Professional Documents
Culture Documents
1lessons Learned Database - v2.0
1lessons Learned Database - v2.0
Lessons learned collected by Capital Effectiveness initiative – Technical Affairs and Projects Sector
The Lessons Learned Database is a proprietary tool developed by the Saline Water Conversion Corporation (SWCC) to
capture all the situations that have impacted SWCC's project performance (whether positively or negatively).
Overview This tool should be used by all project teams to:
1) Summarize key insights related to their projects, and
2) Leverage Lessons Learned from current and/or completed projects to maximize project value
The sheet "Categories" includes the categories to which Lessons Learned belong to:
1) Capital Planning
2) Project Planning
3) Procurement & Contracting
4) Engineering
5) Construction
Categories 6) Testing & Commissioning
7) Handover & Closeout
8) Project Controls
9) Quality & HSSE
10) Team Effectiveness and Organization
11) Other
The categories, as well as sub-categories defined, can be modified and updated by SWCC when deemed necessary
The sheet "Lessons Learned Log" is a living document capturing SWCC's Lessons Learned from its capital projects.
For each new lesson learned, the Lessons Learned Responsible enters a new row, and fills the required data based on the
project's information.
The key inputs are described below:
1) Project Type defines the nature of the project: All (applicable for all types), Desalination, Pipeline, Reservoir, Housing, Other
2) Project Stage shows the current stage of the Stage Gate process (in which lessons are captured): Multiple (applicable
across several stages), Select (Initial Planning), Define (Detailed planning and tender for execution), Execute (incl. testing and
commissioning), Handover & Closeout
3) Category is the group to which the lesson learned belongs to (defined in the sheet "Categories")
Lessons Learned Log
4) Sub-category is the sub-group to which the lesson learned belongs to (defined in the sheet "Categories")
5) Description of the Situation should be written in a crisp and concise manner with sufficient information to enable a new
reader to understand the lesson
6) Impact of the Situation refers to either negative effect or an opportunity and includes Cost Impact, Schedule Impact, Team
Impact etc. as appropriate
7) Lessons Learned provides guidance to the reader on the recommended actions to apply and to avoid in similar
circumstances
8) Recommendations beyond Project's Scope presents the actions to be taken to address the lessons learned that are not
specific to the project (e.g. change procedure, change specifications)
Document ID No:
Page: 1 of 1
Lessons Learned Categories & Sub-Categories
Rev. No.: 0
Date of Issue:
Categories 01. Capital Planning 02. Project Planning 03. Procurement and Contracting 04. Engineering 05. Construction 06. Testing and Commissioning 07. Handover and Closeout 08. Project Controls 09. Quality and HSSE 10. Team Effectiveness and Organization 11. Other
0101. Five-year Capital Planning 0201. Stakeholder Engagement 0301. Contracting Strategy 0401. Cost & Budget Planning 0501. Contractor Management - Construction
0601. Testing 0701. Handover 0801. Reporting Management 0901. Quality Assurance & Quality Control 1001. Teamwork / Collaboration 1101. Equipment & Spare Parts
0202. Permitting Plan 0302. Prequalification of Tenderers 0402. Design Schedule 0502. Contractor Management - PMC 0602. Commissioning 0702. Closeout 0802. Risk Management 0902. Inspections 1002. Team Communication
0203. Project Scheduling 0303. Preparation and Issuance of Tender Documents
0403. Contractor Management - Engineering
0503. Resource Management 0803. Management of Change 0903. Health Requirements 1003. Technical Experience and Capabilities
0204. Cost & Budget Estimation 0304. Tender Evaluation 0404. Standards & Specifications 0504. Permits Issuance 0804. Cost & Budget Control 0904. Safety Requirements 1004. Management support
0305. Award and Contract Negotiation 0405. Value Improvement 0505. Technical Issues 0805. Project Schedule Control 0905. Security Requirements 1005. Decision making
0306. Vendor Management 0406. Design Review 0806. Document Management 0906. Environmental Requirements 1006. Team Satisfaction
0307. Defects & Warranties 0407. User Requirements 0807. Management of Claims 0907. HSSE Orientation & Training Plan 1007. Training
Sub-categories
Document ID No:
Prepared by:
Lessons Learned Log
Rev. No.: 0
Date of Issue: 22-Feb-18
System/Equipment associated
ID Date Entered By Project Name Project Type Project Stage Category Sub-Category with the LL Description of the Situation Impact of the Situation Lessons Learned Applicability
(if applicable)
1. Identify potential delays resulting from long approval cycles
Departments/Personnel are not provided with
Team Effectiveness and 2. Communicate with relevant personnel early on to either
LL_0_1005_00001 15-Feb-18 Capital Effectiveness team NA All Multiple Decision making - sufficient delegated authority to manage their Unnecessary approval cycles Future Projects Only
Organization support in accelerating approvals or delegate authorities to the
project effectively
project level
Team Effectiveness & Waste of time and effort to onboard new 1. Maintain continuity of personnel throughout project to
LL_0_1001_00003 15-Feb-18 Capital Effectiveness team NA All Multiple Teamwork / Collaboration - Project team is changed during project phases Future Projects Only
Organization people and transfer knowledge to them control cost and reduce interfaces
Execute (incl. Project schedule delayed and potentially 1. Ensure proper transparency of controls, clear accountability
LL_0_0805_00026 15-Feb-18 Capital Effectiveness team NA All testing and Project Controls Project Schedule Control - Poor scheduling controls budget exceeded and/or quality and a meaningful audit trail of information to validate that the Future Projects Only
commissionning) unsatisfactory reported level of progress reflect what's happening on site
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 4
1. Ensure that contractor is eligible to lead the construction
Execute (incl.
Preparation and Issuance of Tender Contractor couldn't fulfill his obligations as Ineffective project implementation phase. If pre-qualification criteria are not solid enough, include
LL_0_0303_00031 15-Feb-18 Capital Effectiveness team NA All testing and Procurement and Contracting - Future Projects Only
Documents described in the contract jeopardizing quality and plan specific criteria in the tender that increase the likelihood of
commissionning)
project's success
Execute (incl. Each contractor presents a monthly report in his Difficulty/Prolonged time in
1. Prepare a standardized format for contractor's monthly
LL_0_0801_00032 15-Feb-18 Capital Effectiveness team NA All testing and Project Controls Reporting Management - own format, with structure and content showing understanding and analyzing monthly Future Projects Only
reports with similar structure across projects of the same type
commissionning) significant differences reports
Execute (incl. Schedules are not standardized, with
Inability to track project progress 1. Prepare a standardized format for contractor's schedule
LL_0_0801_00033 15-Feb-18 Capital Effectiveness team NA All testing and Project Controls Reporting Management - contractors submitting different types of forms, Future Projects Only
accurately with similar structure across projects of the same type
commissionning) and varying level of detail
1. Develop robust documentation that is relatively
Weak documentation from the Supervision High dependency on supervision
LL_0_0806_00034 15-Feb-18 Capital Effectiveness team NA All Multiple Project Controls Document Management - independent from consultant and contractor, with all internal Future Projects Only
Committee consultant
letters archived and maintained
Define (Detailed
planning and Project specifications are modified in many Waste of time and effort during 1. Adopt standard specifications to be applied across projects
LL_0_0404_00035 15-Feb-18 Capital Effectiveness team NA All Engineering Standards & Specifications - Future Projects Only
tender for projects tendering process of the same type
execution)
Execute (incl.
Inspections are not always documented with Evidence of effective quality assurance is
LL_0_0902_00036 15-Feb-18 Capital Effectiveness team NA All testing and Quality and HSSE Inspections - 1. Document all inspections with pictures Future Projects Only
pictures missing
commissionning)
Handover & Spare parts are not always updated when Difficulty in matching spare parts to 1. Update list of spare parts if new/renovated equipment is
LL_0_1101_00037 15-Feb-18 Capital Effectiveness team NA All Other Equipment & Spare Parts - Future Projects Only
Closeout equipment is changed/renovated existing equipment utilized (to be handled by O&M and Procurement)
Define (Detailed 1. Align with PED on all project requirements, including a
Many rounds of discussions are
planning and Preparation and Issuance of Tender Preliminary Scope of Work (SoW) is not clear detailed shopping list
LL_0_0303_00038 15-Feb-18 Capital Effectiveness team NA All Procurement and Contracting - scheduled with tenderers to clarify the Future Projects Only
tender for Documents and comprehensive 2. Schedule workshops with tenderers to provide guidelines
SoW
execution) and align on key technical requirements
Ranges of the budget could be revealed
Select (Initial Budget is communicated to personnel that do 1. Apply strict measures on Supervision Consultant and
LL_0_0401_00039 15-Feb-18 Capital Effectiveness team NA All Engineering Cost & Budget Planning - to tenderers, which might increase their Future Projects Only
planning) not contribute to budget planning internal employees to ensure confidentiality
financial offers
1. Maintain soft copies of all documentation
Project overall progress is delayed and
LL_0_0806_00040 15-Feb-18 Capital Effectiveness team NA All Multiple Project Controls Document Management - Incomplete documentation recorded 2. Define an archiving methodology that provides easy access Future Projects Only
quality could be jeopardized
to documents
Select (Initial O&M equipment installation might face 1. Communicate with O&M to take their view on project
LL_0_0407_00041 15-Feb-18 Capital Effectiveness team NA All Engineering User Requirements - Project location is not easily accessible Future Projects Only
planning) serious hurdles location into consideration, before taking the final decision
Lack of understanding of project 1. Share SoW and all necessary documents with all the
Select (Initial SoW is not communicated properly to all project requirements leads to reduced project stakeholders that will have a role in the project
LL_0_0201_00042 15-Feb-18 Capital Effectiveness team NA All Project Planning Stakeholder Engagement - Future Projects Only
planning) stakeholders performance and inability to monitor 2. Communicate regularly with stakeholders to ensure a
activities appropriately thorough understanding of SoW
Execute (incl. 1. Project schedule follows the reviewed and approved SoW
Project bottlenecks resulting from dependency Project budget is exceeded (e.g. re-
LL_0_0401_00043 15-Feb-18 Capital Effectiveness team NA All testing and Engineering Cost & Budget Planning - 2. Ensure that activities are planned in a way to reduce inter- Future Projects Only
among activities mobilization)
commissionning) dependency and minimize bottlenecks
Define (Detailed
Delay in receiving and evaluating bids, 1. Schedule 1 full day including a site visit and meetings with
planning and Preparation and Issuance of Tender Contractor requests multiple extensions,
LL_0_0303_00044 15-Feb-18 Capital Effectiveness team NA All Procurement and Contracting - resulting in delay in project awarding key personnel. Contractor shall prepare all the questions and Future Projects Only
tender for Documents meetings and site-visits
and initiation clarifications needed
execution)
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 5
Ras Al Khair Power and Ras Al Khair Power It would save a lot of time and money if some items are not
Select (Initial Many items have detailed specifications, but
LL_1_0404_00062 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Engineering Standards & Specifications - Waste of time and money described very detailed and left to the EPC contractors Future Projects Only
planning) others again very coarse
Team Plant - Phase 1 standard
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The EPC contractor of the P-Package has split
Contractor Management - The EPC contractor should limit\ the split of engineering and
LL_1_0501_00064 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction - the whole contract in packages but failed to Future Projects Only
Construction vendor packages and assures a plant integration
Team Plant - Phase 1 commissionning) have a sufficient plant integration
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The Project Quality of an EPC contractor and main vendors
P-Package EPC contractor has large
LL_1_0901_00066 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Quality and HSSE Quality Assurance & Quality Control - should be done by a third party, who can baseline the Future Projects Only
deficiencies in quality standards and experience
Team Plant - Phase 1 commissionning) experience and focus on quality against industry standards
Define (Detailed
Ras Al Khair Power and Ras Al Khair Power
planning and The selection criteria should include quality, scope and risk
LL_1_0304_00067 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Procurement and Contracting Tender Evaluation - P-Package EPC contractor is selected on price Future Projects Only
tender for assessment
Team Plant - Phase 1
execution)
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The 380 kV substation shall be ordered before or together
The critical path is influenced by the 380 kV
LL_1_0505_00068 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - with the power plant package, and should be part of the power Future Projects Only
substation
Team Plant - Phase 1 commissionning) package
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The contractor of the P-package was always EPC contractor shall present his activity-based planning,
Setting unrealistic milestones is
LL_1_0805_00071 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Project Controls Project Schedule Control - pushed to agree on milestones, with a top-down which shall be analyzed and optimized to agree on realistic Future Projects Only
counterproductive
Team Plant - Phase 1 commissionning) planning milestones
Ras Al Khair Power and Ras Al Khair Power Execute (incl. A senior QA/QC manager shall be appointed to be
Contractor Management - QA/QC is in the responsibility of contractors, but
LL_1_0501_00073 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction - responsible for the procedures from day 1, as this impacts the Future Projects Only
Construction is not being considered sufficiently
Team Plant - Phase 1 commissionning) entire progress and quality of the project
Define (Detailed
Ras Al Khair Power and Ras Al Khair Power Reference is made to Article 9 of the law for This reference article is out of date and does not align with
planning and Preparation and Issuance of Tender
LL_1_0303_00074 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Procurement and Contracting - Securing the Purchases of the Government and Royal Decree No. M/58 of the MoFA decision No. 362 as Future Projects Only
tender for Documents
Team Plant - Phase 1 the Implementation of its Projects and Works stated in the contract. Details should be updated
execution)
Ras Al Khair Power and Ras Al Khair Power Execute (incl. P-Package contractor never had a reliable Before starting the engineering, the contractor shall submit a
LL_1_0806_00075 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Project Controls Document Management - Master Document List (MDL) because he MDL for both the basic and detailed design. The quality of the Future Projects Only
Team Plant - Phase 1 commissionning) divides the engineering in packages MDL should improve in the course of the project
P-Package contractor split the whole The contractor should propose in the tender phase the
Ras Al Khair Power and Ras Al Khair Power engineering up in packages resulting in scope activities to execute the engineering, responsibilities and
Select (Initial
LL_1_0301_00076 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Procurement and Contracting Contracting Strategy - gaps and interface issues within the scope of allocation of work. Furthermore a clear Work Breakdown Future Projects Only
planning)
Team Plant - Phase 1 the P-Package. He failed to show a Work Structure shall be shown to specify the engineering lots and to
Breakdown Structure identify possible scope gaps
P-Package contractor never followed standard
engineering procedures. Basic design was not
Before passing Gate Reviews, the contractor is not allowed to
Ras Al Khair Power and Ras Al Khair Power completed before starting detailed design.
Select (Initial go the next stage. These gate reviews could be:
LL_1_0406_00077 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Engineering Design Review - Procurement was done before the basic design Future Projects Only
planning) These Reviews would result in actions, which could be tracked
Team Plant - Phase 1 freeze and long lead items were ordered before
in the next phase.
the concepts were frozen. Therefore reverse
engineering was required.
A high number of DRM’s and Project Interface Meetings (if
Ras Al Khair Power and Ras Al Khair Power Execute (incl. No Design Review Meetings (DRM) were
Contractor Management - more than one EPC contractor) are required and need to be
LL_1_0501_00078 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction - scheduled in the contract; only Engineering Future Projects Only
Construction planned in during the start-up of the project (1st 12 to 18
Team Plant - Phase 1 commissionning) Management Meetings (EMM)
months)
Define (Detailed
Ras Al Khair Power and Ras Al Khair Power
planning and Preparation and Issuance of Tender P-Package contractor has no experienced The integration of the engineering management in the overall
LL_1_0303_00079 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Procurement and Contracting - Future Projects Only
tender for Documents engineering management structure shall be shown in the tender phase.
Team Plant - Phase 1
execution)
The engineering quality shall be in the focus during the
Ras Al Khair Power and Ras Al Khair Power Execute (incl. P-Package contractor submits engineering with prequalification phase, since this can make and break a
Contractor Management -
LL_1_0501_00080 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction - a very low quality impacting the schedule and project. If there is only a limited confidence in the EPC Future Projects Only
Construction
Team Plant - Phase 1 commissionning) construction contractor to deliver high quality engineering, he should be
forced to use an engineer of record
Ras Al Khair Power and Ras Al Khair Power Execute (incl. A joined documentation management system between the
The contractor used to send all design
LL_1_0806_00081 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Project Controls Document Management - contractor, owner and consultant is improving the document Future Projects Only
documents and letters by emails
Team Plant - Phase 1 commissionning) flow
P-Package split the whole manufacturing up in The integration of the vendor packages shall be assured. The
Ras Al Khair Power and Ras Al Khair Power Execute (incl.
small packages, resulting in scope gaps and Project Quality of the main vendors shall be done by a 3d
LL_1_0306_00082 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Procurement and Contracting Vendor Management - Future Projects Only
interface issues in the scope of the P-Package. party. Furthermore, a clear work breakdown schedule shall be
Team Plant - Phase 1 commissionning)
Also no Work Breakdown Schedule is available presented after the concept review phase
Ras Al Khair Power and Ras Al Khair Power Execute (incl. P-Package contractor procured the majority of
The contractor should only procure the components only after
LL_1_0306_00083 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Procurement and Contracting Vendor Management - the components before the basic engineering Future Projects Only
the basic design has been completed.
Team Plant - Phase 1 commissionning) has been completed
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Factory Acceptance Tests (FAT) of a number of FAT shall be done after the detailed engineering has been
LL_1_0901_00085 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Quality and HSSE Quality Assurance & Quality Control - systems for the P-Package have been done completed. FAT of the main equipment shall be supervised by Future Projects Only
Team Plant - Phase 1 commissionning) before the detailed engineering is completed. the O/OE to make sure the I&T plans are implemented
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Construction has been stopped on site on a
The cash flow of the contractor should be robust to allow
LL_1_0306_00086 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Procurement and Contracting Vendor Management - number of occasions due to non-payments to Future Projects Only
payments to vendors
Team Plant - Phase 1 commissionning) vendors
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The construction of the P-package is more The construction schedule should reflect the critical path and
LL_1_0805_00087 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Project Controls Project Schedule Control - focused on showing progress and milestone the resources shall be allocated to the construction Future Projects Only
Team Plant - Phase 1 commissionning) payments than the critical path activities/areas impacting the critical path
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 6
Ras Al Khair Power and Ras Al Khair Power
Select (Initial HAZOP study and Analysis Report is not This important part of the contract is to be completed along
LL_1_0904_00090 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Quality and HSSE Safety Requirements - Future Projects Only
planning) completed with basic system design within one year of contract award
Team Plant - Phase 1
Ras Al Khair Power and Ras Al Khair Power It would be ideal to award the EPC contract for both Power
Select (Initial 2 different EPC Contracts were assigned for
LL_1_0305_00094 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant Procurement and Contracting Award and Contract Negotiation - and Desalination to a single EPC contractor/consortium to Future Projects Only
planning) Power and Desalination Packages
Team Plant - Phase 1 avoid delays and confusion due to interface issues.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Contract does not define the number of power Clear definition shall be available in the contract regarding the
LL_1_0505_00098 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - blocks or the number of evaporators to be size and number of Power Blocks and Number of MSF Units Future Projects Only
Team Plant - Phase 1 commissionning) supplied clearly. based on availability in the market.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Design of all major equipment for the Project shall be verified
Issues with equipment (e.g. Brine Recycle
LL_1_0505_00102 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - thoroughly by the Consultant or third Party. All equipment Future Projects Only
Pumps, Energy Recovery Device)
Team Plant - Phase 1 commissionning) shall have proven record of reliability.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. In the critical construction phase the number of experienced
The number of inspectors and engineers is not
LL_1_0902_00105 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Quality and HSSE Inspections - inspectors and engineers shall be adequate to deal with the Future Projects Only
sufficient for the critical stages of the project
Team Plant - Phase 1 commissionning) construction inspections and as built drawings
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The technical committee is very lean and lacks The number of engineers of the owner shall be increased and
Team Effectiveness and Technical Experience and
LL_1_1003_00106 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and - experience in construction. They mainly come shall have the required experience in similar construction Future Projects Only
Organization Capabilities
Team Plant - Phase 1 commissionning) from the O&M field projects.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Fencing and gate shall be established at the beginning of the
Fence and security of the site was very late and
LL_1_0904_00107 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Quality and HSSE Safety Requirements - project. An electronic access system shall be established with Future Projects Only
security is still not fully automated
Team Plant - Phase 1 commissionning) a security team, which is actually functioning
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Contractor should not be allowed to ship the material without
Contractor Management - Major costly equipment are imported and
LL_1_0501_00109 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction - FAT and shipment clearance or ahead of scheduled erection Future Projects Only
Construction delivered to site early in the project.
Team Plant - Phase 1 commissionning) date.
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 7
No detail approached on Smoke Control
System, its operation and interface requirement
with the Fire & Gas Detection and Alarm
Ras Al Khair Power and Ras Al Khair Power Execute (incl.
System. No Firefighters Smoke Control Station Future buildings HVAC design needs to comply as per IBC,
LL_1_0904_00118 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Quality and HSSE Safety Requirements - Future Projects Only
detail in specification in all buildings where as NFPA101, NFPA90A and NFPA92A and NFPA72.
Team Plant - Phase 1 commissionning)
automatic smoke venting requirement indicated
in specification. Safe means to manual &
override operation is not considered
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Steel structure coating: Galvanization or
LL_1_0505_00140 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - painting; Problem: Paint DFT is very thick and Either use galvanization or paint Future Projects Only
Team Plant - Phase 1 commissionning) will peel off
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Seismic Importance Factor: Occupancy As per latest code (ASCE-2010) The Importance Factor for
LL_1_0505_00143 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - Category 3, Importance Factor 1 based on UBC Power Plant is 1.25. This IF is to be applied for all Power Future Projects Only
Team Plant - Phase 1 commissionning) (i.e. IF=1.00) Plant Buildings
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 8
Ras Al Khair Power and Ras Al Khair Power Execute (incl.
Piping material for Fire Fighting is Carbon steel Piping material for the fire Fighting ring main shall be GRE
LL_1_0505_00145 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - Future Projects Only
with Galvanizing and the piping can be underground to minimize interference.
Team Plant - Phase 1 commissionning)
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Local direct expansion type air conditioning can be installed at
Center Chilled Water Facility (HVAC building) is
LL_1_0505_00149 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - each building in order to optimize the facility for air Future Projects Only
in Power Package Scope
Team Plant - Phase 1 commissionning) conditioning.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Temperature does not affect the operation of equipment
Train Section of the RO Building shall be air-
LL_1_0505_00150 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - (membrane) installed in RO Building, so air-conditioning is not Future Projects Only
conditioned
Team Plant - Phase 1 commissionning) necessary. Ventilation system is sufficient
Ras Al Khair Power and Ras Al Khair Power Execute (incl. In order to eliminate flooding risk and provide ease of
The discharge headers for seawater supply
LL_1_0505_00151 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - maintenance of the pump , the pump discharge shall be Future Projects Only
pumps are to be laid underground
Team Plant - Phase 1 commissionning) above ground
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Each Power Block will have its own dedicated Specification change involved provision for one centralized
LL_1_0404_00152 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Engineering Standards & Specifications - Closed Circuit Cooling Water System plus one common Closed Circuit Cooling Water System for all common Future Projects Only
Team Plant - Phase 1 commissionning) common CCCW system (TSPC-P-QD70-M-104) auxiliaries and the Desalination Plant
A Common Header and DM water distribution to Power Block
Ras Al Khair Power and Ras Al Khair Power Execute (incl. DM Water Distribution: 14 Make Up Pumps fed by 5x25% make up water pumps all consumers. No pump
LL_1_0404_00153 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Engineering Standards & Specifications - (2x100%) for each Power Block plus 2x100 % required for Desalination Plants. Future Projects Only
Team Plant - Phase 1 commissionning) for Desalination Plants (TSPC-P-QD70-M-084) Higher redundancy and significant reduction of power
consumption during normal operation.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. The Specification of the flow modulating Gas Bypass Damper
Gas Bypass Damper: As per Contract it was a
LL_1_0404_00154 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Engineering Standards & Specifications - was changed to Open/Close . Exhaust gas temperature is Future Projects Only
flow modulating Damper (TSPC-P-QD70-G-064)
Team Plant - Phase 1 commissionning) now being controlled by the Gas Turbine Control system .
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Gas station is located near the Power Plant and
As far as possible both should be nearer to Power Plant. GIS
LL_1_0505_00155 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - GIS (380kV Substation) is away from Power Future Projects Only
is to be closer to the Plant
Team Plant - Phase 1 commissionning) Plant
Ras Al Khair Power and Ras Al Khair Power Execute (incl. No common filtration system or moisture
Required redundant filtration and moisture separation system
LL_1_0505_00158 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - separator is available on the common gas Future Projects Only
for the common header at Plant area.
Team Plant - Phase 1 commissionning) supply line at Plant side.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. In Plant areas due to safety reasons above ground FG line
The Fuel Gas line is constructed above the
LL_1_0505_00162 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - should be avoided. Gas line may be routed through Future Projects Only
ground in Plant Area.
Team Plant - Phase 1 commissionning) underground trenches or buried.
Ras Al Khair Power and Ras Al Khair Power Execute (incl. Seawater intake: Facility for segregation with
This facility needs to be incorporated in order to clean the
LL_1_0505_00165 8-Apr-15 Desalination Plant Project and Desalination Desalination Plant testing and Construction Technical Issues - dam-boards is not available at common bay after Future Projects Only
intake bay without any shutdown over a period of time.
Team Plant - Phase 1 commissionning) the travelling band screen
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 9
1. Experienced Engineering Manager overviews and
Riyah-Ras Al Khair Water Execute (incl. coordinates between Contractor and Designer
Contractor Management - Lack of coordination between EPC Contractor
LL_2_0501_00174 2-Jun-16 ILF Consulting Engineers Water Transmission Transmission testing and Construction - Designs might have quality issues 2. Continuity for staffing of key positions is vital (no change of
Construction and Designer
System System commissionning) these position throughout the project should be achieved -
respective penalties to be defined)
Water Bill of Quantity did not include a specific quantity Additional quantities resulting from 1. When preparing the BoQ, take contingencies into account
LL_2_0406_00190 5-Mar-18 RNCF Team RNCF Transmission Define Engineering Design Review - for each material, but provided a range of project unplanned issues were approved to avoid requesting approvals even for small additions in
System quantities without having rounds of approvals quantities
Water Project team prepared a Rain Plan to take 1. Prepare plans for periods when project progress is
Project delay was minimized during rainy
LL_2_0805_00193 5-Mar-18 RNCF Team RNCF Transmission Execute Project Controls Project Schedule Control - preventive and/or corrective actions during rainy expected to slow down to take all necessary preventive and/or
days
System days, as they might hinder the project's progress corrective actions
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 10
The Contractors should be obliged to submit a full and
Water Delay in the project and not able to
Shoaiba-Mina Line comprehensive project schedule as part of their bid and
LL_2_0805_00209 7-Mar-18 SMLB Team Transmission Project Controls Project Schedule Control - Detailed scheduling was not submitted on time monitor the progress dur to lack of
B should be updated for the execution phase within two months
System baseline
of project signature
Verifying accuracy of the as-built drawings should be done in
Water
Shoaiba-Mina Line Delay in project progress due to the preliminary stages of the execution phase (i.e.. Suring
LL_2_0505_00210 7-Mar-18 SMLB Team Transmission Construction Technical Issues - As-builts for external utilities are not accurate
B inaccuracy of as-builts design, soils investigation) to avoid disruptions during the
System
construction
Water
Shoaiba-Mina Line Reduced time and effort especially for Ensure having clear specifications from the start to avoid
LL_2_0404_00211 7-Mar-18 SMLB Team Transmission Engineering Standards & Specifications - Contract had clear specifications
B approvals wasting time in approvals
System
Water
Shoaiba-Mina Line Team Effectiveness and Technical Experience and
LL_2_1003_00212 7-Mar-18 SMLB Team Transmission - Lack of expertise in the engineering team Low quality of the design
B Organization Capabilities
System
Water
Shoaiba-Mina Line Size and qualifications of contractor were No delays/stoppages due to contractor's
LL_2_0304_00213 7-Mar-18 SMLB Team Transmission Procurement and Contracting Tender Evaluation -
B essential to maintain performance size
System
Note: The Excel editable file is available with the Capital Effectiveness Team. For more info, please contact yal-shehri@swcc.gov.sa Page 11