Maize Godown Planning+ Schedule

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

ID Task Task Name Duration Start Finish Predecessors Resource Names December 2023 January 2024 February 2024

Mode 212427300306091215182124273002050811141720232629010407101316192225
1 Maize Godown Project 28 days Fri 01-12-23 Thu 28-12-23
2 Material Shifting From 1 day Fri 01-12-23 Fri 01-12-23
Godown

3 Stone Dust Filling + 2 days Fri 01-12-23 Sat 02-12-23 Stone Dust[5 Stone Dust[5 Hyva],Jcb
Compaction Hyva],Jcb

4 Dressing + Steel Binding 4 days Sun 03-12-23 Wed 06-12-23 3 TMT 10mm[3 MT] TMT 10mm[3 MT]

5 Concreting throughout Tie 6 days Tue 05-12-23 Sun 10-12-23 4FS-2 days Cement[500 Cement[500 Bags],Sand[2 Hyva],Stone Chips[4 Hyva]
Beam Bags],Sand[2
Hyva],Stone
6 Brickwork upto purling (3') 5 days Wed 06-12-23 Mon 11-12-23 5FS-4 days Bricks[14,000 Pcs] Bricks[14,000 Pcs]

7 Plaster Internal+External 6 days Fri 08-12-23 Wed 13-12-23 6FS-5 days


8 Sheet Installation Work 10 days Sat 09-12-23 Mon 18-12-23 7FS-5 days Bheem Team Bheem Team

10 Elevator & Conveyor Work


11 Soil Cutting For Conveyor 2 days Thu 30-11-23 Fri 01-12-23 Jcb Jcb

12 Dressing + Brick Soling 2 days Sat 02-12-23 Sun 03-12-23 11 Bricks[500 Pcs] Bricks[500 Pcs]

13 Reinforcement Work 3 days Mon 04-12-23 Wed 06-12-23 12 TMT 10mm[2 MT] TMT 10mm[2 MT]

14 Base Concreting 3 days Wed 06-12-23 Fri 08-12-23 13FS-1 day Cement[500
Cement[500 Bags],Sand[2 Hyva],Stone Chips[3Bags],Sand[2
Hyva] Hyva],Stone Chips[3 Hyva]

15 Brick Work 6 days Thu 07-12-23 Tue 12-12-23 14FS-2 days Bricks[3,000 Pcs] Bricks[3,000 Pcs]

16 Shuttering Work For RCC 10 days Sun 10-12-23 Tue 19-12-23 15FS-3 days
Wall

17 RCC Wall Concreting 10 days Tue 12-12-23 Thu 21-12-23 16FS-8 days Cement[500
Cement[500 Bags],Sand[2 Hyva],Stone Chips[3 Hyva] Bags],Sand[2 Hyva],Stone Chips[3 Hyva]
18

19 Overall Floor Concreting


20 Dust Filling + Dressing 3 days Wed 20-12-23 Fri 22-12-23 Jcb,Stone Dust[5 Hyva] Jcb,Stone Dust[5 Hyva]

21 Reinforcement Work 3 days Sat 23-12-23 Mon 25-12-23 20 TMT 10mm[5.4 MT] TMT 10mm[5.4 MT]

22 Floor Concreting 5 days Sun 24-12-23 Thu 28-12-23 21FS-2 days Cement[1,000 Bags],Sand[4 Hyva],Stone Chips[6 Hyva]
Cement[1,000 Bags],Sand[4 Hyva],Stone Chips[6 Hyva]

Task External Tasks Manual Task Finish-only


Split External Milestone Duration-only Deadline
Project: Maize Godown Planning
Milestone Inactive Task Manual Summary Rollup Progress
Date: Thu 30-11-23
Summary Inactive Milestone Manual Summary
Project Summary Inactive Summary Start-only

Page 1