OUR REF: SECL/RWS/DOM/2023/14

TO: Date: 03th December, 2023

REGIONAL MANAGER

RURAL WATER SUPPLY AND SANITATION AGENCY

P.O.BOX 145

DODOMA

Dear Sir.

RE: CONSTRUCTION OF CHILANJILIZI PUMPIMG WATER SUPPLY PROJECT IN KONGWA


DISTRICT-DODOMA CONTRACT NO : AE-102/2021-2022/DOM/W/77

SUB: Third Gentle reminder: outstanding Interim Payment Certificate(IPC)

Dear sir

We trust this message finds you well, we are writing to bring to your attention the
outstanding Interim Payment Certificate (IPC) related to our on going project
CONSTRUCTION OF CHILANJILIZI PUMPIMG WATER SUPPLY PROJECT IN
KONGWA DISTRICT-DODOMA CONTRACT NO : AE-102/2021-2022/DOM/W/77
dated 5.february 2023. As of today (3 december 2023) we have not received the payment
for IPC (IPC No.1)

Timely payments are crucial to maintaining the smooth progression of our project and
ensuring that all rsources are adequately allocated. We understand that unforeseen
circumstances may sometimes cause delays,and we appreciate your attension to this
matter as this IPC is due for ten (10) months now.

Kindly review and process the paymentat at your earliest convenience. If there are any
concerns or issues regarding the IPC,please do not hesitateto reach out to us. We are
commited to addressing any queries promptly to ensure a seamless resolution.

Thank you for your understanding and cooperation. We value our partnership and look
forward tocontinuing our collaborative efforts on this project
Yours Sincerely,

SKYLINE ENGINEERING CONTRACTORS LIMITED

ENG. ALLY M MAKULA

MANAGING DIRECTOR