UPS5000 Commissioning and Acceptance Report

Project Name Unicomm-KLCC UPS (HW)


Contract No. 0Y04582300140Z
Delivery Organization Malaysia Rep Office
Commissioning Engineer Muhammad Syukri Bin Nordin_m00866450
Commissioning Date 2024-01-06 16:51:51

Commissioning Summary:

Commissioning and acceptance items: total: 87; normal: 87; abnormal: 0


1. Basic equipment information: inspection item: 5. For details, see the following.
2. Hardware installation check: inspection item: 43. For details, see the following.
3. Parameter configuration check: inspection item: 24. For details, see the following.
4. Function test check: inspection item: 8. For details, see the following.
5. Running Parameters: inspection item: 1. For details, see the following.
6. Fire Fighting and Emergency Response: 2. For details, see the following.
7. Maintenance Suggestions / Commissioning conclusion: 4

1. Device Information
Category No. Name Information Record
1.1 Device model UPS5000E
1.2 Device SN N022B1047198
Device
1.3 UPS rack capacity (kVA) 120
information
1.4 Capacity of a single module (kVA) Others
1.5 Cabling mode Top cabling

2. Hardware Installation Check


Category No. Check Item Check Result
(Two power sources) Ensure that the copper bars of the same
2.1 N/A
power source for mains and bypass inputs have been removed.
Ensure that the UPS power and ground cables are tightened
2.2 with the specified torque, and signal cables are securely Pass
connected.
Ensure that the cable sequence of the UPS power cable is
2.3 checked one by one and matches the cable sequence of the Pass
upstream and downstream switches.
Ensure that the UPS mains input, bypass input/output, and
Installation 2.4 Pass
battery cables are not short-circuited.
check

2.5 Whether the PDC is provided by Huawei. No

Ensure that the PDC is free of metal scraps and dust and is
2.6
sealed in a standard manner.

2.7 Huawei PDC internal sealing video.

2.8 UPS mains input switch capacity (A) 125

UPS mains 2.9 Cable for each phase (L1, L2, and L3) of mains input (mm2) 25
input 2.10 Mains input N cable (mm2) Same as the live wire

2.11 Mains input PE cable (mm2) Half of the live wire


UPS bypass Cable diameter same as that
2.12 UPS bypass input
input of the mains
2.13 UPS output switch capacity (A) 125

2.14 Cable for each phase of output (U/V/W) (mm2) 25


UPS output

Page 1 of 13
UPS output
2.15 Output N cable (mm2) Same as the live wire

2.16 Output PE cable (mm2) Half of the live wire

2.17 UPS battery switch capacity (A) 100

Battery switch 2.18 Positive battery cable (mm2) 25


and cable 2.19 Negative battery cable (mm2) 25

2.20 Battery N cable (mm2) 25

2.21 Temperature inside the equipment room (0–40°C) 24

2.22 Humidity inside the equipment room (0–95% RH) 60


Check whether the air conditioners in the equipment room are
2.23 Yes
on.
2.24 There is no condensation on the device surface. Yes
There is no air conditioner or fresh air system vent or water pipe
2.25 Yes
on
Thethe firetop of the device.
extinguishing system has been installed and enabled in
the equipment room, or temporary fire extinguishing facilities
2.26 Yes
have been configured according to the construction
specifications.
Metal scraps, foreign objects, and dust have been removed from
2.27 Yes
the cabinet.
Application 2.28 Check whether the UPS is installed in the smart module. No
environment Check whether holes are drilled on the top of the UPS (affecting
2.29 the load bearing capacity of the cabinet and metal debris No
Iintrusion)
have informed the customer of the potential risks caused by
2.30 drilling holes on the top of the cabinet and confirmed that the
cleaning is complete

2.31 Clean the cabinet and check pictures/videos

2.32 Equipment front

2.33 Equipment rear

2.34 Equipment top

Page 2 of 13
2.35 Ambient environment

2.36 Mains input copper bar

2.37 Bypass input copper bar

Installation
photo

Photo/Video of the environment inside the copper bar and wiring


2.38 compartment in the scenario where the mains and sides share
the same source

2.39 Output copper bar

2.40 Battery copper bar

2.41 Battery switch box

Page 3 of 13
2.42 Power module surface

2.43 Cable inlet and outlet sealing

3. Parameter Configuration
Category No. Parameter Configuration
3.1.1 Single UPS/Parallel UPSs Single
Basic number of racks connected in parallel (not involved in the
3.1.2 1
single
Number UPS scenario) racks connected in parallel (not involved in
of redundant
3.1.3
System settings the single UPS scenario)
3.1.4 Working mode Normal mode
3.1.5 BSC mode Non-BSC mode
3.1.6 Altitude (m) (derated when the altitude exceeds 1000 m) ≤ 1000
3.2.1 Battery string sharing Disable
3.2.2 Battery type Lead-acid battery
3.2.3 Single battery voltage (lead-acid battery) (V) 12
Battery settings 3.2.4 Single battery capacity (lead-acid battery) (Ah) 40
3.2.5 Battery quantity in a string (lead-acid battery) 40
3.2.6 Battery string quantity (lead-acid battery) 1
3.2.7 Charging current limiting coefficient (C)
3.3.1 MUE05A connection Enable
3.3.2 Battery ground fault [BTG] Disable
3.3.3 Genset connection [GEN] Disable
3.3.4 BCB connection [OL] (If the battery switch box or BIB board is Disable
3.3.5 installed, set this
Battery circuit parameter
breaker statusto[STA]
Enable.)
(If the battery switch box or Disable
Dry contact 3.3.6 BIB
EPOboard is installed,
detection [EPO] set this parameter to Enable.) Disable
settings
3.3.7 PDF output switch [OUT] Disable
3.3.8 PDF maintenance switch [MT] Disable
3.3.9 PDF bypass input switch [BP] Disable
3.3.10 SPD status [SPD] Disable
3.3.11 MUE06A connection Disable

4. Function Test
Category No. Test Item Test Result
4.1.1 Single inverter startup Pass
4.1.2 Mains inverter-to-battery mode Pass
Single UPS 4.1.3 Battery-to-mains inverter mode Pass
functions 4.1.4 Single inverter shutdown to bypass mode Pass
4.1.5 Maintenance bypass Pass
4.1.6 Lead-acid battery switch tripping Pass
Parallel UPS 4.2.1 Parallel inverter startup N/A
functions 4.2.2 Parallel inverter shutdown to bypass mode N/A

Page 4 of 13
5. Running Parameters
Category No. Parameter Parameter Record (Photo)

Running
5.1 Running software version
parameter

6. Fire Fighting and Emergency Response


Category No. Test Item Test Result

Fire Fighting and 6.1 UPS equipment room fire extinguishing system
Emergency
Response

6.2 UPS remote EPO switch N/A

7. Maintenance Suggestions

Maintenance 1. Ensure that the equipment room door is normally closed, the air conditioners keep running properly, and the
suggestions equipment room temperature is within a required range.
2. Keep the equipment room clean and regularly clean or replace the equipment dust filter.
.

8. Commissioning Conclusion
Commissioning
Pass
conclusion

(If the check is not


passed, state the
reasons.)

Customer
signature

Remarks

Welcome to Huawei Digital Power service hotline. If you have any questions or need help, please contact us via the
following ways:
(1) Service hotline: 400-822-99992
(2) Inquiry email: dpcaisd@huawei.com
(3) Search for and follow the Huawei Digital Power Service official account in WeChat, and leave a message.
You can also use the intelligent Q&A to search for what you want to know. Please stay tuned for future updates.

Page 5 of 13
UPS5000 Commissioning
and Acceptance Report

Project Name : ${projectName}

${contract}
Contract No. :
Delivery

Organization : ${buOrgName}

Commissioning

Engineer : ${docCreateName}
Commissioning

Date : ${docCreateDate}
Commissioning and acceptance items: total: 87; normal: 87; abnormal: 0

Basi c eq uip men t H ar dwa re in sta ll at io n


in formation c he ck

inspection item: 5. For inspection item: 43. For


details, see the following. details, see the following.

Parameter configu r at io n F un ct io n t e st
check c he ck

inspection item: 24. For inspection item: 8. For


details, see the following. details, see the following.

Run nin g Parame t er s: F ire F ig ht ing a nd


Eme r g en cy
Re spo ns e
inspection item: 1. For
details, see the following. inspection item: 2. For
details, see the following.

Main tenance Su gg e st io ns /
Commission ing Co nc lusi on

For details, see the following.