Professional Documents
Culture Documents
Sewerage Nala Network at Nasrullaganj Su
Sewerage Nala Network at Nasrullaganj Su
For the
Development of
Sub project of
1
ABBREVIATIONS
AC – Asbestos Cement
BIS – Bureau of Indian Standards
BOD – Biological Oxygen Demand
CPCB – Central Pollution Control Board
C-ESMP – Construction Environmental and Social Management Plan
CPHEEO – Central Public Health Environmental and Engineering
Organization
CTE – Consent to Establish
CWM – Construction Waste Management
DRBO – Design Review Build and operate
DO – Dissolved oxygen
DPR – Detailed Project Report
D(R)BC – Design (Review) Build Contractor
DUAD _ Directorate of Urban Administration and Development
DWC – Double Walled Corrugated
ESA – Environmental and Social Assessment
ESMP – Environmental and Social Management Plan
ESR – Elevated Service Reservoir
GoI – Government of India
GoMP – Government of Madhya Pradesh
HDPE – High Density Polyethylene
HFL – Highest Flood Level
IEC – Information, Education and Communication
IPMF – Indigenous People Management Framework
IPP – Indigenous People Plan
ISWM – Integrated Solid Waste Management
LPCD – Liter Per Capita Per Day
MCM – Million Cubic Meter
MLD – Million Liter per Day
MoEF &CC – Ministry of Environment, Forest and Climate Change
MP – Madhya Pradesh
MPPCB – Madhya Pradesh Pollution Control Board
MPUDC – Madhya Pradesh Urban Development Company
MPUDP – Madhya Pradesh Urban Development Project
NAAQM – National Ambient Air Quality Monitoring
NNP – Nasrullaganj Nagar Parishad
NOC – No Objection Certificate
NOx – Oxides of nitrogen
NSR – Noise Sensitive Receivers
2
OHT – Over Head Tank
PIU – Project Implementation Unit
PM – Project Manager
PMC – Project Management Consultant
PMU – Project Management Unit
PWD – Public Works Department
RAP – Resettlement Action Plan
ROW – Right of way
SBM – Swatch Bharat Mission
SBR – Sequential Batch Reactor
SBSF – Small Bore Solid Free
SCV – Self Cleansing Velocity
SEIAA – State Environmental Impact Assessment Authority
SO2 – Sulphur Dioxide
SPS – Sewage Pumping Station
STP – Sewage Treatment Plant
SPCB – State Pollution Control Board
TVDP – Tribal and Vulnerable People Development Plan
TM – Traffic Management
UDHD – Urban Development and Housing Department
UIDSSMT – Urban Infrastructure Development Scheme for Small and
Medium towns
ULB – Urban Local Body
3
EXECUTIVE SUMMARY
INTRODUCTION:
1. Madhya Pradesh (MP) is geographically the second largest, fifth populous, and eighth
most urbanized state in India. MP„s total urban population is of 20.1 million (28% of total
population) concentrated in 476 urban centers. Rapid urbanization in MP has seen
sprouting of new urban settlements across the state, more often close to existing cities.
The last decade (2001-2011) has seen a 20% increase in the number of urban centers,
including a 50% increase in census towns, compared to a 6% increase in the previous
decade (1991-2001).
2. Government of Madhya Pradesh through its Vision Document 2018 has shown its
determination to face the challenges of Urbanization and has undertaken many programs to
support the urban infrastructure. Madhya Pradesh Urban Development Project (MPUDP) is
one of them, which envisages financial support from The World Bank for the various sub
projects of Water Supply and Wastewater Management, in select urban areas.
3. Nasrullaganj is a small town and a tehsil in Sehore District of the state of Madhya
Pradesh. Nasrullaganj is located in the Narmada basin at about 8 km from Narmada
River. Total municipal area under Nasrullaganj Nagar Parishad (municipality) is 8.08 sq.
Km. Nasrullaganj Nagar Parishad has 15 wards with a total population of 23,788 as per
census 2011. The decadal growth rate of Nasrullaganj during 2001-11 was 38% which
indicates a fast-growing trend of the city.
4. Any rapid urbanization has its own problems and woes, the major being the urban
infrastructure. To cater the needs of the civic infrastructure, Nasrullaganj Nagar Parishad
is making all out efforts. The water supply augmentation project based at River Narmada
provides water @ 135 lpcd to the 100% of inhabitants of Nasrullaganj town, was
commissioned in the year 2014 under Urban Infrastructure Development Scheme for
Small and Medium towns (UIDSSMT). The improved water supply to the town has
further increased Wastewater generation. The untreated sewerage of the town, through
drains and water channels (nallah), is discharged in to River Narmada which is life line of
Madhya Pradesh and a source of drinking water to many towns.
a) The proposed sewerage system is designed as Centralized system with gravity flow.
However, it was found during detailed designs that in the initial reaches (ward no. 1,5,12
and 15) of the town that the velocity and flow is very less resulting in low self-cleansing
4
velocity (SCV) in the sewers. Considering this, small bore solid free (SBSF) sewers are
provided in initial reaches of ward no. 1,5,12, and 15 having approximately 13.28 km
length so as to allow the settled sewage to flow at a velocity less than 0.6m/s but more
than 0.15 m/s. Once the flow and velocity is achieved, the small bore section shall drain
in to conventional sewer system. This hybrid mechanism of design/implementation shall
result in a sustainable sewerage system in terms of execution by minimizing excessive
depth of sewers due to steep slopes necessary for generating velocity and shall also in
terms of operation and maintenance wherein the activity of flushing the sewer lines to
ensure SCV will be reduced considerably. Design population of the town within the area
under Nagar Parishad jurisdiction for public amenities, has been projected to 44,232
(2048, Ultimate Year for Sub Project Design).
i. Small bore solid free sewer system of about 13286 m with 100/120 mm High Density
polyethylene Double Wall Corrugated (HDPE DWC) pipe in the initial stretches of
sewer network;
ii. Conventional system 29041 m with 150 /400 mm HDPE DWC pipes;
iii. An intermediate pumping station at Talai Mohalla, Ward No.2, near nallah;
iv. Construction of a STP Based on Sequential Batch Reactor (SBR)Technology with a
capacity of 4.20 MLD for the treatment of sewage generated by 35,944 people in the
intermediate year of design viz., 2033;
v. Construction of 993 circular manholes of 900/1200/1500mm bottom diameter and
560mm top diameter including BIS marked reinforced concrete heavy duty cover
complete for the conventional gravity sewer system;
vi. Construction of 1036 brick masonry chambers of 600 x 450 mm size and 900 mm
depth for connecting the outfall from individual households;
vii. Provision of 3,107 house sewer connections for connecting wastewater from the
households to sewer line.
The estimated cost of these works is approximately INR 255.59 million.
6. The proposed project does not attract EIA Notification of Government of India (GoI) and
hence Environmental clearance from Ministry of Environment and Forest and Climate
Change/ State Environmental Impact Assessment Authority (MoEF & CC/SEIAA) Other
National and State Legislations which are applicable to the proposed project are as follows:
5
ii. Water (Prevention and Control of Pollution) Act of 1974, Rules of 1975, and
amendments: Under this act the proposed sewage treatment plant will require
„Consent to Establish‟ and „Operate‟ from the Madhya Pradesh state pollution
control board.
iii. Air (Prevention and Control of Pollution) Act of 1981, Rules of 1982 and
amendments: Requirements of this act will be applicable both during
construction and operation phase of the project.
iv. Child Labour (Prohibition and Regulation) Act, 2000 and other labor laws of the
country
v. The Right to Fair Compensation and Transparency in Land Acquisition,
Rehabilitation and Resettlement Act, 2013 (RTFCTLARR Act 2013): No land
acquisition or resettlement impacts are anticipated for any of the proposed civil
works of the project. The act however will be applicable in general.
vi. The Street Vendors (Protection of Livelihood and Regulation of Street Vending)
Act, 2014: Requirements of this act will be applicable during construction.
7. The Project is being implemented through MPUDP with the financial assistance of The
World Bank. Therefore, The World Bank‟s environmental and social safeguards policies
and the requirements agreed through Environmental and Social Management Framework
(ESMF) for MPUDP, will be applicable to this sub-project. The applicable safeguard
policies of The World Bank for this sub-project include the following:
6
8. The baseline environmental status is important to understand the region's existing physical
and biological characteristics. Environmental Profile of the Nasrullaganj subproject area is
based on secondary data on Physiographic, Topographic, climatic, aquatic and Biological
profile of the town. There are no sensitive flora and fauna in Nasrullaganj and the species
found are commonly found in urban areas. Moreover, there are no National Parks, Wild life
sanctuaries, Bird sanctuaries within 10 Km radius of the project site. Also, no rare and
endangered species were found in the project area. The climate of Nasrullaganj is relatively
temperate with an average maximum and minimum temperatures of 32.3°C and 18.4°C
respectively. The average annual rainfall reported in Nasrullaganj town is about 1100 mm.
Secondary data on ambient air quality in Nasrullaganj is not available as there is no ambient
air monitoring station in the project area. In view of the above an initial ambient air quality
monitoring was conducted by MPUDC, in October 2017 at three locations. According to
3
these monitoring surveys, PM10 was observed in the range of 50.6 to 67.4 µg/m , PM2.5
3 3
was in of 25.9 to 43.7 µg/m , SO2 was found to be in range 9.1 to 13.4 µg/m , NOx was
3.
found to be in the range 14.2 to 24.7 µg/m All results are well within the National
Ambient Air Quality Standards (NAAQS).
9. Social study was undertaken to understand the cultural and social status of the residing
community. As per 2001 & 2011 Census of India, Nasrullaganj had a population of
17240 and 23788. Males constitute 53% of the population and females 47%. The average
literacy rate is 83% which is higher than the national average of 59.5%; with 89.11% of
the males and 76% of females are literate. Scheduled Caste population comprises 2961
(12.45%) whereas tribal population constitutes a mere 1743 (7.33%) of the total
population. Nasrullaganj Municipal Area has been divided into 15 wards for development
and administrative purposes. The total households of Nasrullaganj city are 4671.
Approximately 25% of this is below poverty line. There is no important cultural and
heritage resource notified by Archeological Survey of India or identified by the State
Government around the subproject area.
11. Based on the Social screening activity and the categorization of potential sub-project of the
MPUDP, the present sub project of Sewerage work of Nasrullaganj town falls under low
7
impact category, which do not have any fresh land acquisition and has a overall positive
impact by treating the wastewater of the town which was earlier polluting the river
Narmada and create unhygienic conditions. Whereas Integrated Sewerage Subprojects
involving construction of treatment plant, outfall sewers, and construction of deep sewer
lines in dense urban areas. Hence, Categorized as E a .
12. As per environmental and social management framework of MPUDP, the proposed project is
categorized as Ea and Sc and accordingly Environmental and Social Assessment, was
conducted for addressing possible issues/ concerns arising from proposed project.
13. The anticipated impacts and corresponding mitigation measures are discussed in Phases
namely: Influence area and general impacts. Based on the magnitude and duration of the
project activities, the nature, duration and extent of impact are assessed.
14. The overall impact of the project on the beneficiary communities and the environment is
expected to be positive resulting in an improvement in the health and quality of life of the
people in the subproject area. There are no environmental sensitive areas in the
subproject area, therefore no such permanently negative or adverse environmental
impacts were identified. No social impact likely to occur due to the acquisition of land,
also Nasrullaganj does not falls under declared Schedule V area, hence does not require
any additional efforts to ensure participation of Scheduled Tribes.
15. STP and IPS for proposed project has been planned to setup on Government lands. No
squatters or encroachers in and around these sites are likely to be affected by the project.
For laying of sewer works, there will be temporary disruption to the local community in
terms of traffic congestion, access to roads, (especially in dense areas and narrow roads),
shops and residences. In congested streets, the residents have built ramps over the drains
to have a direct access to the road or pathway. During laying of pipelines, due care will
be taken to not to disturb these ramps however, in some cases such ramps may have to be
demolished.
16. Possible Environmental and Social Impacts during preconstruction, Construction Phase
and Operation Phase has been identified and mitigations during these phases have been
suggested. Various environment and social impacts identified include 1) air pollution due
to dust and noise pollution during construction; 2) disposal of waste produced due to
excavation activities; 3) loss of vegetation (maximum 10 tress mainly of Babul- Vachellia
Nilotica along the alignment of network); 4) temporary loss of access to residents, due to
laying of sewer network (Temporary shifting of vendors- Vendors (sitting on ground) - in
total 20, Kiosks to be temporarily affected: 15, Extensions like approach for houses over
8
drains: to be temporarily affected-100); 5) temporary disruption to traffic; and 6)
temporary loss of income (approx. 145 roadside shops) etc. Such impacts would be
jointly estimated and verified during construction stage by the PIU and Design Review
Built Contractors (DRBC).
17. The tribal population of Madhya Pradesh increased to 15,316,784 in 2011 from 12,233,474 in
2001. In Madhya Pradesh certain areas have been declared as scheduled area as Specified by
the "Scheduled Areas under the fifth Schedule of Indian Constitutions". None of the areas of
Sehore district is scheduled in Schedule V by Government of Madhya Pradesh. However,
Social Impact screening and assessment was done for this population in Nasrullaganj and no
negative impacts due to the project were identified on tribal people.
18. On the basis of identification, assessment and prior informed consultations, it was found
that these groups are not a distinct groups, and also do not have any separate cultural,
economic, social, or political institutions. They are well versed with local Hindi language
also. No negative impact assessed during the process, so no separate IPP/TVDP is
prepared.
19. A brief summary of different stages consultation during the DPR and ESA preparation is
provided below:
i. DPR preparation Phase: Consultant representatives visited Nasrullaganj Nagar
st
Parishad on 1 June 2016 for kickoff meeting and site visits for preparation of ESA.
th st
ii. After draft ESA preparation, Public Consultations were organized on 20 and 21 June
2016, as part of the ESA study. Four (4) Public consultation, sensitization and inclusion
meetings were held within the wards (ward no. 2, 6, 11 and 12) of the project area with
the help of respective local administration and the elected representatives.
iii. In the month of April 2017 there were some modification done in the DPR and
th
accordingly ESA was revised and again public consultation were organized on 26
June 2017, as part of revised ESA study, especially in the core area and market area
of the proposed project.
th th
iv. 4 Stakeholder meeting held at different area of Nasrullaganj NP on 9 September
2016.
20. Stakeholders have been adequately consulted as part of the project preparation and
Environment and Social Assessment. Focused group discussions as well as informal
9
discussion with local people and ULB authorities were conducted at different levels of
project preparation as part of the Environmental Impact Assessment of the project. The
sub-project was welcomed by the local population in general. However, the local people
were concerned about the safety during the excavation and pipe laying process. They
were concerned about the loss of livelihood, accessibility, damages to properties and
grievance redressal. One strong suggestion which was identified from consultations was
execution of construction work within a scheduled time frame with provision of prior
notice to residents, shop-owners. Their concerns, views and suggestion are incorporated
in the project DPR and EMP.
21. Although there would not be any permanent negative or adverse environmental or social
impacts, but will have temporary impacts on water quality, air quality (impact on health),
traffic blockages, safety hazards for pedestrians, possible damage to private property,
possible interruption in commercial activity, and accidental breakage of other public
infrastructure such as water pipes.
22. Social assessment clearly defines that no issue of land acquisition and livelihood loss is
foreseen in the project. Hence, no compensation provision is required. However, if any
loss of livelihood would be noticed during implementation of this project, then the
affected party will be compensated according to Environment and Social Management
Framework (ESMF) guidelines for MPUDP. A public grievance mechanism (as
prescribed by ESMF of MPUDC) is to be followed. There is a clear mention and
highlighting if the social development issues and outcomes in this report. A section
chalking out institutional mechanism, capacity building requirements and monitoring and
evaluation mechanism is also included.
23. The ESA will be made available at public locations and will be disclosed in the web sites
of Nasrullaganj Nagar Parishad (Municipality), MPUDC, PMU and at the info-shop of
The World Bank. The consultation process will be continued and expanded during
project implementation to ensure that stakeholders are fully engaged in the project and
have the opportunity to participate in its development and implementation.
Environmental and Social Management Plan
24. Environmental and Social Management Plan. An environmental and social management
plan (ESMP) has been developed to provide mitigation measures to reduce all negative
impacts to acceptable levels. Locations and sitting of the proposed infrastructures were
considered to further reduce impacts. These include (i) locating facilities on government-
owned land to avoid the need for land acquisition and relocation of people; and (ii) laying of
pipes in RoW alongside main/access roads, to reduce acquisition of land and impacts on
livelihoods specifically in densely populated areas of the town.
10
25. The ESMP includes mitigation measures such as (i) implementation of traffic management
plan in coordination with local traffic police to minimize traffic impacts; (ii) awareness
campaigns and consultations to inform residents and businesses of potential disturbances;
(iii) provision of walkways and planks over trenches to ensure access will not be impeded;
(iv) use of noise-dampening measures in areas with sensitive receptors such as hospitals,
schools, places of worships and other silence-zones; (vi) use of dust-suppression methods
such as watering and/or covering of stockpiles; and (vii) finding beneficial use of
excavated materials to extent possible to reduce the quantity that will be disposed off. As
for the O&M phase, facilities will need to be repaired from time to time, but
environmental and social impacts will be much less than those of the construction period
as the work will be infrequent, affecting small areas only. The ESMP includes mitigation
measures and monitoring plan to ensure compliance to environmental and social
standards during O&M phase.
26. The ESMP will guide the environmentally-sound construction of the subproject and ensure
efficient lines of communication between Madhya Pradesh Urban Development Company
(MPUDC), project management unit (PMU), project implementing unit (PIU), consultants
and contractors. The ESMP will (i) ensure that the activities are undertaken in a responsible
non-detrimental manner; (ii) provide a pro-active, feasible and practical working tool to
enable the measurement and monitoring of environmental and social performance on site;
(iii) guide and control the implementation of findings and recommendations of the
environmental and social assessment conducted for the subproject; (iv) detail specific
actions deemed necessary to assist in mitigating the environmental and social impact of
the subproject; and (v) ensure that environment, health and safety guide lines of the GoI
and World Bank are complied with. The ESMP includes a monitoring program to
measure the environmental condition and effectiveness of implementation of the
mitigation measures. It also includes observations on- and off-site, document checks, and
interviews with workers and beneficiaries. The estimated cost of implementing ESMP
measures is about INR. 5.84 Million.
27. This ESA will be verified by MPUDC through its PIUs based on the final design of the
Design Review, Build and Operate (DRBO) Contractor and the relevant ESMP provisions
will be updated to address the impacts due to the design changes (if any). The updated ESA
ad ESMP will be shared with World Bank for necessary clearance and re disclosure by
MPUDC.
28. Urban Development and Housing Department (UDHD) of Government of Madhya Pradesh
11
(GoMP) is the Executing Agency for MPUDP and is responsible for management,
coordination and execution of all investment program activities. Implementing Agency is
the Madhya Pradesh Urban Development Company Limited (MPUDC) of GoMP, which
is implementing this program via a Project Management Unit (PMU) at Bhopal, and
regional Project Implementation Units (PIUs). PMU will appoint contractors to build
infrastructure and PIUs will coordinate the construction. PMU and PIUs will be assisted
by Project Management Consultants (PMC).
29. The contractor will be required to submit to PMU, for review and approval, a Contractor
environmental and Social Management plan (CESMP) including (i) proposed
sites/locations for construction work camps, storage areas, hauling roads, lay down areas,
disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following
the approved ESMP; (iii) monitoring program as per CESMP such as labour management
plan, social impact management; and (iv) budget for CESMP implementation. No works
are allowed to commence prior to approval of CESMP. During implementation, the
Contractor would be required to submit periodic reports covering ESHS parameters as
required in the CESMP.
30. A copy of the ESMP/approved CESMP will be kept on site during the construction
period at all times. The ESMP will be included in the bid and contract documents. Non-
compliance with, or any deviation from, the conditions set out in this document
constitutes a failure in compliance.
32. Affected person(s) shall file its grievance with the respective ULB, PIU or Contractor in
writing or through telephone, clarifying the area of grievance i.e., grievances related to
construction activities affecting the community or individuals livelihood or loss of
property/utility or restriction of access, and the grievances regarding the quality of service
during operation and maintenance period. The grievance shall be addressed within 48 hours.
However, if there is any technical issue, the aggrieved will be informed accordingly.
33. Project Manager of the concerned PIU for the project shall be the nodal officer for the
grievance redressal and shall maintain records of all the complaints/feedbacks received and
action taken. The meeting of the committee shall be convened as and when necessary and
12
at such place or places as it considers appropriate; and conduct the proceedings in an
informal/formal manner as he / she considers appropriate with the object to bring an
amicable settlement between the aggrieved parties. A Government Order to this effect
has already been issued.
35. There are no environmentally sensitive areas (like forest, sanctuaries, etc.) in or near sub-
project area. Hence the impacts identified are only confined to construction and operation
phase within the project area.
1. INTRODUCTION
13
the 16 Municipal Corporations, four (Indore, Bhopal, Jabalpur, and Gwalior) are million-
plus cities.
Rapid urbanization in MP has seen sprouting of new urban settlements across the state,
more often close to existing cities. The last decade (2001-2011) has seen a 20% increase
in the number of urban centers, including a 50% increase in census towns, compared to a
6% increase in the previous decade (1991-2001). The last decade also saw more than a
quarter-fold increase in population of the four largest urban agglomerations including
Bhopal and Indore. In the cities in MP, household access to piped water supply ranges
between 48-80%, per capita; water supply ranges between 35 to 150 lpcd; access to
underground sewerage range between nil to 40%; waste collection ranges between 85-
90%, and 60-80% of rainwater runoff is effectively drained.
The development objective of the proposed Madhya Pradesh Urban Development Project
(MPUDP) supported by The World Bank is to enhance the capacity of the relevant State-
level institutions to support ULBs in developing and financing urban infrastructure. To
achieve the above, the project envisages the components: Institutional Development
Component, Urban Investment Component, Bhopal-Indore Super Corridor (Feasibility
Study only).
The proposed Nasrullaganj Sewerage Project is one of the subproject under the Madhya
Pradesh Urban Development project (MPUDP) funded by the GoMP and the World
Bank. Proposed project is designed to collect the sewage water from the each household
and carry it to a suitable place for providing the desired treatment before the treated waste
water is being finally disposed to Nallah (natural water channel) or Reused for the
purposes like irrigation, gardening, firefighting, Industrial & institutional supply or
ground water recharge etc.
This project has been identified as Category Ea (Refer Appendix 2 for Environmental
Screening) project based on the environmental screening carried out for the project as per the
Environmental and Social Management Framework (ESMF) of MPUDP. This requires
14
an ESA report and an Environmental and Social Management Plan.
With regard to social safeguards, the project has been classified as „Category S c, because
no land acquisition is expected also no permanent adverse impacts on assets and
1
livelihood is anticipated, hence no RAP is required as per ESMF. Only minor damage to
road side properties and loss of income for certain days and locations during construction
phase may be identified. Such impacts shall be assessed by D(R) BO contractor and this
ESA and ESMP will be updated and approved by MPUDC. A quick social assessment is
carried out in the project area to identify indigenous people as per Indigenous People
Management Frame work (IPMF) and need for preparation of IPP was not identified.
The output of the above work led to this comprehensive Environmental and Social
Assessment report.
It should be noted that this categorization refers to the categorization of subprojects as stated in the MPUDP ESMF.
Category Ea , Category Eb and Category Ec of MPUDP is similar to Category A, Category B and Category C of as
per OP4.01 of the World Bank. Overall, as per safeguard policies of the World Bank, MPUDP has been categorized
as a Category A Project.
15
To make suggestions of possible alterations to the proposed design, based on the
assessment findings;
To propose mitigation measures for the potential adverse environmental and social
impacts and safety risks;
To ensure public participation; in the overall project cycle and
To prepare an Environmental and Social Management and Monitoring Plan.
1.5. Methodology
The ESA study was carried out based on desk review, field assessments and public
consultations with the community who are likely to benefit from the project, the potential
project affected persons and relevant Government Institutions. During the assignment
potential impacts of all stages of the project from pre- construction, through construction
and installation to operation in project area were evaluated against applicable
environmental and social standards, regulations and guidelines, the existing
environmental conditions, and issues and concerns raised by all project stakeholders. The
assessment process incorporates the following key stages:
16
the opportunity for alternatives or objections to be raised by the potentially affected
parties; non-governmental organizations, members of the public and other stakeholders.
See Appendix 5 for a) list of stakeholder's consultation; and b) a summary of the issues
and concerns raised.
Public meetings
Public Meetings with the communities were conducted in the project area with the help of
the local administration especially the corporators and ULB officials. The selection of the
wards for the meetings was done based on different categories, localities and level of
problems. Several meetings were held at different locations within the project area from
June 2016 to September 2017. The discussions during these public meetings were
centered on key emerging issues relating to the project as well as the communities.
One-on-one interviews with government agencies and institutions in the project area were
undertaken. These interviews were conducted to augment and confirm data and
information obtained through secondary sources.
Physical/chemical component;
Biological/ecological component;
Sociological/cultural component; and
Economic/operational component.
17
1.6 Mitigation and Monitoring
1.6.1. Mitigation
Mitigation measures were taken into consideration and defined during the impact
assessment process. The results of the mitigation analysis and the mitigation measures
included in mitigation plan of the Environmental & Social Management Plan along with
detailed budgetary estimates
1.6.2. Monitoring
The following monitoring approach is proposed:
The monitoring plan has been included in Environmental & Social Management Plan
(ESMP);
Joint verification and updation of ESMP based on DBRC design ; and
The PIU and MPUDC shall monitor the implementation of ESMP and track
indicators for IEC activities, grievance redressal, participation of women, Scheduled
Tribes and other vulnerable people. Quarterly report shall be prepared.
2. PROJECT DESCRIPTION
2.1.1. Background
Nasrullaganj is a small town and a tehsil in Sehore District of the state of Madhya
Pradesh. The town is located in the Narmada basin at about 8 kms from Narmada River.
Nasrullaganj lies on SH - 22 which connects to NH -12 towards Bhopal in the east,
Indore in the west and Sehore in the north. There is one major economic centre i.e. Krishi
Upaj Mandi in Nasrullaganj from where commodities are traded. Geographically
0 0
Nasrullaganj lies between 22 30' to 23°20´ N latitude and 76°22´ to 78 08' E Longitude.
18
Nasrullaganj is connected to Bhopal with SH 22 in the east at 92 kms, to Indore with NH
58A in the west at a distance of 165 km and to the district headquarter Sehore with SH 22
in the north at a distance of 73 kms. Budni at a distance of 50 km is the nearest railway
station.
Nasrullaganj is located at 440 m above Mean Sea Level. The average maximum and
minimum temperatures are 32ºC and 18.4°C. The average annual rainfall reported in the
town is about 1100 mm.
Since Nasrullaganj stands in the foothills of Vindhyachal Hill Range in the middle of
Malwa region, most of the area is an undulating plateau and is covered with black soils of
different grades. Due to this, soil of the region is productive. Babbar River flows in the
northern part of the town and Narmada River flows in the southern side of the city. A
nallah flowing in North-South direction bisects the town.
Total municipal area under Nasrullaganj Nagar parishad is 8.08 Sq. Km, which consists
of developed and undeveloped land. Nasrullaganj Nagar Parishad has 15 wards having a
total population of 23788 as per census 2011. The major occupation of the people in
Nasrullaganj town and its hinterlands, is agriculture; hence Krishi Upaj Mandi
(Agriculture Produce Market) is a major activity which accounts for a significant socio
economic profile of the town. The major commodities traded from the town are wheat,
pulses and soya bean. The market is connected to the nearest major railway station at a
distance of 60 kms in Hoshangabad which through Itarsi, is connected to all parts of the
country. The produce from the Mandi is sent to the nearby cities including Itarsi, Bhopal,
Dewas, Sehore, Indore, Obeidullaganj, and Mandideep etc. Bhopal is the nearest airport.
The intent of the proposed subproject is to ensure that comprehensive, technically and
financially viable system for Sewerage system for the whole city. This report deals with the
preparation of ESA report of Sewerage System of Nasrullaganj Nagar Parishad (NNP) area.
19
20
Figure 2-2: Nasrullaganj Base Map
21
2.2. Existing Water Supply and Sanitation System
The total installed capacity of the Water Supply System of Nasrullaganj town was 0.50
MLD which has been augmented to 5.60MLD under a water supply scheme under
UIDSSMT in the year 2014. The augmented capacity of 5.60 MLD shall ensure water
availability for the present and future population of the town at 135lpcd. The source of
water is Narmada River.
a) Bada nallah
b) Sehore side nallah
c) Runnjankhedi nallah
d) Beejla nallah
e) Muslim muhallah nallah
The BOD content of the municipal wastewater is appx 100 mg/l as per the test report
given at appendix 1, however, this is on lower side since the sewage flowing in drains/
nallah is already diluted. The Sewage generated is collected through individual septic
tanks which are cleaned periodically or are discharged into drains along the roads. The
houses without septic tanks discharge sewage directly into drains.
Similarly, the wastewater from schools, colleges, hospitals and hotels also is
discharged into natural nallahs. Since, there is no separate system for the collection of
wastewater from meat market and hospital, the wastewater is also discharged into the
nallahs along with domestic wastewater.
The people of Nasrullaganj, owing to their good economic condition are willing to
have an integrated sewerage system, so that the sewage collection and treatment can
be done in systematic manner and the town can have a clean and hygienic
environment. The absence of water supply, roads, disposal of garbage, and sewerage
may be identified as the four most important factors affecting the well-being of people
living in slums. In the proposed project entire Municipal area including permanent
settlements and slums are proposed to be connected to the sewerage system.
22
2.3. Need of Project
To sustain the high growth rate of the town, development of sewerage system is an
important aspect of the infrastructure that needs to be developed on priority. There is also
ground water pollution posing a danger of cross-contamination for the water supply
mains. In areas where there are no toilets, there is considerable open defecation posing a
threat to public health. In all the areas raw sewage is discharged into nallahs and drains
which is a danger to public health and also offends water pollution control regulations.
This raw sewage is finally meeting River Narmada through a major nallah passing
through the town. River Narmada is the life line of Madhya Pradesh and the State
Government is committed to conserve River Narmada against any kind of pollution. The
State has envisaged providing Sewage Treatment Infrastructure in all the Urban Entities
on the banks or within a range of 10 km of River Narmada.
The poor sewerage infrastructure will also retard the further development of the city. It is
therefore necessary to provide a comprehensive sewerage scheme covering all parts of the
NNP and ensuring that the sewage is adequately treated before disposal into water courses.
Proposed project is designed to collect the sewage water from each household and
carry it to a suitable place for providing the desired treatment before the treated waste
water is being finally disposed to nallah or Reused for the purposes like irrigation,
gardening, firefighting, Industrial & institutional supply or ground water recharge etc.
b) Design population of the town within the area which is under Nagar Parishad
jurisdiction for public amenities. The design population for this area has been
projected as 44,232 (2048, Ultimate).
c) Providing, laying and jointing of sewer network for 100% coverage of town. The
sewer design has been carried out for gravity flow utilizing the available ground
topography of the project area to have a gravity flow system having self – cleansing
velocity, and keeping depth of sewer within limits for ease of maintenance during
O&M period. SBSF sewers are provided in initial stretches where SCV is not achieved
to reduce flushing as far as possible.
23
2
d) STP based on SBR Technology has been provided for treatment of sewage. The STP
technology is being selected primarily taking into consideration less land requirement
and Operation and maintenance cost and effluent discharge characteristics as per
CPCB guidelines, so that treated water can be discharged into inland water ways
which are being potential drinking water sources.
The total estimated cost of Nasrullaganj Sewerage Project is Rs.255.90 million. The
details of major activities of the proposed project are summarized below:
1. Sewer Network
For the collection and conveyance of sewage from the households in the town, a sewer
network 42327 m is proposed. The network comprises a small bore solid free sewer
system and conventional gravity sewer system. The details of sewer pipeline in both
the cases are as below:
a) 100/120 mm HDPE DWC pipe is proposed for small bore solid free sewer system
for a length of 13286 m. This SBSF Sewer system is primarily proposed in the
fringe areas of the city such as ward Nos. 1, 5, 12 and 15.
Total Length
S. No. Diameter (mm) Pipe Material
(m)
1.0 150/180 23315 DWC HDPE
2.0 170/200 715 DWC HDPE
3.0 200/238 168 DWC HDPE
4.0 250/295 991 DWC HDPE
5.0 300/345 1208 DWC HDPE
6.0 400/480 1653 DWC HDPE
7.0 600 391 RCC NP 3
Total 29041
The DPR proposes SBR technology, however the bids will be invited on technology neutral basis. In case the
selected DRBO process a technology other than SBR, the revision in the ESA/ ESMP will be done. This clause has
already been included in the Bid document. The modified ESMP will be submitted to the WB for approval. The
work will be started after the approval of WB.
24
The work shall include the excavation of trenches, bedding as required, laying of pipe,
back filling and compaction and construction of road as per original condition.
It is proposed that the treated wastewater from STP shall be reused for flushing, fire
fighting, cleaning gardening and community purposes, for which the provision of
pumps of 1.00MLD capacity and pipeline of 5 km long of 110 mm of HDPE/PVC
pipe has been made. It is proposed that the pipe line shall be laid along the major
roads so as apply the water in the green areas along road. Furthermore, 500 trees of
various species shall be planted within the STP campus and around it, in a 6m thick
ring form green area all around the SPS, on either side of the approach road from
town to at least 500 m ahead of STP, on the banks of nallah (up to 500 m either side
of STP) etc which shall be watered by the treated wastewater. The remaining quantity
of treated wastewater shall be discharged in the nearby nallah section which
otherwise is carrying the untreated sewage along with storm water in the present
times. The digested sludge shall be transported to the regional landfill proposed under
ISWM (Bhopal Cluster), at Aadampur Chhaoni at the outskirts of Bhopal.
The STP shall be having RCC frame structure boundary wall up to 8 feet height so as
to isolate the STP from the transfer station adjacent to it within the same and prevent
any kind of interference between the two activities. The work shall also include
construction of all-weather road and staff quarters for operators and watchman within
the premises of STP.
As per CPHEEO manual design standards, the STP is designed for 15 years, whereas network is designed for 30
years.
25
3. Intermediate Pumping Stations
An intermediate sewage Pumping Station with a capacity of 0.65 MLD is proposed at
Ward No. 2, Talai Mohalla, near nallah (Khasra No. 79), over an area of 250.00 Sq.
m. The pumping station will have a sump of 12KL (30 minutes detention for ultimate
demand capacity), along with two pumps of 2.00 KW for intermediate peak flow, a
pump of 3.00 KW for twice the intermediate peak flow and a pump of 4.00 KW for
thrice the intermediate peak flow of 0.65MLD for pumping from sump to main trunk.
The pumping station will be surrounded by a 6 m wide green belt.
4. Laterals
This includes providing and laying 100/120 mm diameter DWC HDPE class pipe with
a total length of 10360 m for connecting house chamber to Manholes on sewer lines.
There are about 3107 households in Nasrullaganj to be connected into the sewer
network (under conventional sewer system) requiring about 1036 house service
chambers. An average length of 10.0 m for connecting each house service chamber to
manhole has been considered for connecting the household to chamber and thereafter
to the manholes in sewer lines.
5. HT feeder line
HT feeder line from the nearest 33 KV substation (about 5 km) shall be laid from the
taping point to the sewage pump houses for uninterrupted power supply to the STP
and pumps and motors of sewage pump house. Although the HT feeder line is
proposed to be laid within the RoW, however, a rapid environment assessment will be
done after finalizing the alignment by the DRB Contractor.
26
6. Rider mains
Rider main shall only be provided for the roads with a width more than 5m. Rider
mains comprising of 150/180 mm DWC SN 8.0 class pipe with a length of 10164 m
will be laid in a slope of 1 in 100 for a maximum length of 150 m. The pipe will be
connected to the house chambers and will carry the sewage to main sewer line on the
either side of the road.
7. Manholes
This involves construction of 993 circular manholes with 900/1200/1500 mm bottom
diameter and 560 mm top diameter including ISI marked reinforced concrete heavy duty
cover complete for the conventional gravity sewer system. The depths of manholes vary
from 1.60 m to 6.0 m as per the site conditions. For small bore solid free sewer system
232 circular manholes with 900/1200/1500 mm bottom diameter and 560 mm top
diameter including BIS marked reinforced concrete heavy duty cover complete will be
provided. The depth of these manholes will be limited up to 2.0 m.
8. House Chamber
This involves construction of 1036 numbers brick masonry chambers of 600 x 450
mm size and 900 mm depth, one for connecting outfall from individual households.
9. Small Bore Sewage Collection System with Interceptors
Looking at the existing developed areas and complexities involved in deep excavations in
narrow streets, it is proposed to use Small Bore Solid Free system (SBSFS) along with the
conventional system. SBSFS involves shallow tapping of effluent from septic tanks or
inceptors making it solid free, thus, helping in reduction of diameter of pipes required and
hence, less width of trenches will be needed. The work will include construction of 1122
interceptor tanks for settlement of suspended solid/sludge in sewage from households.
The frequency of removal of sludge from these interceptors will vary from 2 to 3
years. The digested sludge from the septic tank/interceptor will be sucked by a sewer
suction machine and will be disposed off at press filter of proposed STP. After
thickening the sludge thickened sludge will be put in to the sludge drying bed
proposed near the STP for drying the sludge. The digested sludge shall be transported
to the regional landfill proposed under ISWM (Bhopal Cluster), at Aadampur
Chhaoni at the outskirts of Bhopal.
27
This will include
The most important aspect of the project is to connect each household in the sewer
network so that the raw sewage is collected and conveyed to the STP for treatment. It is
proposed that the Urban Local Body shall take up Information, Educational and
Communication (IEC) activity and create general awareness amongst the citizens to
connect to sewer network. The ULB shall be approaching the property owners at least 15
days prior to start of the work in the specific ward or zone. The ULB shall be informing
the property owner in writing as well as through camps, to obtain applications for sewer
connections. The basic infrastructure of the property essential for providing the connection
to sewer network shall be developed by the contractor as per the recommendations and
approval of ULB. For this General Arrangement Drawings for different scenarios have
been developed and included in the bid documents. There could be following possible
scenarios for house connections in conventional.
a) The houses situated on the narrow streets and in fringe areas of 2 - 3 m will be
connected to the sewer network through SBSFS.
b) For the houses on wider streets with a width of 5 m or more, the inlet of septic tank or
the inspection chamber within the property boundary shall have to be connected to
House service chambers which are then connected to Manholes and which finally
connects to sewer lines. It is assumed that the property owner shall bring the black and
grey water up to the boundary of property; however, the DPR proposes development
of infrastructure within the property boundary as stated above and connect them to
municipal network. This will be done in the light of relevant provisions of Municipal
Act and the State policy thereof.
c) The toilets built under Swatchh Bharat Mission (SBM) will also be connected to the
network through SBSFS. This will need no dismantling etc.
Accordingly the house chambers shall be connected to the outlet at the property
boundary or inspection chamber of the houses. The sewage water from households
shall be brought directly from the outlet of house so that the raw sewage is obtained in
sewer lines.
28
3. Legal, Policy and Administrative Framework
The summary of regulations and mandatory requirements for the subproject is presented
in Table 3.1 below.
Law Description
Environment Related
Environment Emissions and discharges from the facilities to be created or refurbished
(Protection) Act, 1986. or augmented shall comply with the notified standards.
This is an umbrella act of Government of India and will be applicable for
the project.
Water (Prevention and Control of water pollution is achieved through administering conditions
Control of Pollution) imposed in consent issued under provision of the Water (Prevention and
Act of 1974, Rules of Control of Pollution) Act of 1974 of Government of India. These
1975, and conditions regulate the quality of effluent, the location of discharge and
amendments the frequency of monitoring of effluents. This act will be applicable to the
sub-project and the proposed sewage treatment plant will require NOC
„Consent to Establish‟ and „Operate‟ from the Madhya Pradesh state
pollution control board. The ULB has already applied to MPPCB and the
Consent shall be obtained before award of contract.
Air (Prevention and The subproject with a potential to emit air pollutants into the atmosphere
Control of Pollution) have to obtain CTE under Section 21 of the Air (Prevention and Control
Act of 1981, Rules of of Pollution) Act of 1981 from Madhya Pradesh Pollution Control Board
1982 and (MPPCB) before starting construction of the project and CTO before
amendments. commissioning and operation the project. The occupier of the
project/facility has the responsibility to adopt necessary air pollution
Requirements of this act will be applicable both during construction and
operation phase of the project.
29
Law Description
Madhya Pradesh State Prepared in accordance with the National Water Policy, it states that “for
Water Policy, 2003 environmental balance, skillful and planned management of all types of
developmental activities, economic use on equitable basis and in view of
the prime importance of water for all human and other living beings, an
effective and sound water policy is necessary”.
Policy is detailed in 17 sections dealing with different aspects of water
resources. No. 7 deals with Water Allocation Priorities, and according to
which drinking water supply shall have the highest priority followed by
irrigation, power, tourism, etc.
Water Resource Department is nodal department for permitting different
uses of water resources. Policy also states that “clear provision for
reservation of drinking water shall be made in irrigation projects”
Social Related
The Right to Fair The Act provides for enhanced compensation and assistances measures
Compensation and and adopts a more consultative and participatory approach in dealing
Transparency in with the Project Affected Persons.
Land Acquisition, No land acquisition or resettlement impacts are anticipated for any of
Rehabilitation and the proposed civil works for Nasrullaganj Sewerage Scheme, hence this
Resettlement Act, impact is not applicable to the propose subproject.
2013 (RTFCTLARR
Act 2013)
MP Nagariyon Madhya Pradesh is the only Indian state where a separate act has been
Kshetra ke passed by the state legislature for regularizing tenure of squatters on
Bhumiheen Vyakti government land. GoMP has been granting leasehold land titles or Pattas
(Pattadhruti to “landless persons” or residents of squatter settlements in urban areas
Adhikaron ka Pradan on the basis of the MP Nagariyon Kshetra ke Bhumiheen Vyakti
Kiya Jana) (Pattadhruti Adhikaron ka Pradan Kiya Jana) Adhiniyam, 1984,
Adhiniyam, 1984, popularly known as the Patta Act. The Act applies to all urban areas of
popularly known as MP. The `Patta‟ Act was introduced to grant leasehold rights to the
the Patta Act. landless persons occupying urban lands. The Act entitles all landless
persons occupying less than 50 sq m of land on a specified cut of date to
leasehold rights for residential use on the same land or on another site.
This act is not applicable for the proposed subproject because no such
groups are affected by the proposed subproject activities.
The Street Vendors GOI recently enacted the act that specifically aims to protect the rights
(Protection of of urban street vendors and to regulate street vending activities. It
Livelihood provides for Survey of street vendors and protection from eviction or
and Regulation of relocation; issuance of certificate for vending; provides for rights and
30
Law Description
Street Vending) obligations of street vendors; development of street vending plans;
Act,2014 organizing of capacity building programmes to enable the street
vendors to exercise the rights contemplated under this Act; undertake
research, education and training programmes to advance knowledge and
understanding of the role of the informal sector in the economy, in
general and the street vendors, in particular and to raise awareness.
Requirements of this act will be applicable during construction.
The Scheduled An Act to recognise and vest the forest rights and occupation in forest
Tribes land in forest dwelling Scheduled Tribes and other traditional forest
And other dwellers who have been residing in such forests for generations but
Traditional Forest whose rights could not be recorded; to provide for a framework for
Dwellers recording the forests rights so vested and the nature of evidence required
(Recognition of for such recognition and vesting in respect of forest land. This does not
Forest Rights) Act, apply to this sub project.
2006.
31
Table 3-2: World Bank Safeguard Policies applicable for MPUDP
32
World Bank Safe Objective Applicability Trigger Safeguard
Guard Policies Requirements
People to ensure that they do not suffer due to India, the share of scheduled Tribes in key stakeholders it is
development; that they receive social and the project area is 7.33% only. Further, confirmed that the tribal
economic benefits they are scattered all over the town. people in the project area
do not exhibit typical
characteristics such as
living as a group; speak
separate language from
dominant population,
having separate
institutions in close
attachment to the forest
etc. Hence, the policy
does not apply. No
separate IPP is required
OP/BP 4.11 This policy aims at assisting in the This policy may be triggered by sub- No This policy is not
Physical preservation of cultural property, historical, projects where cultural property, triggered. While there
Cultural religious and unique natural value-this historical, religious and unique natural are no physical cultural
Resources includes remains left by previous human value-this includes remains left by resources identified in
inhabitants and unique environment features, previous human inhabitants and unique the project area, since
as well as in the protection and enhancement environment features may be affected the location of
of cultural properties encountered in Bank- due to project. sewer/feeder line is not
financed project. finalized, chance find
procedure should be
proposed and
implemented.
33
World Bank Safe Objective Applicability Trigger Safeguard
Guard Policies Requirements
General EH & S The General Environment, Health and Safety These Guidelines are technical YES Guide lines for Water
Guidelines (EHS) Guidelines contain information on reference documents with general and and Sanitation projects
World bank cross-cutting environmental, health, and industry-specific examples of Good available
group safety issues potentially applicable to all International Industry Practice
projects. (GIIP).The Guidelines contain the
performance levels and measures that
are normally acceptable to World Bank
Group and that are generally
considered to be achievable in new
facilities at reasonable costs by existing
technology.
ESMF including Resettlement Policy Framework (RPF) and Indigenous Peoples Planning Framework (IPPF) will be applicable for all the activities of
MPUDP, i.e., activities under Technical Assistance and implementation including operation and maintenance of all subprojects and activities.
34
4. Baseline Environment Profile
4.1. Baseline Study
This chapter deals with the existing environmental profile of the project area. The
baseline details recorded will form the basis for the potential impacts due to the proposed
sewerage project.
35
36
4.3. Physical Environment
4.3.1. Meteorology
Nasrullaganj has a sub-tropical climate. A hot summer and general dryness characterize
the climate of the area, except during the southwest monsoon season. The year may be
divided into four seasons. The cold season, December to February is followed by the hot
season from March to about the middle of June. The period from the middle of June to
September is the south-west monsoon season. October and November form the post
monsoon or transition period.
The normal annual rainfall reported in Nasrullaganj town is 1100 mm. The district Sehore
receives maximum rainfall during south-west monsoon period i.e. June to September. July
is the wettest month of the year and about 36% of the annual rainfall occurs during this
month. About 92.4% of the annual rainfall occurs during the southwest monsoon period
i.e. between June to September. About 6.2% and 1.4% rainfall is received during winter
and summer season respectively.
The climate of the town is relatively temperate with an average maximum and minimum
temperatures at 32.3°C and 18.4°C respectively. The normal maximum temperature
0
noticed during the month of May is 44 C and minimum during the month of December
0
9.8 C.
Seasons Months
Summers March end to June mid
Rainy June mid to August end
Post Manson September to November
Winters December to February
Autumn March
37
Figure 4-3: Air and Noise Monitoring Sites in Nasrullaganj
Monitoring site
near SPS
Monitoring
site near NNP
Monitoring site
near STP
38
Table 4-3: Ambient Air Quality of Nasrullaganj
3
S.No AAQM PM 2.5 (µg/m )
Station
Maximum Minimum Average Permissible Limit WHO Ambient Air
(dB) as per Quality Guidelines
NAAQS (24 hour) (24 hour)
1. AAQM 43.7 36.1 40.20 60 75(Interim target 1)
(Near STP 50(Interim target 2)
site) 37.5(Interim target 2)
2. AAQM 41.1 33.4 38.7 60 25 (guideline)
(Nagarpalika
office)
3. AAQM 34.5 25.9 29.65 60
(SPS site)
3
S.No AAQM PM 10 (µg/m )
Station
Maximum Minimum Average Permissible Limit WHO Ambient Air
(dB) as per Quality Guidelines
NAAQS (24 hour) (24 hour)
1. AAQM 67.4 57.2 62.3 100 150(Interim target
(Near STP 1)
site) 100(Interim target
2. AAQM 67.3 50.6 57.5 100 2)
(Nagarpalika 75(Interim target 2)
office) 50 (guideline)
3. AAQM 62.4 51.8 56.7 100
(SPS site)
3
S.No AAQM SO ᵪ (µg/m )
Station
Maximum Minimum Average Permissible WHO Ambient Air
Limit (dB) as per Quality Guidelines
NAAQS (24 (24 hour)
hour)
1. AAQM Near 12.8 7.5 10.55 80 125 (Interim target 1)
STP site) 50 (Interim target 2)
39
2. AAQM 13.8 9.8 11.7 80 20 (guideline)
(Nagarpalika
office)
3. AAQM SPS 13.4 9.1 11.02 80
site)
3
S.No AAQM NO ᵪ (µg/m )
Station Maximum Minimum Average Permissible Limit WHO Ambient Air
(dB) as per Quality Guidelines
NAAQS (24
hour)
1. AAQM 22.5 14.2 19.15 80 1 hour- 200
(Near STP (guideline)
site) 1 Year- 40
2. AAQM 24.7 16.8 20.27 80 (guideline)
(Nagarpalika
office)
3. AAQM SPS 16.5 20.9 18.7 80
site)
th th st rd
Source: Monitoring done on 14 , 16 , 21 and 23 of October by Noida Testing Laboratories
The information collected at AAQM station reveals that the quality of Ambient air in
Nasrullaganj is within the Standards set by CPCB. The table shown above reveals that the
quality of ambient air ( PM 2.5) near the STP site is 40.20 against the CPCB standard of
60 similarly near Nagar Palika office and SPS site the ambient air quality is 38.7 and
29.65 respectively.
Ambient air quality of Nasrarullaganj at ( PM 10 ) near the STP site was found to be 62.3
while near Nagar Palika office and SPS site same was 57.5 and 56.7 against the CPCB
standard as 100.
The SOx in the ambient air quality of Nasarullaganj near STP was report 10.55 against
the CPCB standard of 80. Similarly near Nagar Palika office and SPS site it was reported
as 11.7 & 11.02 respectively against the CPCB standard of 80. The level of NOx near the
STP site was found to be 19.5 ranging between 14.2 to 22.5. while the CPCB standards it
should be 80. The NOx level near the Nagar Palika was 20.27 ranging between 16.8 to
24.7 against the CPCB standard of 80. The data revels that the ambient air quality of
Nasrullaganj is within the Limit having no adverse impact.
Noise Monitoring
Noise Level Monitoring was done at three locations given in Table below in the day and
night time noise level was monitored in the range of 53.2 dB to 57.4 dB while in the night
40
time it was 33.6 db to 37.8 dB. It was found to be within the permissible limits National
Ambient Noise level standards are given in appendix 10.
Source: Noise Level Monitoring done on 14 Oct 2017 by Noida Testing Laboratories, for MPUDC
41
4.3.4 Soil
Nasrullaganj stands in the foothills of Vindhyachal Range in the middle of Malwa region.
The most of the area is made of undulating plateau surface and is covered with black soils
of different grades. Due to this it has got good productive soil. The black cotton soil, in
general, is varying from 0.60 m to 2m in the Nagar Parishad limits. However, the other
type of soil in this area is yellow soil mixed with small sized stones.
The district is generally covered with black cotton soils covering almost three fourths of
the area. This part is occupied by Deccan Basalts. The rest part has red-yellow mixed
soils derived from sandstone, shale, gneiss. The alluvial soils are found along the river
courses. The higher elevations i.e. the hilly regions have a cover of gravel, which is made
up of small rounded pieces of weathered trap. The Vindhyas and Bijawars have a thin
cover of sandy loams. The soils in granitic area are clayey. The schist has a thin capping
of loam with lot of quartz grains. The alluvium is derived from hill slopes by numerous
streams and watercourses.
42
4.3.5. Physiography
Physiographically the district has been divided into three units based on the valleys formed
by the major rivers i.e. Narmada basin, Chambal basin and Betwa basin.
4.3.6 Topography
The northern part of the Nasrullaganj city is slightly hilly. Natural Slope of the NNP area
is north to south. A major nallah flowing from north to south bisects the town. River
Babbar flows towards the northern side of Nasrullaganj whereas River Narmada is appx 8
km towards south.
Sewage collection is effected by gravity and therefore accurate topographic survey of the
project area based on street levels is of prime importance to the design of the system and
43
its subsequent efficient performance. A topographic survey has been carried out for city
area and a contour map has been prepared. As per the survey, the general slope of the
town is in south west direction. The sewerage network and the location of STP are
envisaged in accordance to the general slope of the town. Natural drains or water
channels also play an important role in deciding the alignment of sewerage network. As
per the topographic survey, the highest level is 299.47 whereas the lowest invert level is
287.34 which means a fall of 12.13 m. However, as stated in previous sections, a major
nallah flowing from north to south direction, bisects the town. Owing to the topography,
a SPS has to be provided.
Nasrullaganj Municipal Area has been divided into 15 wards for development and
administrative purposes. The total households of Nasrullaganj city are 4671.
44
Male 12599 1565 12.65 959 7.61
Female 11189 1396 12.47 784 7.00
No. of Household 4671 573 12.26 326 6.98
Family Size 5.09 5.16 5.34
Sex Ratio 888 892 817
Source: Census 2011
45
Table 4-8: Category-wise Classification of Workforce in Nasrullaganj, 2011
No of
S. No Category Percentage
persons
1 Main Workers 6527 27.44
2 Marginal Workers 857 3.60
3 Non workers 16404 68.96
Total Population 23788 100.00
Source: Census 2011
The female WPR (workforce participation rate) in the City is only 4.6% in 2011, as against
15.1% of Madhya Pradesh and 15.4 % of India.
Out of the main workers, 84% are engaged in other activities, those engaged in primary activities
are 14% and remaining are engaged in household industries. "Other Workers‟ include workers
engaged mainly in manufacturing industries, trade and commerce, construction activities,
transport and communication and other service activities. Thus majority of population is engaged
in secondary and tertiary sector activities in Nasrullaganj town.
46
Out of the marginal workers, 79% are engaged in other activities, those engaged in
primary activities are 16.7% and remaining are engaged in household industries.
The Development Plan of Nasrullaganj has not been prepared by the Directorate of Town
& Country Planning. However, an indicative land use pattern is given as under:
Table 4.11: Tentative Land Use pattern of Nasrullaganj
% of Municipal
S.No Land use Area in sqkm
Area
1 Residential 1.13 13.98
2 Amenities 0.33 4.08
47
3 Roads 0.24 2.97
4 Water Bodies 0.20 2.47
5 Commercial 0.28 3.48
6 Agriculture/ Green 5.90 73.02
Total Population 8.08 100.00
Source: City Development Plan, Nasrullaganj
A high literacy rate of 83% and marginal slum population is a clear indication of the
economic and social growth of Nasrullaganj.
48
5. ANALYSIS OF ALTERNATIVES
Analysis of alternatives involves a thorough study of the possible alternatives to the
proposed project and its components. As part of the environmental and social assessment,
an analysis of various alternatives was carried and the same has been summarized below.
The proposed project is formulated for the collection of sewage through small bore and
conventional gravity sewers and its treatment scientifically for accepted standards of
effluent discharge before it is reuse or disposed. The scheme is being framed in
accordance with the guidelines given in CPHEEO Manual of Sewerage and Sewage
Treatment Plant. The project is designed for small bore and conventional gravity sewers
as per the ground topography.
The designs were carried out initially for conventional gravity sewer system. The less
quantity of sewage resulting in non-achieving of SCV in initial stretches required
flushing for cleaning of these pipelines during operation and maintenance. Thus to avoid
flushing and to enhance the sustainability of the system in terms of better workability,
Non-Conventional sewer system in the form of Small bore solid free sewer has been
suggested in this project.
The proposed hybrid system comprising of conventional gravity sewers and SBSF sewers
has 3-5% lower CAPEX and 1-2% high OPEX.
Small Bore Solid Free sewer system
Small bore sewer system shall be provided with interceptor tank having 24 hours of
detention period. The suspended solids and sludge in the sewage generated from the
households shall be settled in this interceptor tank. The settled sewage water shall be
flown in small diameter sewer lines at lesser velocity up to the conventional gravity
sewers. The small bore sewer pipelines shall have the diameter of 100 mm. The depth of
small bore sewer pipe is less as it required flatter slope due to less velocity requirement.
The frequency of man holes has been taken as 100m c/c, as the sewage is solid free and
do not require any frequent cleaning.
a) Sewer Lines
The small bore sewer line shall comprise of 100mm HDPE-DWC pipe laid on design
gradient as per ground topography so as to reduce excavation and road restoration.
49
Table 5-1: Details of Small bore sewer system
The details of velocities achieved in different diameters in the network for conventional
and hybrid system (SBSF and conventional) is as below,
Table 5-2: Details of velocities achieved in different diameters in the network for
conventional and hybrid system
50
42326.30 26390.10 62.35 2048
As per the above it is clear that in case of Hybrid system i.e., combination of
conventional sewer system with SBSF sewer system the self-cleansing velocity is
achieved in almost 50% of the sewer lines including 100% in the trunk sewer and all
major arteries of the network in initial year itself. Sewer lines in conventional system
which have velocity less than SCV shall be flushed during O&M for generating self-
cleansing velocity as suggested in CPHEEO manual and given in IS 4111 part 2.
The proposed hybrid system is selected over the conventional network due to the
following reasons:
51
The land parcels available near the tail end of the sewer network were agriculture lands or
private except for nala area which is in possession of the ULB and is presently being used
as landfill/ dumping ground. However, in the Integrated Solid Waste Management
(Bhopal Cluster), it is proposed to develop transfer station for collection and transfer of
solid waste of town on this land. The approximate quantity of Solid waste likely to be
generated in next 15 years is 8.986 Million tonnes per day. The area of land available after
construction of STP is approximately 1.42 Ha which shall be sufficient for storage of solid
waste for 15 -20 days within which period it will be transferred to the common landfill
site. Hence, out of 2 hectares of the land, 0.5 hectare of land has been proposed for STP.
The land required to construct STP is approximately 0.50 Ha while the available land is
almost approx. 2 Ha. The land selected is almost flat and without any vegetation (except
some shrubs).
Nasrullaganj comes under Bhopal Cluster. The work for this cluster has already been
awarded to the Private Partner. The land for common landfill site is already in
possession. The work of common landfill site is already in progress and is likely to be
completed by the end of December 2018. These landfill will cater the Municipal waste
52
this project are likely to be completed by the end of December 2018 whereas the work
of STP will be completed within two years of date of award which is much beyond the
scheduled date of completion of common landfill site.
53
Nallah section caring capacity near STP location
Discharge (Q) = 35 * 1
3
= 35 m /s
Calculation of discharge from STP to nallah:
54
5.3. Comparison of Different Methods of Sewerage Technology
Biological Treatment Technologies-Comparison
Sr Parameter Technologies
No
Oxidation pond Aerated Lagoon UASB (Up flow ASP (activated sludge MBBR (Moving Bed SBR (Sequential Batch Membrane Bio Phytorid
anaerobic sludge process) Bio Film Rector) Reactor) Reactor
blanket) (MBR)
1 Treatment Combination of facultative (semi Anaerobic- Aerobic suspended Aerobic attached growth Aerobic suspended Aerobic Root Zone
Process Aerobic-Anaerobic - aerobic) - biological biological growth - biological - biological (modified growth - biological suspended Treatment Process.
biological Process. suspended growth Activated Sludge (Improvised Activated growth - Organic Load and
process Process) Sludge Process) biological nutrient removal by
GETTING REPLACED (Improvised Plantation uptake.
OLD OLD WITH MODIFIED MODIFIED NEW ADVANCE Activated ADVANCE
TECHNOLOGY TECHNOLOGY /IMPROVED TECHNOLOGY IMPROVISED Sludge Process) IMPROVISED
GETTING VERSIONS TECHNOLOGY ADVANCE TECHNOLOGY
OBSOLETE IMPROVISED
TECHNOLO
GY
2 Process in BOD reduction BOD reduction This is strictly An Aerobic biological An Aerobic biological An Aerobic biological It is a biological It involves 2 stage
brief takes place due to takes Place anaerobic Process. process where aeration process where aeration process where aeration, reactor with a treatment.
oxidation by aerobically and/ or BOD reduction followed by followed by settling and decanting suspended 1. Primary Settling
Sunlight in aerobic, combination with takes place by settling/sludge recycle settling/sludge recycle happens in a single tank biomass. The where the solid
anaerobic, or anaerobic converting organic happens in a separate happens in a separate including nutrient solid‐liquid separation is
aerobic- anaerobic (facultative) matter to tanks. In case of tanks. Separate sludge removal and sludge separation in achieved due to the
environment. Suspended growth methane/carbon di- conventional treatment, digestion/ stabilization digestion. SBR is a membrane formation of bio-
Complete treatment Process. This is oxide and other separate sludge digestion/ is provided. batch process, which bioreactor is flocs assisted by a
happens in series of modification of gases, through stabilization is provided. eliminates the achieved by a onetime added
ponds. oxidation ponds. Bacterial synthesis. inefficiencies of microfiltration biomedia. The
UASB followed by continuous systems like membrane No sludge generated is
lagoon/ASP Activated Sludge secondary also reduced in the
treatment is must. Process, Extended clarifier is used same chamber and
Aeration etc. and has the sludge disposal is
ability to only required once a
55
flow itself by
gravity eliminating
the use of any
electricity, for
biological aerobic
oxidation in the
presence of friendly
organisms which is
inoculated only
once at the time of
commissioning.
Nutrient uptake of
Nitrogen and
Phosphates occur in
this tank with the
help of plantation
3 "SIZE- Suitable for any Suitable for any Suitable for any Suitable for any size, no Suitable for any size. Suitable for any size, no Suitable for any Scalable to any
WISE" size, no limitation. size, no limitation. size, no limitation. limitation. However, not limitation. size. However size. Applicable
Suitability Larger sizes demand Larger sizes demand Larger sizes recommended for high not used for from table top
of much higher space much higher space demand much capacities (50 MLD and high capacities. miniature plant to 5
the process higher space Above). MLD size. For
above capacities,
modular approach is
followed.
Biological 50 mg/lit 50 mg/lit 30 mg/lit (UASB+ASP) 20-30 mg/lit 20-30 mg/lit 5 mg/lit 5 mg/lit 5mg/lit
Oxygen
Demand
(BOD)
Chemical 250 mg/lit 250 mg/lit 100 mg/lit (UASB+ASP) 100 mg/lit 100 mg/lit 50 mg/lit 50 mg/lit
Oxygen 25mg/lit
Demand
(COD)
Total 100 mg/lit 100 mg/lit 100 mg/lit (UASB+ASP) 100 mg/lit 50 mg/lit 10 mg/lit 5 mg/lit
Suspended 10 mg/lit
Solids
(TSS)
Ammonical no treatment no treatment no treatment no treatment no treatment 5 mg/lit no treatment
<1 mg/lit
Nitrogen
(NH4-N)
Source: DPR of proposed sub project
63
56
Total no treatment no treatment no treatment no treatment no treatment 10 mg/lit no treatment
Nitrogen <1 mg/lit
(TN)
Total no treatment no treatment no treatment no treatment no treatment 2 mg/lit no treatment <1 mg/lit
Phosphorou
s (TP)
Fecal no treatment no treatment 100 MPN/100 (after 100 MPN/100 (after 100 MPN/100 (after 100 MPN/100 100 MPN/100 100 MPN/100
coliforms disinfection) disinfection) disinfection) (after (after
disinfection) disinfection)
5 Additional Being obsolete Being obsolete Nutrient removal treatment Nutrient removal Nutrient removal No additional Separate No Additional
treatment & final
treatment technology, up technology, up & final tertiary treatment tertiary treatment & final treatment is Nutrient treatment required
gradation or pre- gradation or pre- treatment (filtration,
required to post post (filtration, etc.) are required etc.) tertiary treatment required. removal
achieve the treatments are not treatments are not are required (filtration, etc.) are treatment is
latest possible possible required required.
outlet
norms
57
7 Usage of Treated effluent "as Treated effluent "as Treated effluent "as-such" Can be used for Can be used for Can be used for Can be used for Can be used for
cannot be used for even
treated such" cannot be such" cannot be low gardening. However, gardening. However, non-potable non-potable non-potable
effluent used for even low used end purposes such as needs tertiary treatment needs tertiary purposes such as purposes such purposes such as
end purposes such for even low end construction, floor washing for other non-potable treatment for other gardening, car as gardening, gardening, car
non-potable
as construction, purposes such as etc. Secondary purposes. purposes. washing, car washing, washing, industrial
floor washing etc. construction, floor treatment in form of ASP. industrial industrial washings, railways
washing etc. Followed by tertiary washings, washings, for washings,
Tertiary treatment treatment must be provided railways for railways for cooling tower etc.
must be provided even for low end uses. washings, etc. washings, etc.
even for low end However,
uses. biological
nutrient
removal prior
to
use is
recommended
8 Inlet flow Can handle Can handle Cannot handle Cannot handle Cannot handle Can handle Cannot handle Handles all flow
variations variations
9 Level of No automation No automation Very few automation Very few automation. Very few automation Fully automatic Fully automatic No controlling
automation However, additional with manual with manual needed. No
/ energy automation is possible. override. Air override. automation
efficient requirement is However, required. Designed
optimized
equipment through energy to operate in
oxygen uptake
rate requirement is absence of
control.
Feedback very high due monitoring Only
is taken (through to type of flow of sewage to
PLC /SCADA) process itself. be checked once a
from dissolved day.
oxygen meter
installed in SBR
basins and fed to
VFD, which
makes
58
the blower to run
efficiently all the
time. This total
system ensures
air is supplied
proportionately
to the inlet load
all times of
operation.
Besides, plants
being operated
through PLC /
SCADA control,
all treatment unit
operations are
operated in
controlled and
optimized
conditions.
Hence,
energy
consumption is
optimized.
10 Future Not possible Not possible Not possible Possible Possible Possible Possible Possible.
Augmentatio
n
11 CAPITAL COSTS
approx. 25-30 30-40 85-90 (UASB followed by 85-90 85- 90 90 -100 300 -325 135-150
Capital cost ASP) Cost may
for plant, increase
Rs. or
Lakhs/ML decrease
D based on
local
conditions
additional Not possible to Not possible to 40 40 40 0 25
cost for include additional include additional
nutrient treatment treatment
removal &
tertiary
treatment,
Rs.
Lakhs/ML
D
59
Total plant Not possible to Not possible to 115- 125 125 -130 125 -130 90 -100 325- 350 135-150
cost to achieve the outlet achieve the outlet
achieve the quality quality Cost may
latest increase
outlet or
quality, Rs. decrease
Lakhs/ML based on
D local
conditions
12 AREA REQUIREMENTS
60
Approx. 10000 6000 1000 700 350 400 450- 500 1300
Area
requirement
, for plant
(m2/MLD)
additional -- -- 100 100 100 0 50 Any
area shape
required for
tertiary
treatment
(m2/MLD)
Total area -- -- 1100 800 450 400 500 - 550 0
required
for plant to
achieve the
latest
outlet
quality
(m2/MLD)
13 Approx. Negligible Negligible 110- 125 190 - 220 190 -220 130- 150 250- 300 0
POWER Only for
requireme lifting
nt, for sewage if
plant below
kWh/MLD surface
level
14 Overall Negligible negligible 1.5 - 2.0 3.5 - 4.0 3.5 - 4.0 2 - 2.5 6-7 0.8
O&M
COST
including
power in
Rs. / m3
Very less This is an anaerobic It is the best and
15 Merits Very less or no manpower process efficient It is best and efficient Latest outlet quality It is best and Zero
efficient
manpower required. required. Power so it has the advantage of treatment amongst all treatment saving the norms can meet with treatment Operation
area as compare to SBR technology
No power requirement is only low energy consumption. conventional treatment the without saving the area as maintenan
to achieve the old conventional
requirement for for aerators. There is biogas production. outlet treatment any separate tertiary compare to the ce
main plant.
Minimal Minimal sludge Low production of surplus quality standards. and better outlet treatment. conventional required.
sludge production. production. Can sludge. quality as compare to Energy efficient treatment and The
the ASP & meeting
Can handle handle intermittent the treatment. Power better outlet constructi
61
intermittent flows. flows. Robust and old outlet quality consumption is quality as on is
Robust and can can withstand shock standards. optimized through compare to the all totally
withstand shock loadings. control of aeration rate technologies & civil and
and duration.
loadings. Secondary meeting the latest no
62
clarifiers are
eliminated. outlet quality replaceme
There is flexibility in standards except nt cost of
adjusting reaction time Nutrients. spares for
and tank volume to
meet 25 years
variable loading. or more.
No odour problem. Operates
Very less personnel is totally in
required. Excess bio- absence
sludge is fully
stabilized.
In built nutrient
removal supervisio
system. Underwater n. Best in
parts are in Stainless class for
steel. nitrogen
and
phosphate
removal.
No
electricity
required
apart
from
sewage
transporta
tion.
Aesthetic
ally
appealing
and zero
foul odor
16 Demerits Obsolete Obsolete Power generation schemes Larger footprint and In case, virgin PVC It requires skill Very high capital Higher
technology. Latest technology, Latest have been implemented at power consumption as media is not used, manpower supervision, and O&M cost. area
plant may not
outlet quality norms outlet quality norms many locations in India but compare to latest perform as and when required. It requires skill required
technologies.
cannot be achieved. cannot be achieved. have a mixed performance Additional well. High power manpower for
consumption as
Large footprint. Large footprint. track record. There are only sludge stabilization and coarse supervision.
few locations where power bubble aeration is
Eutrophication is nutrient removal used Periodic cleaning
generated successfully. which reduces
resulting to high This treatment is required. oxygen and replacement
suspended solids. is due to less flow during Latest outlet quality transfer efficiency. of membranes.
63
Sensitive to initial years of STP, lesser norms cannot be Latest outlet quality High membrane
industrial waste quantum of organic solids achieved without norms cannot be replacement cost
(replacement
discharges. than expected, seasonal additional nutrient achieved without once
Mosquitoes and variations specially dilution removal & tertiary additional nutrient in every 6 years).
of sewage in monsoons,
other pest etc. treatment. removal & tertiary Fouling of
infestation. Odour Further, 30 -40% of the treatment. membrane.
resulting nuisance power generated is Separate Nutrient
64
65
As per the above it is observed that SBR process of sewage treatment is most
suitable in the light of following:
1.0 Treated sewage meets the effluent characteristics as per the standards set out by
Central Pollution Board without any separate tertiary treatment.
Recommended Values under
Parameter
the subproject
pH 5.5 to 9.0
Fecalcoliforms,
Less than 230
MPN/100 ml
2.0 The Power consumption is optimized through control on aeration rate and
duration thereby reducing cost of energy charges in SBR process.
3.0 Area of construction is less as secondary clarifiers are not required which is
great concern in the present scenario where land is precise in the urban centers.
4.0 There is flexibility in adjusting reaction time and tank volume to meet variable
loading which is primarily due to change in sewage flow during the day looking
to peak and off peak hours.
5.0 The plant does not have any odor problem for the surrounding areas. Thus no
nuisance to the resident of nearby areas due to operation of plant for next 30
years i.e., design period.
6.0 Very less personnel is required for operation and maintenance of plant and
therefore the cost of personnel is less.
7.0 In built nutrient removal system helps in removing the nutrients.
8.0 Due to underwater parts made of stainless steel the wear and tear is very less
and therefore the Operation and maintenance cost is also less.
66
5.4. Details of pipe alignment
Details of depth of excavation for proposed sewer network in Nasrullaganj
42.327 100.00
The table above gives the proposed depths of pipe laying. As can be seen, the designs
67
6. ASSESSMENT OF ANTICIPATED IMPACTS
6.1. Introduction
This Chapter identifies and discusses both positive and negative impacts associated with
the proposed Project and their mitigation measures. Based on (relevant portion from the
design tables of the DPR) the screening and field visits and parameters provided in
ESMF for Environment and social aspects, the Nasrullaganj sewerage sub project is
categorized as Ea and Sc. The anticipated impacts and corresponding mitigation measures
are discussed in Phases namely: design, construction, operation and decommissioning
Phases. Based on the magnitude and duration of the project activities and the
environmental attributes of the receiving environment presented in earlier chapter on
environmental setting, the nature, duration and extent of impact are assessed. Minor
project impacts have also been identified and basis for their insignificance has been
provided. Wherever relevant, the ESMP also addresses the minor impacts and provides
environmental mitigation or environmental enhancement measures.
68
going to have any impact on the STP
activities. Even the proposed STP which will
be surrounded by the boundary of height of
about 2.4 m and will not have any impact on
the transfer station. The proposed land in
total (including STP and transfer station) has
4 to 5 trees; however the land parcel for STP
has no tress. Hence no tree cutting is
expected.
STP construction works will be confined to
sites, and construction will include general
activities like excavation for foundation,
construction of foundations, columns, walls
and roof in cement concrete and masonry,
and fixing of mechanical and electrical
fixtures, etc.
Detail of construction impacts explained in
section 6.2.2
2. SPS 1 50m 100 m dia Influence area of SPS covers 100 m
dia diameter. The SPS is proposed at ward no.
2, Talai mohalla, near drain, Khasra No.79.
The SPS is proposed adjacent to a drain. The
total area of the Khasra is 1090 sqm out of
which the construction is restricted to 25
sqm which will be surrounded by 6m thick
green space and hence, there will be no
major impact of this activity. There are a few
shops and houses within the area of
influence, however, this impact will not be
on the structure of them and any other
impact will only be during the construction
period.
3. Sewer Network 1.0 m in each side of Construction activity: Earth work excavation
and Nallah sewer network will be undertaken by backhoe excavator and
Channelization include danger lighting at every 100 m., and
using hard barricades, while sewer laying
works will include laying pipes at required
gradient, fixing collars, elbows, tees, bends
and other fittings including conveying the
material to work spot and testing for water
69
tightness. Sufficient care will be taken while
laying so that existing utilities and cables are
not damaged and pipes are not thrown into
the trenches or dragged, but carefully laid in
the trenches. As trenches are a maximum of
2 m in the town area, there is no risk of
collapse of trenches or risk to surrounding
buildings. Once they are laid, pipes will be
joined as per specification and then tested for
any cracks of leakages. The maximum
working hours will be 8 hours daily, the total
duration of each stage depends on the soil
condition and other local features. About
60% of the excavated soil will be used for
refilling the trench after placing the pipe and
therefore residual soil after pipe laying and
refilling is not significant. This remaining
excavated soil shall be used for levelling of
ground (based on suitability) in and around
the town.
Excavation along the roads, hauling of
construction materials and operation of
equipment on-site may cause traffic
congestions. Narrow roads in the core/old
town area of Nasrullaganj are 3m wide.
However, potential impact is negative but
short term and reversible by mitigation
measures. Prior to the commencement of
work at every section, a specific traffic
management plan will be prepared by the
contractor and will be implemented to
minimize such impacts.
Ramps constructed by some of the residents
may be disturbed during construction,
however, due care will be taken while
designing and deciding the final alignment
of pipeline so as to minimise such incidents.
Presently it seems that ramps of
approximately 150 houses may need to be
disturbed during construction. Potential
70
impact is negative but reversible and short
term.
Detail of construction impacts explained in
section 6.2.2
4 HT Feeder Line 1.0 m in each side of The final alignment of HT feeder line is not
proposed feeder line finalized as yet; a rapid ESA of HT feeder
line shall be carried out by the DRBO
contractor after finalization of alignment.
Detail of construction impacts explained in
section 6.2.2
71
Construction of approximately 62.78 km long sewerage network including all required
trunk/ branch/ lateral sewer. Construction of STP
Construction of sewage pumping station
Potential Environmental Impacts: The environmental impact of the proposed project may
be categorized in two phases:
i. During the construction phase which would be temporary and short term;
ii. During the operation phase which would have long term effects
72
73
However, the emission of NOx, SO2 will be is not expected to cause any change in the
ambient air quality. During pipeline laying the following activities cause air pollution:
Emissions from equipment used for construction of the pipeline.
Emissions of dust during excavation of soil
During pipeline laying, air emissions are not expected to adversely impact ambient air
quality in and around project activity area. Due flat terrain good dispersion is available
dispersal of the pollutants and thereby and thereby the impacts due to NOx, SO2
emissions during the construction will be negligible.
Construction activities will take place across the whole project components that include
Sewerage Treatment Plant, lying of sewer pipe line and outfall. In general, the impact of
the construction will depend on;
The proximity of the construction activities to noise sensitive receivers (NSRs);
The specific heavy equipment deployed; and
The length of time over which the construction works are taken.
74
75
Effective noise management protocols would be implemented wherever applicable during
construction and operating phases of the life of this project. Besides this protocol
measures, construction work will be limited to day time periods, thus avoiding the night
time which is the most noise sensitive. The following measures should be treated as a part
of the project proposal which include:
locating noisy equipments as far as possible from NSRs;
orienting equipment with high directivity to emit noise away from NSRs;
switching off unnecessary or idle equipments;
fitting of noise mufflers to mobile equipments; and
Preventive maintenance of equipment to minimize noise emissions.
In the light of the prevailing low ambient noise levels in the area surrounding the project
sites, it is Inevitable that some noise disturbance will be experienced, particularly during
the construction of the sewer network. Such impacts, although temporary and therefore
reversible, are assessed to be negative and low to moderate significance.
76
Normally removal of vegetation and land clearing is associated with soil erosion,
however these issued are localized temporary effect and associated with construction
phase only. Excessive debris, trash or construction remnants (e.g. dirt piles) may create
problems related to drainage, unhygienic conditions and poor aesthetics. Solid wastes
generated from the construction activities are excess excavated earth (spoils), discarded
construction materials, cement bags, wood, steel, oils, fuels and other similar items.
Domestic solid wastes may also be generated from the workers‟ camp. Improper waste
management could cause odor and vermin problems, pollution and flow obstruction of
nearby watercourses and could negatively impact the landscape. If construction materials
are handled appropriately, it may affect minutely
The construction of STP facilities is not going to involve the large scale construction
activities; however, all the workers will be equipped with necessary personal protective
equipments (PPE) and will be trained for safety aspects to be followed during working
hours.
77
ecologically sensitive areas was made. The area does not have any flora and fauna
components which require any special attention from conservation point of view. There is
no environmental sensitive area within 10 km radius of the project.
With regard to sensitive aquatic areas and water bodies, there are none. It was also
observed that the major land use pattern of the area is residential, with limited
agricultural and no forest areas.
h) Traffic Congestion
Due to the excavation work which will take place on the main roads of the city, there will
be a disturbance in the traffic movement. People may suffer some inconvenience during
the morning and evening peak hours. Traffic disruption can be expected in busy areas
such as area around Main roads area due to transportation of material of construction.
Any excavation along the roads in these areas will inhibit traffic movement. Temporary
inconveniences caused by construction if the project is implemented in a timely manner.
However, the same interviewees felt that they had little confidence in the ability of the
agency to execute a project in an efficient manner. They had grievances with the long
duration of construction work.
78
i. Temporary flooding of adjacent areas due to accidental leakages/bursts and also
due to blockages and backlogging of lines.
ii. Water pollution and possibility of mixing with water supply line due to leakages/
overflows from the sewer lines
iii. Impairment of receiving water quality inefficient sewage treatment process
c) Noise quality
Improper handling and irregular maintenance of operating machines including pumps,
generators, air diffusers, etc may lead to increased noise pollution during operation activity.
a) Land Requirement
No Private land is required for the project, as construction of proposed infrastructure be
on government land. Details of land identified for the construction of proposed
infrastructure given below:
(i) The STP the land near Trenching Ground with Khasra No. 123 having an area of 2.0
hectares against a requirement of 0.5 Hectares and in possession of the ULB, is selected
,
(ii) The Sewage Pumping Station has been proposed at Khasra No.79, the land being
Government land.
The land required for STP and SPS belongs to the ULB/government and is vacant. The
portion of the land required for STP is not utilised under farming or any other purposes.
Moreover there would be no loss of community assets during the construction, as noticed
during site visits and interaction with the local people. Construction of all proposed
79
structures STP, SPS and pipelines etc will be undertaken on public land, as there will be
no agricultural or forest or community land requirement there are no adverse impacts
either on general or on any vulnerable group.
Construction of SPS may have a temporary negative impact on the nearby structures;
however, this is not a major impact since the construction is proposed on 25 sqm only.
The impact will only be during construction phase.
b) Impact on Livelihood
The excavation work may lead to road blockage and as a result the commercial
establishments and vendors may face some trouble in operating their business on daily
basis.On the basis of screening and site visits along the road stretches through which pipes
are likely to be laid reveal that there will be temporary disruption to on-going commercial
and vending activities. These temporary disruptions may result in loss of income during
construction period for certain days. Tentative estimation of loss has been calculated on the
basis of field visit along the roads, the exact estimation will be possible with the placement of
DRBO contractor. On the basis of approved design, join verification will be done to assess
exact figures and accordingly updation will be done in ESA.
In case temporary shifting of vendors with temporary structures is necessary, such shifting
will be undertaken on a weekly holiday, to avoid income loss on the day(s) of shifting. The
vendors will be assisted to shift and will be able to continue plying their trade during the
construction period at the alternative location. Only mobile vendors will be shifted to a
nearby location during the period of construction an alternative location for shifting will be
provided by the contactor. Only mobile vendors will be shifted to a nearby location
80
during the period of construction, an alternative location for shifting will be provided by
the ULB. Table 6-2 presents the key impacts and management measures.
Loss of income due no. of Total no. of such shops * assistance as per entitlement
to obstruction of lanes average no. of days matrix in ESMF
access to likely to Tentative number.of small
commercial be get Trader to be given livelihood
establishments affected- assistance= 145
owing to temporary 15 Tentative number of vendors
blocking of lanes. to be given livelihood
assistance(as per collectorate
rate) = 10@ no. of
days(average 7 days)
Impact on standing No such impact is seen as of Compensation as per support
crops now. However, this impact rate for district.
will be reassessed during
joint verification survey
81
Type of Impact Estimation Provision of Compensation
undertaken in construction
stage
The construction of civil works for which the required labour force, associated goods and
services cannot be fully supplied locally for a number of reasons such as worker
unavailability and lack of technical skills and capacity. In such cases, the labour force (total
or partial) would need to be brought in from outside the project area from nearby municipal
towns and villages and sometimes outside the state. This rapid migration of labour to the
project area may affect the project area negatively in the terms of additional burden on public
infrastructure such as local social and health services, utilities such as water and electricity,
housing and social dynamics and thus impact on local communities. Other related issues
could be increased risk of spread of communicable diseases, and increased rates of illicit
behaviour and crime. Some of the adverse environmental impacts are illegal waste disposal
sites, inappropriate Waste water discharges, camp related noise, access roads and land use
issues. Such adverse impacts may get amplified by local-level low capacity to manage and
absorb the incoming labor force, and specifically when civil works are carried out in, or near,
vulnerable communities and in other high-risk situations.
While the sub project ESIAs would require to assess such potential issues linked to
temporary project induced labour influx, the specific impacts can only be assessed once
the contractor is appointed and decides to outsource labour.
Some of the risk factors identified are (i) weak institutional capacity of the implementing
agency; (ii) many contractors without strong worker management and health and safety
policies; (iv) pre-existing social conflicts or tensions; (v) weak local law enforcement, and
82
(vi) prevalence of gender-based violence3 and social norms towards it in the community
(vii) local prevalence of child and forced labor. (Viii) perception of insecurity by the
local community due to illicit behavior or crimes including theft, physical assaults,
substance abuse, human trafficking etc.(ix) limited availability of affordable
accommodation and rents within Municipal area.
There are multiple and comprehensive Acts and Rules at both state and national level that
set out the provisions for appropriate working conditions and for good labour
management. However, multiplicity of laws and rules sometimes cause confusion in its
applicability in a specific context. Further in case of contracted workers and Primary
labor suppliers the enforcement weakens.
Hence, the contractor would require to develop labour management procedures and
mitigation measures in the CESMP before the start of works and monitor and update the
labour management Plan as necessary during the course of the project. MPUDC would
develop a separate training module with the help of technical partner to build the capacity
of PMU, PIU, Supervision Consultants and Contractors in preparation and execution of
this labour management Plan.
This Labor Management Plan would address specific activities that will be undertaken
to minimize the impact on the local community, including elements such as
Communication and awareness plan on national labour and women harassment laws and
its penal implications, leave provisions and other allowances for workers benefit,
Worker codes of conduct with respect to manual scavenging, engagement with local
residents, child labor, nondiscrimination, harassment of coworkers including
women and those belonging to SC and STs and other minority social groups.
Training programs on HIV/AIDS and other communicable diseases, etc.
Workers‟ Camp Management Plan addressing specific aspects of the establishment
and operation of workers‟ camps provided the ULB is unable to cater to the demand
for affordable housing for this additional workforce in terms of rentals, hostels,
apartments etc.
Compliant handling Mechanism for Nasrullaganj Sewerage Scheme.
The responsibility for managing these adverse impacts is being clearly reflected as a
contractual obligation of the Civil Works Contractor and Supervision Consultant, with
appropriate mechanisms for addressing non-compliance.
6.4. Conclusion
Consultations with relevant officials including concerned officials, Municipality office,
community, other sources and first-hand observations during the field visit no additional land
is required for the project, as land is available for construction of proposed STP and also
sewage construction will not result in fresh land acquisition. Also there are no squatters
83
and encroachers present in and around the proposed STP premises. Thus, given that there
is no land acquisition, there are no R&R issues related to land acquisition, including but
not limited to loss of property, resettlement, land regulations, etc. Sewer lines will pass
through various residential colonies of sewerage zone. Moreover there would be no loss
of community assets during the construction as noticed during field survey and
consultation with the local people. Loss of access in temporary manner temporary
shifting leading to loss of income of vendors, kiosks operating en-route would be
compensated by local mitigation measures as discussed later in the report. Based on the
overall secondary data analysis and field investigation, the proposed project is expected
to benefit the Nasrullaganj town, as the wastewater that currently flows untreated into the
Narmada river will be captured, treated and the remainder of the treated effluent will be
allowed to flow into the river. The likely beneficial impacts of the projects include:
Improvement in sewerage collection and treatment within the cities/towns
Prevention of storm drains carrying sanitary sullage or dry weather flow
Prevention of ground water and soil pollution due to infiltration of
untreated liquid waste
Prevention of discharge of untreated sewage into River Narmada
Improvement in water quality of River Narmada, a national resource
Improvement in environmental sanitation health and reduction in
associated health hazards within the cities/towns
Improvement in quality of life, human dignity and increased productivity
7.1. Background
84
and designing viable and sustainable mitigation and compensation plans. Extensive
public consultation meetings for the Nasrullaganj Sewerage Project took place while
undertaking ESA study. The main objective for the consultation process was to involve
the community at the very early stages so as to identify likely negative impacts and find
ways to minimize negative impacts and enhance positive impacts of the project.
Stakeholder meetings were held while preparing DPR. Several Public sensitization and
meetings were held within selected wards of the project area from 2016 to 2017 with the
help of respective local administration and the elected representatives. Key findings of
these meetings are presented in Table 7-2. The attendance lists and minutes of meetings
are presented in Appendix 5. During public meeting the participation of both men and
women was ensured. However, looking to the lack of participation of women, Focussed
discussions with females were also conducted.
85
7.3. Details of consultations
st
1 Stake Holders Meeting
Minutes of the meeting for the discussion held with the Officials of Nasrullaganj
st
Nagar Parishad (Municipality) on 1 June 2016:
Consultant representatives visited Nasrullaganj Nagar Parishad for kickoff meeting
and site visit for preparation of ESA report proposed subproject.
86
Following points were discussed during the meeting with ULB officials:
the initiative taken by the MPUDP for the preparation of ESA for
Chairman welcomed
Sewerage scheme
The need for the project was discussed with the Chairman of the Nagar Parishad.
to be directly being
Chairman and CMO discussed the problems in the Nasrullaganj related to Sewerage.
Sewage, as well as effluents from public toilets, etc. were found
discharged in storm water drains and finally to River Narmada.
The socio economic profile of the Nasrullaganj was explained by the Chairman.
There is an immediate need of improving the present sewerage works infrastructure in the
town. Chairman explained the problematic areas related to sewerage system.
Consultant noted down the problematic areas and present situation of the town and discussion
was held on the need.
representative of Nagar Parishad.
Supply Hours & Frequency, Water Tax, Staff for Water Works,
The present condition of Water Supply including Source, Distribution System, Zones
where water is supplied,
etc. was collected.
population, Ward Map and information
All the data related to the town like CDPs, Ward wise
about existing Water Supply Scheme was collected.
The chairman was of the view that the project shall be taken up at the earliest.
The main concern of the ULB was road restoration should be done immediately after
the pipe laying.
How the connection will be made with the properties.
Fiduciary gap in expenses on O&M and recovery from tariff was another major
concern.
nd
2 Stake Holders Meeting
The discussion on draft ESA held with the ULB Officials and Public of Nasrullaganj Nagar
th st
Parishad on 20 and 21 June 2016. Consultant representatives visited Nagar Parishad
(municipality) for presenting draft ESA report. Following table shows participation details:
nd
Table 7-1: Details of 2 Stake Holders Meeting
S. No. Date Venue Number of Participants
Total M F
1. 21-6-2016 Ward No. 02 16 13 3
87
Total 67 52 15
88
Table 7-2: Public Consultation Details
1 Ward 21-6-2016 Local The Sewerage Project The people welcomed the People were informed that
89
Charges shall be State Government's
imposed only after the decision
system starts
functioning
2 Ward 21-6-2016 Local The Project Background, The main suggestion of The people were informed
No. Residents, Environmental, Social, participants was: that :
06 And public traffic safety issue and Provision of Drain in Proper traffic signage
representative benefit from the project were Built-up Section to shall be provided for
of ward Total - explained to the eliminate the issue of speed limits.
Sprinkling of water will
The Consultants
17+ 19 Stakeholders. road side water-logging
Participants Team be done to minimize
informed that existing • For Safety of Local Dust Pollution
toilets will be connected to traffic and pedestrian in Barricading of
the sewer line proposed Built-up Zone, fencing excavated portions will
under this scheme. should be provided. be done
Road Side Water logging • Adequate provision for Danger signals will be
3 Ward 21-06- Local The Sewerage Project The main worries of The suggestion was
No. 2016 Residents, Background, Environmental, participants was: noted down and
What
11 And public Social, traffic safety issue included in ESMP.
about the
representative and benefit from the project The costing of road
recently built roads.
90
of ward Total - were explained to the They were of the view reconstruction is
17 Stakeholders. that the roads shall be incorporated in
Participants Whole ward is not having redone to their detailed project report.
sewer network. Existing original strength and People were informed
Household toilets mainly position about the safeguards
based on Septic tanks and
The excavation will
adverse effect of flowing
lead to disruption in
sewer into the open drains
of city. traffic and commuting
People were worried about
and therefore, work
access to their houses and shall be done in night.
work places including Peoples also
shops demanded for proper
traffic signage for
speed limits for
minimizing the
accident
4 Ward 20-5-2016 Local The Project Background, People welcomed the The concerns of the people
No. 12 Residents, Environmental, Social, project. The majority was were noted and measures
And public traffic safety issue and in favour of this project as and safeguards have been
representative benefit from the project were it intends to conserve included in ESMP. People
of ward Total - explained to the River. However, the were also informed about
17 Stakeholders. issues and concerns raised the possible safeguards
Participants are as under:
The tariff will be
exorbitant.
Excessive excavation
may be dangerous for
91
the foundation of the
Excavated portions
buildings
Traffic
during night.
may be
disturbed.
92
rd
3 Stakeholder meeting: In the month of April 2017 there were some modification done in the
th
DPR and accordingly ESA was revised and again public consultation were organized on 26
June 2017, as part of revised ESA study, especially in the core area and market area of the
proposed project.
th th
4 Stakeholder meeting held at different area of Nasrullaganj NP on 9 September 2016.
th
Table 7-3: Details of 4 Stakeholder meeting
S. No. Date Venue Number of Participants
Total M F
1. 26-4-2017 Ward No. 05 20 20 0
2. 26-4-2017 Ward No. 06 19 19 0
3. 26-4-2017 Main Market 120 7 5
Area
4 27-4-2017 Ward No. 6 13 0 13
93
The participants emphasized the provision of diversions and aligning the way in the
interest of community safety and environmental protection, repeatedly.
Sewer network alignment shall be decided in such a manner that no structure is
removed or demolished. However, in case it becomes necessary, special care should
be taken for structures to come in the alignment especially in case of removing or
shifting the sacred trees, temples, mosques and other places of cultural and historical
significance (by following the rituals and customs of community concerned).
Utilities disturbed, if any, during excavation shall be restored at the expense of the
contractor or be included in the cost of works and shall be restored as fast as possible.
Grievance Redress mechanism shall be set up and a quick response to any grievance
shall be appreciated.
Compensations, if any, shall be decided and released to the affected person, as soon as
possible.
Parking of vehicles will be a major problem during construction, hence, the excavation
works shall be done in such phases that the problem is minimized. It will be better if
the excavation in a particular stretch say 250 m is done, pipe line laid and road is
restored (may be not to its original but at least temporarily) and then work in next 250
m is started. This will also reduce the issues related to access to shops.
Residents have constructed ramps over the drains to have direct access to road/
pathway and avoid possible accident (falling in drain). After the sewers are laid, this is
possible that some of the drains are closed. This will add to the available RoW.
94
95
8. GRIEVANCE REDRESSAL MECHANISM
In order to redress the grievance raised by any affected person during project construction /
implementation, project level Grievance Redress Committee (GRC) through a government order
shall be established as a grievance redress mechanism for the project. In addition to the project
level GRC, redress of grievances relating to Land Acquisition will be as per the RTFCTLARR
Act, 2013.
The Project level GRC shall be constituted with five persons including a female member.
One from the ULB / Executing Agency
Any One Elected Representative (Local Project Area)--( preferably female)
A person who is publicly known and accepted by the locals (in the project area) to
speak on their behalf (to be identified by the Elected Representatives of the ULB)
Community Development officer from PIU
ULB level community organizer or Chief Municipal Officer's representative
Affected person(s) shall file its grievance with the respective ULB, PIU or Contractor. The affected
may register his or her grievance personally or on phone disclosing his or her identity and address.
The affected will have to clarify the area of grievance. The grievances related to construction
activities affecting the livelihood or loss of property/utility or restriction of access and the
grievances regarding the quality of service during operation and maintenance period will only be
entertained by the GRC. Grievances related to corruption will only be dealt under the laws of the
land.
The grievance shall be addressed within 48 hours. However, if there is any technical issue, the
aggrieved will be informed accordingly.
The Design Engineer in-charge from PIU for the project shall be the nodal officer for the
grievance redressal.
The meeting of the committee shall be convened as and when necessary and at such place or places
as it considers appropriate; and conduct the proceedings in an informal manner as he / she considers
appropriate with the object to bring an amicable settlement between the aggrieved parties.
A structured approach will be followed for redressing grievances. The grievance will be
addressed to the Project Manager of the concerned PIU but it will be the duty of the engineer of
the PIU on site and /or the Public Relations Officer at PIU to take orders from the Project
Manager and take immediate curative action. In case the grievance is not addressed within 48
hours, the grievance shall be sent to GRC.
The aggrieved project affected person / family may formally approach the GRC in the first stage and
submits their appeal along with any supporting documents / information. The grievance committee
shall accordingly convene a meeting (either based on a case to case basis or a clustered approach, but
without unreasonable delay). The committee shall look into the grievances and information provided
and based on this, propose ways to resolve the issues. Based on the final
96
decision, the proceedings of the GRC will be documented and executed by the ULB / Executing
agency through contractor.
If still not satisfied with the resolution provided by the GRC, the complainants can then appeal to
the grievance redress mechanisms available on CM helpline; there are two ways to access the
CM helpline
(a) The complaint will be directly registered through toll free no. “181”
(b) The complaint will be registered online by filling a prescribed format on
cmhelpline.mp.gov.in/schemes.html
Note: The MPUDC shall be linked with the CM helpline.
97
9. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN
9.1. Overview
The ESMP presented in this Chapter summarizes the key impact elements identified and
the remedial measures, the actions to be taken by various parties and the monitoring
activities. An indication of the time scale for implementation and cost involved is also
provided. The ESMP can be further updated during implementation with documented
procedures and guidelines for work practices so as to be responsive to the situations that
various Contract Parties will encounter. The Parties should formulate procedures and
practices and maintain records. The implementation of the ESMP should be done within
the provisions of the law, requirements of ESMF for MPUDC and for the ultimate benefit
of the people in the Project area. The effectiveness of the ESMP shall be monitored and
assessed through regular monitoring, formal inspections and at the end of the Project
when an overall audit of the works shall be carried out.
The management plan further identifies what measures should be taken in the event of
emergencies or incidents during the operation of the facilities. During construction phase
social impact on Loss of temporary Livelihood and temporary loss of income due to non-
access to shops due to excavation shall be assessed and accordingly the social management
plan be updated in line with the ESMF for MPUDP. The Plan is outlined in Table 9.1
overleaf while the estimated cost of the ESMP is presented in Table 8.2 thereafter.
98
Table 9-1: Environmental and Social Management Plan (ESMP)
99
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
Sludge Disposal of sludge leading Permanent Efficient methods for Sludge DRBO
disposal to contamination of land and dewatering, drying and
water. stabilizing of effluent sludge
with minimum land
requirement, shall be
adopted.
Provision shall be made for
Sludge yard at STP (for seven
days capacity) as sludge drying
bed as well as storage of sludge.
The digested sludge shall be
transported every seventh day to
the regional landfill proposed
under ISWM (Bhopal Cluster),
at Aadampur Chhaoni at the
100
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
outskirts of Bhopal.
Provision Accidents leading to Permanent Ensure adequate provision of DRBO
for safety injury or death of Handrails on both sides of
of workers workers walkways close to deeper tanks
and safe ( Fall of workers from and STPs;
operation of Height, Fall into deep All electric switches ( including
STPs water tanks, Short unit specific on-off switches
Circuiting) installed at respective units ) and
Accidental slip, trip and fall panels should have adequate
in walk ways or work areas protection from rain water to
Fire prevent short circuiting
Exposure to toxic gas such Proper earthling with installation
as chlorine of earth circuit breakers shall be
made
Walk ways designs shall be made
with proper slope to avoid
accumulation of rain water.
Material handling and storage
shall be so designed that walk
way surface remains free from
wet or oil surface situation to
prevent slips, trip or fall
accidents.
Prepare emergency preparedness
plan including identification of
assembly area in case of fire.
101
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
Sewage Pumping of Noise and odour nuisance to Permanent Ensure that the noise standards PMU and DRBO
Pumping sewage from surrounding areas. must be met at sewage pumping contractor
Station District SPS station.
to STP Ensure that the pumping station is
provided with a noise barrier and
adequate green belt around the
pumping station
Use of less noise generating
equipment with regular
maintenance.
Solid waste should not be kept for
more than 24 hours
Sewerage Accidental Due to accidental burst or Temporary Designing sewers with adequate DRBO
102
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
103
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
104
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
105
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
106
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
107
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
108
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
109
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
110
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
111
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
112
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
113
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
114
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
C. Operation Phase
Sewer line Leakage/ Water pollution and possibility Permanent There is a temporary concern of PMU
overflows of mixing with water supply leakages and overflows leading to O & M
line flooding of adjacent areas in the town contractor
(screening checklist). However this
can be mitigated and managed by:
115
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
116
Activity Potential Negative Duration Mitigation Measures Responsible Agency
Impact/Concern of Impact
117
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
Design and Provision for Proper drainage Yes (not specific but DPR for Sewerage system The proposed DPR
Development accidental arrangements to included as a part of includes these activities
leakages / prevent water associated
bursts in SPS stagnation/ construction
flooding in SPS activity)
site area
Location of Appropriate Yes DPR for Sewerage system The proposed SPS will be
SPS siting, and indoor which will prevent
enclosing within noise and enclosed nature
building to reduce and appropriate cleaning
noise and odour and maintenance will
nuisance to prevent odour nuisance
surrounding area
Joint Cost in DPR for Design
Verification Review
and Update
ESA and
ESMP
Construction Excavation, Review of Yes DPR for Sewerage system The proposed DPR
Cutting and existing includes these activities
filling infrastructure,
operations shoring trenches,
reinstatement/
resurfacing
Damage Proper reviewing Yes DPR for Sewerage system The proposed DPR
public utilities of existing includes these activities
118
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
drawing s of
utilities,
informing concern
authorities and
reinstatement of
public utilities
Dust Water sprinkling No Water tanker: Rs. According to DPR 4 Km
generation on excavated Approximately stretch in each zone will be
material to Rs. 5,04,000 /- completed in 2 years. This
suppress dust and Top cover for dumper means approximately 75
provision of top truck: Rs. 33750/- m will be covered per day.
cover when 750 L of water will be
transported consumed for 75 m using
through vehicles sprinkler average 2 times a
day Labour cost- Rs.
150/day Rs. 300/tanker +
Rs150/labourer = Rs. 450
Per meter cost = Rs.
450/75m = Rs 6/- Total
cost for 42 Km= Rs.
2,52,000 Keeping a 2 day
margin for construction
and reinstatement of the
site 2x252000= Rs.
504000/-
119
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
Top cover: Approximately
30 Sqm of top cover may
require for each vehicle.
Assuming 5 such vehicle
involved in transporting
excess soil to dumping
location (considering
construction schedule and
max Excavated earth
disposal). Hence 5 trucks*
required top cover 30
Sqm* Cost of Tripol cover
at Rs. 75/ Sqm
Noise and Usage of sound No. Rs. 1,62,750/- As per the schedule, the
vibrations barriers or sheets. construction in 1 zone
each has to be executed in
24 months For providing
sound barriers like GI
sheets, 4 Km out of 42 Km
of stretch of sensitive
zones in sewer work is
considered assuming
excavation, construction
and backfilling activity
will take place
120
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
simultaneously at different
stretches.
Considering 302 GI sheet
of 3‟x 8‟ would cover 75m
length (both sides) of
construction activity daily.
(150 sheets are needed of
for one side of 150 m
stretch, so for 2 sides 300
sheets and 2 more sheets to
enclose one open side of
the barricading; 150 m is
taken as a safer option as it
will not be possible to shift
the barrier to another site
same day) Hence 302
sheets* Cost of GI sheet
Rs.1000 per sheet (Rs.70-
100 per Kg)* labour cost (
four labours at avg. rate of
Rs. 180 per day) =
And for 4 Kms =
Rs. 1,62,750/-
Temporary Alternate traffic Yes DPR for Sewerage system
flooding or , re-routing,
water logging Ensuring storage
121
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
of excavated soil
material on the
higher lying areas
Increased Traffic re-routing Yes DPR for Sewerage system
traffic
inconvenience
Safety Putting fences or No Rs. 40,00,000 The cost of fencing the
hazards to other barricades to excavated trenches is
workers and demarcate the assumed @ Rs 200 per
residents area meter. The total length at
which the fencing may be
needed is assumed to be
4000 m
Labour Health Sanitation No Cost of construction of pit and The labour camps can be
influx hazards and toilet building & cleaning divided into 1camps for the
approximately Rs. 7,98,000.00 project, for appropriate
management nuisance due
management and maintenance
and Labour to absence of work. So per day camp will
camps (if facility for have around 100 labourers
adopted) sanitation or The approximate cost of
solid waste one toilet unit in a camp
management would be around Rs
7,50,000.
122
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
pits X 2 camps X 3 times
cleaning the cost will come
as Rs.48000/-.
123
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
Total EMP cost 15,77,400
124
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
Loss of Joint survey of PIU and contractor will be done before NNP/DRBO Through
Income implementation to assess the exact number of loss of contactor & out the No additional cost
Livelihood income livelihood due excavation in narrow lanes,the PIU construction
shops not get accessible, when the alignment of pipes period As per current
will be finalized by the DRBO contractor collectorate rate (skilled
Approval of updated ESA based on joint survey with labour as per 01.01.18
final design from MPUDC daily wage rate -INR
All compensations (as per entitlement matrix in 324.42)
ESMF)to be disbursed before start of excavation in the
3,75,000
particular stretch.
Tentative number.ofsmall Trader to be given
livelihood assistance(as per entitlement matrix)= 145
Tentative number of vendors to be given livelihood
assistance(as per collectorate rate) = 20 +15 @ no. of
days (average 7 days)
Impacts to Joint survey of PIU and contractor will be done before NNP/ before as per support price by
trees and implementation to assess the exact impact on trees and DRBO construction fixed at district level
plants plant along the final sewer network. contractor, phase
Approval of updated ESA based on joint survey from PIU
MPUDC
Plantation and up keeping of minimum 500 trees by
the contractor (included in Scope of work of
contractor)
125
Phase Component Mitigation Cost included in Cost in Rupees Remarks
of EMP measure the DPR (or Details if provided in
(Yes/no/not clear) DPR)
Unidentified Unforeseen impacts encountered during NNP/ Through 5,00,000
Impacts implementation will be addressed in accordance with DRBO out
the principles of the policy contractor, construction
PIU phase
Total SMP cost INR18,75,000
126
9.2. Monitoring and Evaluation
Monitoring is an important tool in establishing the success or failure of a project in regards to
compliance to environmental safeguards. Evaluation is also important in assessing the
achievement of the mitigation measures set out in the Environmental Management Plan,
performance and efficiency of the project in regards to ESMP. Monitoring and evaluation
process will involve the assessment of the following benchmarks:
The implementation process of guidelines stipulated in the ESMP
Evaluate impact of the project to the environment and social setting of
Nasrullaganj Town
Monitoring of the involvement of the community through public consultations in
decision makings and the implementation of the project
The ESMP will guide the environmentally sound construction of the subproject and ensure
efficient lines of communication between MPUDC, project management unit (PMU), project
implementing unit (PIU), consultants and contractors. The ESMP will (i) ensure that the
activities are undertaken in a responsible non-detrimental manner; (i) provide a pro-active,
feasible and practical working tool to enable the measurement and monitoring of
environmental performance on site; (ii) guide and control the implementation of findings and
recommendations of the environmental assessment conducted for the subproject; (iii) detail
specific actions deemed necessary to assist in mitigating the environmental impact of the
subproject; and (iv) ensure that safety recommendations are complied with. The ESMP
includes a monitoring program to measure the environmental condition and effectiveness of
implementation of the mitigation measures. It will include observations on- and off-site,
document checks, and interviews with workers and beneficiaries.
Construction stage:
127
(i) Facilitate and ensure that all necessary environmental clearances/permissions,
including that of contractor‟s are in place prior to start of construction
(ii) Organize an induction course for the training of contractors, preparing them on
ESMP implementation, environmental monitoring, and on taking immediate
action to remedy unexpected adverse impacts or ineffective mitigation measures
found during the course of implementation.
(iii) provide oversight on environmental and social management aspects of subproject
and ensure ESMP is implemented by PIU and contractor.
(iv) Supervise and provide guidance to the PIU to properly carry out the
environmental monitoring as per the ESMP
(v) Oversee grievance redress mechanism to address any grievances brought about in
a timely manner; ensure that records are properly maintained
(vi) Consolidate monthly environmental and social monitoring reports from PIU and
submit semi-annual monitoring reports to WB.
(vii) Oversee site closures to ensure that all work / facility sites are restored properly
prior to issuing work completion certificate to the contractor
Operation stage:
(i) Ensure and consent for operation (CFO) is obtained from MPPCB for STP prior
to start of operation
PIU Responsibilities.
PIU will be headed by a Project Manager and supported by PMC. An Assistant Project
Manager of PIU will be given additional responsibilities of safeguard tasks. Assistant
Project Manager will be supported by PMC Environmental Specialist and Environmental
Coordinator. Key tasks and responsibilities of the Assistant Project Manager for this
subproject include the following:
(i) Provide necessary support to PIU and Nagar Parishads in obtaining permission
from MPPCB; liaison with PMU and regulatory agencies
(ii) Oversee day-to-day implementation of ESMPs by contractors, including
compliance with all government rules and regulations, take necessary action for
obtaining rights of way
(iii) Oversee environmental monitoring by contractors
(iv) Take corrective actions when necessary to ensure no environmental impacts
(v) Submit monthly environmental monitoring reports to PMU
(vi) Conduct continuous public consultation and awareness
(vii) Address any grievances brought about through the grievance redress mechanism
in a timely manner as per the EMP
Contractor’s responsibilities.
Bidding stage:
(i) Understand the ESMP requirements and allocate necessary resources (budget, staff, etc.,)
(ii) Understand the regulatory compliance requirements related to labour welfare, safety,
environment etc.,
128
Design stage:
(i) Review the ESA Report including the screening checklist, category and the ESMP, and
conduct site visits to understand the environmental sensitivity of the project sites.
(ii) Update the screening checklist, confirm the category, and update/revise the ESA Report
of the project reflecting the changes /amendments /additions that are effected in the
project during the detailed design
(iii) Update / revise and finalize the ESMP
(iv) Provide all necessary technical assistance to PIU / ULB in obtaining regulatory
clearances/approvals.
(v) Ensure that all design-related measures of the ESMP, and conditions, if any, of
government regulatory agencies (like MPPCB consent conditions) are duly included in
the final designs.
(vi) The contractor will be required to submit to PMU, for review and approval, a Contractor
environmental and Social Management plan (C-ESMP) including (i) proposed
sites/locations for construction work camps, storage areas, hauling roads, lay down areas,
disposal areas for solid and hazardous wastes; (ii) specific mitigation measures following
the approved ESMP; (iii) monitoring program as per C-ESMP such as labour
management plan, social impact management; and (iv) budget for C-ESMP
implementation. No works are allowed to commence prior to approval of C-ESMP.
(vii) Prepare and submit:
a. Construction waste management (CWM) plan
b. Traffic management (TM) plan
c. Emergency preparedness plan
Construction stage:
(i) Ensure that all regulatory clearances (both project related and contractor related) are in
place before start of the construction work.
(ii) Mobilize EHS personnel prior to start of work
(iii) Confirm with PIU availability of rights of way at all project sites prior to start of work.
(iv) Implement the mitigation measures as per the ESMP including CWM & TM Plans
(v) Follow the ESMP measures/guidelines for establishment of temporary construction
camps, construction waste disposal sites, and material borrow areas, etc.,
(vi) Implement ESMP and ensure compliance with all the mitigation and enhancement
measures
(vii) Conduct environmental monitoring (air, noise, water etc.,) as per the ESMP
(viii) Undertake immediate action as suggested by PIU / PMU / PMC to remedy unexpected
adverse impacts or ineffective mitigation measures found during the course of
implementation
(ix) Submit monthly compliance reports on ESMP implementation
(x) Act promptly on public complaints and grievances related to construction work and
redress in a timely manner in coordination with PIU
(xi) Comply with applicable government rules and regulations
129
Operation stage:
(i) Obtain CFO from MPPCB in coordination with the ULB, and comply with MPPCB
conditions, if any, during the operation phase
(ii) Implement the operation phase ESMP including the monitoring plan
(iii) Submit quarterly ESMP implementation report
130
Table 9-3: Environmental and Social Monitoring Plan
monitoring
agency/Lab
PM10 μg /m3, Two location Twice a Contractor PMU and
PM2.5 μg/m3, SO2, in the town year through PMC
Construction
NOX, CO approved
monitoring
agency/Lab
Rainfall, humidity, USEPA's At STP site Once in Contractor PMU and
Wind Speed, Wind Meteorological
Applications
every season through PMC
direction, Monitoring approved
Noise
131
Env. And Stage Institutional Responsibilities
Social Parameter Standards/Me Locations Frequency Implementation Supervision
Component thods
Rainfall, humidity, USEPA's One location Once in a Contractor PMU and
Wind Speed, Wind Meteorological within City year through PMC
direction, Monitoring approved
operation
132
Env. And Stage Institutional Responsibilities
Social Parameter Standards/Me Locations Frequency Implementation Supervision
Component thods
Physical Parameter: Consider the Sewer Once in Contractor PMU and
Texture, Grain Size, following Construction every season through PMC
Gravel, Sand, Silt, methods: Sites and SPS approved
Clay; Chemical IS-2720 monitoring
Soil
133
Compliance with National Campsite As per Contractor Supervision
national Labour Labour Laws CESMP, Consultant,
Laws on manual OHS Quarterly District
scavenging, guidelines Reports Labour
engagement with local Department
residents, child labor,
and PIU.
nondiscrimination,
harassment of
coworkers including
women and those
belonging to SC and
STs and other
minority social groups
construction
etc...
Labour provisions
Labour
at Camp site
Awareness and
Training for
Labour on Laws,
provisions, penal
implications,
workers benefits,
Occupational
health and safety
measures and
communicable
diseases.
134
Table 9-4: Cost of Environmental Monitoring Plan
Item Location Season Year Total no. of samples Unit Cost Total Cost
( One before start of
construction)
Environment Monitoring during Construction Stage
Air quality Monitoring 3 3 2 18 10,000.00 180,000.00
Metrological data 1 3 2 6 8,000.00 48,000.00
Noise / vibration 3 3 2 18 8,000.00 1,44,000.00
Soil analysis 3 2 2 12 5,500.00 66,000.00
Waste Water 5 3 2 30 10,000.00 3,00,000.00
Sub total 7,38,000.00
Environment Monitoring Cost (Operation Stage)
Air quality Monitoring 2 1 10 20 10,000.00 2,00,000.00
Metrological data 1 1 10 10 8,000.00 80,000.00
Noise / vibration 2 1 10 20 8,000.00 1,60,000.00
Soil analysis 2 2 10 40 5,500.00 2,20,000.00
Water Quality 5 2 10 100 10,000.00 10,00,000.00
Sub-Total 16,60,000.00
TOTAL for Environmental Monitoring 23,98,000
Total cost for Environment Management Plan 15,77,400
Total Cost of SMP 18,75,000
Total Cost of EMP + SMP+ Monitoring 58,50,400
No land acquisition and R&R is anticipated. In case of Temporary impact on structures or loss of income due to construction
activities if any is identified during implementation phase same shall be assessed through joint verification between PIU, ULB and
contractor representatives and shall be managed as per the ESMP. The PIU and MPUDC shall monitor the implementation of ESMP
and track indicators for IEC activities, grievance redressal, participation of women, scheduled Tribes and other vulnerable people.
Quarterly report shall be prepared.
135
9.3. Project Implementation and Monitoring Agencies
The Urban Development and Housing Department (UDHD) of Government of
Madhya Pradesh (Go MP) will be the Executing Agency for MPUDP, responsible for
management, coordination and execution of all investment program activities.
Implementing Agency will be the Madhya Pradesh Urban Development Company
(MPUDC) of Go MP, which will implement this program via a Project Management
Unit (PMU) at Bhopal, and Project Implementation Units (PIUs) at project towns.
PMU will appoint contractors to build infrastructure and PIUs will coordinate the
construction. PMU and PIUs will be assisted by Program Management Consultants
(PMC). Table 8.5 presents the organizational roles mapped for this subproject.
136
Level Organization Role
loss of livelihood etc that may come up during project
implementation and
Implementation, supervision and progress monitoring of
all Community Awareness and Participation activities
State and Project Assist PIU in the implementation and supervision of
Town Management Environment and Social Safeguards
Consultants Informing the PIU and PMU, if the contractor is not
following the policies stated in Chapter legal
framework.
Assist PIU in evaluating R&R cases, if any, and assess
the loss incurred
Assist PIU in making a structured programme with
respect to the implementation of the safeguards
State Panel of Will help MPUDC in detailed ESAs and preparation of
Consultants ESMP, RAPs etc.
District District Collector Transfer of Government Lands, Grievance Redress, if
Level (Revenue) any.
City level Council Overall monitoring of ESA execution
In case of any grievance, bring it to the notice of
appropriate authority through Mayor/Chairman /
Commissioner/ Chief Municipal Officer
ULB Support in Implementation of safeguards
Assistance in obtaining necessary government approvals
and orders for implementation of project
Implementation, supervision and progress monitoring of
reforms consolidation activities
Implementation, supervision and progress monitoring of
town planning activities
Take part in the Implementation of all Community
Awareness and Participation activities
Maintain account with provisional sums for R&R
activities
ULB shall carry out the social outreach and necessary
Information, Education and Communication (IEC)
activities to ensure adequate social acceptability through
citizen participation, community engagement and will set
up a mechanism for consumer grievance redress and
attend to consumer complaints in a timely manner. It shall
also obtain timely feedback of citizens on the services
provided and keep updated MPUDC from time to time
and take due care of needs of the urban poor and
minorities.
137
10. TRIBAL VULNERABILITY IDENTIFICATION AND ASSESSMENT
Scheduled areas are autonomous areas within a state, administered federally, usually populated by a
predominant Scheduled Tribe.
138
10.3. Public Consultation
During the entire planning phase, an effort has also been made to help people
understand the positive impacts and benefits from the project for them in terms of,
reduction in the sewer disposal problems, minimization of health risks through
provisions of sewerage scheme,. The process has helped in building confidence
amongst the residents of different wards of Nasrullaganj including SC and STs and
mainstreamed them in the process and making them partners in the project. For
consultation the wards selected on the basis of highest population of SC/ST in NNP.
10.3.2. Interview/Meetings
An enquiry was made with concerned department officials/representatives, running
different social and economic welfare schemes for Tribal groups. Information was
gathered about socioeconomic, religious and culture status from officials. During
discussion with officials it was found that tribal people mainly migrated from rural to
urban areas for their livelihood and for education. They do not reflect primitive
characters (like living in groups, culture and dialect).
Free prior informed consultations during design finalization stage and construction
stage will be carried out at two levels (i) consultation with communities for laying the
lateral pipes, collection chambers and connection to toilets, (ii) for participation in
capacity building and awareness generation activities for mainstreaming. The detailed
plan will be chalked out by PMU and PIU once the DRBO contractor is onboard. The
awareness programme will be held through separate NGO.
139
11. CONCLUSION AND RECOMMENDATIONS
The Environmental Social Assessment (ESA) Study was carried out based on field
assessments and public consultations with the community who are likely to benefit or to be
affected by the proposed Project and the Proponent in compliance with the agreed ESMF
for MPUDP, World Bank safeguard policies and EIA Notification 2006 of GoI. The
project report of the proposed sub-project for Nasrullaganj City after environment and
social analysis concludes that the project have overall positive benefits on the life and
environment of the people. No land acquisition or livelihood losses are expected due to the
project.
The sewerage network will provide improved environmental conditions due to the contained
handling of wastes, leading to improved public health conditions and will likely reduce the
average medical expenses of the residents in the project areas. Because of the sewer line
connection, all the waste water will be collected and directed to treatment plant, which only
after treatment will be disposed off to the river, hence decreasing the pollutant load in the
river. Connection to sewer lines will enhance the aesthetic value of the area, as there will be
more cleanliness and no wastewater discharge to open area. This will also lead to appreciation
in the property value. This will eventually lead to increase in standard of living of the people in
the project site.
There are no environmentally sensitive areas (like forest, sanctuaries etc.) in or near sub-
project area. Also there are no archeological and historical protected areas/ sites within or
near the town. No land acquisition is expected nor is any permanent adverse impacts on
assets and livelihood anticipated, hence no RAP is required as per ESMF. Only minor
damage to road side properties and loss of income for certain days and locations during
construction phase may be identified. Such impacts shall be assessed by DRBO contractor
and this ESA and SMP will be updated and approved by MPUDC and World Bank. In
Project area, no indigenous people are identified meeting the requirement of IPMF, so no
separate IPP is required. Hence the impact identified are mostly related to construction and
operation phase.
The subproject is unlikely to cause significant adverse impacts because: (i) most of the
individual components involve straightforward construction and operation, so impacts will
be mainly localized; (ii) in most cases the predicted impacts are likely to be associated
with the construction process and are produced because the process is invasive, involving
excavation, obstruction at specific construction locations, and earth movements; and (iii)
being located mainly in the already constructed facilities and built-up area will not cause
direct impact on terrestrial biodiversity values. The potential adverse impacts that are
associated with design, construction, and operation can be mitigated to standard levels
without difficulty through proper engineering design and the incorporation or application
of mitigation measures and procedures as given in ESMP.
140
Appendix 2: 2(A)Screening Checklist of Nasrullaganj Sewerage Project
7. Scheduled Areas No
141
Socio-Cultural- Economic activities
15. (religious/heritage/ cultural sites, No
tourist interests, etc.)
142
in the Environmental
Management Plan section.
143
Sr. Components Yes No Details
No
Number of household to be
6 None Nil
displaced?
144
Sr. Components Yes No Details
No
Population to be benefitted
145
Sr. Components Yes No Details
No
146
Sr. Components Yes No Details
No
147
Based on the Social screening activity and the categorization of potential sub-projects of the
MPUDP- ESMF, the present sub project of Sewerage work in Nasrullaganj town falls under
low impact category since no significant issues arise from the land to be acquired for Sewage
treatment plant and pumping station. In view of the above, these sub project would require
preparation of an Environmental and Social Assessment, as part of the DPR, and
implementation of Generic Safeguard Management Plan (SMP), relevant to the project.
On the other hand based on the Environmental Screening activity, the propose dsub project
falls under high impact category.
148
2 (B): Criteria for Categorization
5
It should be noted that this categorization refers to the categorization of subprojects done for MPUDP,
and should not be confused with the classification of overall Projects given in OP4.01 of the World Bank. As
per safeguard policies of the World Bank, MPUDP has been categorized as a Category A project.
149
Social Categorisation of Subprojects
During the screening process the social risks will be assessed through the screening
formats submitted by the borrower along with the loan application. Screening formats
are given in Appendix and screening checklist for project towns are provided in
Volume-II. Based on the screening, the social category of the project is determined and
necessary SIA and related RAP/ ARAP as applicable shall be prepared. Based on the
magnitude of impact to the Project Affected Persons(PAPs) through screening of
6
projects, projects have been categorised as either Sa, Sb or Sc outlined in Table below.
Categorization of Subprojects
Management
Levelofissues
measures
Sa significant SIA and RAP 1. If it involves acquisition of private land or
adverse impacts permanent loss of private assets and livelihood
expected 2. If it involves physical displacementof200 and
more PAPs are affected.
Sb Moderate SIA and 1. if the affected people are not physically
adverse social Abbreviated displaced and less than 10 percent of their
impacts productive
expected RAP. 2. if fewer than 200 people are displaced,
No private land acquisition or no impacts to
Sc No social issues Social Screening PAPs
Expected hence Report Construction stage impacts on assets near ROW
Socially benign
The social categorization will be done based on the social screening information
provided by the ULB. However, based on the outcome of Social impact assessment,
the category will be revisited at the time of appraisal of each subproject.
It should be noted that this categorization refers to the categorization of subprojects developed for
MPUDP, and should not be confused with the classification of overall Projects.
150