PSA Plant Building Construction Work Schedule

Cox's Bazar Unit 10 Days plan


SL Activity Day ### ### ### ### ### ### ### ### ### ###

Working on
Given Layout in
1 Brick work 4
one side
remaining brick
layout

2
Gypsum board and aluminum( door,window) 4 Not started yet Planned
fitting

3
External and internal wiring and lighting & 4 Completed
electrical work

4 Internal Paint 3

5 Epoxy Coating 3 Start

Material

Gypsum due
Electrical due MDB due
Grill material Due
Hand Over Date 28Th Paint Due
Epoxy 25/12/23 due

Manpower Now Need Total Proposed


Gypsum
Electrical
Grill material
Paint
Epoxy
28 December 2023 ### ###

start complete

planned complete