that full body harness was 100% tie off on a proper sor/
Working at height anchorage point. Site engineers
6
(scaffolding) • Assign standby person to monitor under the work area.

• Ensure that scaffold was inspected and tagged by Aramco approved


scaffolding supervisor / Inspector
• Scaffold to be correct in size and height for the task, scaffold to be
positioned directly below work face. Foreman/Supervi
Collapse, scaffolding failure
• Area barricade and warning signage to be provided. sor/
• Keep the foundation of the scaffold away from any adjacent excavation Site engineers
by 1.5 of the depth.
• Check the ties point and the outriggers if needed as GI. (8.001) says.

• Barricade off work area and place warning signs.


• Clear all personnel from the area before raising, lowering or slewing
the Platform.
• If working under the overhead structures, bridge, in a tunnel etc, Foreman/Supervi
Overturn of the equipment or
7 Using man-lift remember the leverage factor and ensure ample clearance above the sor/
falling hazards
platform to cater for any unexpected amplified upward platform Site engineers
movement.
• Operator Awareness-never allows any part of body through, under or
between platform arms.
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

• Ensure load on platform is secure &evenly distributed, do not exceed


manufacture rated capacity.
• When elevated, drive only on ground capable or supporting its weight.
• Do not tie off the platform to any fixed structure or plant, or use the
platform as an anchor point.
• Never allow any person to work underneath any part of the boom.
• Avoid congested work areas.
• Never use ladder or boxes to gain extra height.
• Never stand on handrails to gain extra height.
• Clearly define the work area.
• Keep all personnel clear.
• Operator shall be trained as per Aramco requirement.

• Steel erection personnel performing activities on walking/working


surfaces with unprotected sides or edges more than 1.8 m (6 ft) above
a lower level shall be protected by a guardrail system, safety net
system, personal fall arrest system, etc.
Foreman/Supervi
• Fall protection equipment, including full-body harnesses, shall be
Fall from height sor/
inspected daily to ensure that it has not been damaged and is in good
Site engineers
condition.
• Materials, equipment and tools not in use while working at heights
shall be secured against displacement

• Crane operators shall be SA-certified and shall be responsible for Foreman/Supervi


crane operations. sor/
Assembly and
• Whenever there is any doubt as to safety of the lift, the crane operator Site engineers
8 erection of steel
shall, stop all hoisting activities., Refuse to handle unsafe loads
structure
• Materials being hoisted shall be rigged to prevent unintentional
displacement.
• Hooks with self-closing safety latches, or their equivalent, shall be
used to prevent components from slipping out of the hook.
Hoisting and Rigging failure
• Loads shall be lowered in a controlled and slow manner when the load
is near personnel.

• The total load shall not exceed the rated capacity of the hoisting and
rigging equipment.
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

• Structural stability shall be maintained at all times during the steel Foreman/Supervi
erection process. sor/
• The steel erector shall, at all times, be responsible for the adequacy Site engineers
and installation of any temporary bracing or guy cables required to
lack of steel structure stability
counteract loadings imposed during erection.
• Permanent floors shall be installed as the erection of structural
members progresses.

• Metal decking and grating shall be tightly installed and immediately Foreman/Supervi
secured (i.e., fastened) upon placement. sor/
Installation of Metal • A minimum of four fasteners per metal decking and grating panel shall Site engineers
9 Falling hazards
Decking and Grating be used.

• Provide temporary rest shelter. Foreman/Supervi


• Provide cold water or ice in the cooler jug. sor/
Working during • Provide hydration salts to site personnel. Site engineers
10 Heat exhaustion / Cramps
summer
• Rotation of personnel (rest – work rotation) must be established when
required.
• Ensure good housekeeping before, during and after the job completion.
• Regular disposal of waste, debris and scrap materials must carry out as
per WAST Management Plan.
• Trash bin for waste, used paper cups, scrap and debris must be
provided as per Waste Management Plan.
• Drinking containers must be in good sanitary, tightly capped and clearly
marked for use and cup dispensers must be provided.
• Working area must be cleaned and secured and left in a workable
Housekeeping Material scattered in the Foreman/Supervi
condition by other personnel at maintenance.
11 workplace health hazard slip sor/
trip fall • Work areas shall be kept clean and tidy at all times to prevent a built up Site engineers
of combustible materials and tripping hazards which could prove
dangerous in the event of an emergency.
• Pick up all objects, material, waste, etc. that should not be left on the
floor during and after activity.
• DO NOT leave the tools spread, organize and create proper and safe
places for tools
• Any defective equipment should be removed and quarantined.
HEALTH SAFETY AND ENVIRONMENTAL
King Salman Energy Park (SPARK-Dry Port) - Infrastructure and Maintenance Buildings
CONTRACT NO. 6600050462

Authority Name Signature Designation Date


HSE SUPERVISOR 11 June 2022
Prepared by: Joel Estiuta
ES&H MANAGER 11 June 2022
Reviewed by: Awad Al Saad
PROJECT MANAGER 11 June 2022
Approved by: Mr. Loae Hamedosh

You might also like