Professional Documents
Culture Documents
Risk Assessment Sheets-Sop
Risk Assessment Sheets-Sop
Risk Assessment Sheets-Sop
SHEETS
Following are the work activities that are already analyzed and risk calculated. The SM NIRAMAN
INFRASTRUCTURE PVT.LTD s operational control procedures and expertise required are mentioned in risk
assessment sheets
No. Description Remark
1 Buffing with sand grinder
2 Cable pulling – Horizontal
3 Electrical installation – up to 415v
Excavation – Manual
Excavation - Mechanical
4 Fire on site
5 Fixing of anchor fasteners
6 Flame cutting
7 Installation of bus-duct in electrical shaft
8 Manual handling
9 Mechanical sheet cutting
10 Mechanical sheet folding
13 Office work
15 Setting up site offices
18 Site access
19 Storage and use of HFL
20 Storage of materials on site
21 Temporary electric connection
22 Thickness maintaining operation
23 Transportation of electric panels
24 Use of chemicals
25 Use of disc cutters and wheels
26 Use of hand tools
27 Use of portable pipe threading machines
29 Use of tower crane
31 Veneer cutting
32 Welding
33 Working in confined space
34 Work on occupied premises
35 Work with hand held portable machines
36 Working adjacent to others
37 Working in energized area
38 Working in hot climate & high humidity
39 Working on ladders
40 Working on shearing machine
41 Working with sizing machine
42 Working with vertical drilling machines
COMMISSIONING ACTIVITIES????
USE OF ORDINARY CRANES, HYDRA AND
OTHER LIFTING TOOLS AND TACKLES????
ELECTRICAL AND INSTRUMENTATION
WORK???
USE OF PLATE ROLLING MACHINES????
Note:
An SMN statement must be made by the section in-charge and route, manpower and equipment requirement will be
carefully planned. Safe access means and fall protection arrangements must be planned and arranged before start
of work Valid certificates for winches or any other mechanical equipment should be obtained.
CONTROLS TO BE EMPLOYED:
1 A site specific assessment should be made in conjunction with the site HSE representative and with the
additional control measures
2 Personal protective equipment must be established.
3 Good communication system must be established between different levels
4 A brakeman is to be present all the time near the cable drum to prevent over-run of the drum
5 Cable socks must be used to fasten the cable to the winch book
6 As far as reasonably practicable, manual handling of cable drums shall be stopped from rolling by choking or by
wedges
7 Cable drums must be stored / handled as per manufacturer’s instructions.
8 Empty cable drums to be disposed / scrapped as per manufacturer instructions. It should never be used as a
means of access or egress/work platform.
9 Temporary ties should be provided at every two meters in vertical position the end of cable should be tied to an
rigid structure at the end of each shift
10 Ensure cable jack is placed on firm ground and the area around should be barricaded. A watcher should be
appointed
PPE to be used:
Safety shoes; Reflective Jacket; Safety Helmet; Safety harnesses; Hand gloves
Managerial / Supervisory input:
Possibility of temporary exposure to live electric cables (for lighting, etc.) must be checked. This is a critical activity
and must be closely monitored for any deviations in required measures/controls by the Supervisor on adequate
measures to be taken for avoiding it.
Training:
All the technicians shall be trained on proper use of the machine tool by the concerned supervisor. They will also be
trained on guarding, earthing and usage of PPE by HSE representative. Any other training may be arranged based
on site requirements.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-charge
or his representative shall sign it before carrying out the activity on site.
Controls to be employed:
1. Written information and instructions (method statement) will be required before starting work with complex
systems.
2. A clear access of 1m, gloves and matting to BS697 and BS921 are to be provided for “live” working
3. Access to the live conductors should be controlled and proper signage be placed in the area
4. All circuits to be worked on will be treated as live until verified dead. There is no exception to this requirement.
Experience of the employee is irrelevant
5. Local Government Electrical Works authority seals should not be broken and final connections will not be made
without written authority.
6. If installations are at confined space, permit-to-work system must be followed.
PPE to be used:
Safety shoes, Reflective Jackets, Safety Helmets, Protective hand gloves
Managerial / Supervisory input:
Live work will be directly monitored by the supervisors and the activity is to be performed by competent
electricians only.
Adequate PPE, first aid facilities and trained first-aiders should be ensured when “live” work is carried out
“Lock out/Tag out” (LOTO) procedure may be used wherever possible.
Training: All the electricians employed for live working should be adequately trained and competent to perform the
checks. Before authorizing to carry out live work, they will be trained on safe working practices and permit to work
systems. One among the group will be trained on first-aid treatment of electric shocks and burns.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the project manager
or his representative shall sign it before carrying out the activity on site
Note: Please refer to risk assessment on “working in hot and humid conditions”
PPE to be used
Safety shoes; Reflective Jackets, Safety Helmets, Gas respirators (if traces of toxic gases are identified after
inspection), Ear plugs (if the noise level is more due to the activities)
Managerial / Supervisory input:
Verify the approved drawings for underground services and also make sure that existing services are de-activated or
protected from hazards / damage. This work must be closely monitored by the supervisor and restrictions must be
employed for vehicles. Noise levels are to be monitored if necessary. Presence of toxic gases must be checked.
Permit-to-work system must be implemented and followed
Training
All the workmen on the job must be trained on working with excavation works. Prior to undertaking the job, daily
toolbox talk on excavation has to be conducted by the Supervisor and records to be maintained.
Approved by: Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the
Project In-charge or his representative shall sign it before carrying out the activity on site.
An emergency fire and evacuation procedure will be chalked out for each subcontractor, which will be continuously
reviewed and updated as required and practiced. Exit routes will be clear of obstructions. Hot work will be strictly
controlled, and work areas inspected 30 minutes after the completion of the job to check of any risk of fire hazard.
Quantities of liquids and chemicals will be restricted and suitable storage faculties provided record will be maintained
of routine inspection of fire-fighting equipment.
Training :
All site operators will be trained on fire and evacuation procedure on induction training. Operators using highly
flammable materials or carrying out hot work will be trained in appropriate measures site management will be aware
of the requirements of the above standards regulations.
Approved by: Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the
Project In-charge or his representative shall sign it before carrying out the activity on site.
The supervisor must ensure that all ladders and scaffolding to be used are in proper condition
Constant supervision is a must for the critical activity and deviations from the agreed procedure must be
checked.
Fault reporting systems should be encouraged.
Training:
All persons involved in the activity will be trained on the hazards and precautions in the induction training. Toolbox
talks should be conducted by concerned supervisor everyday and it should be recorded.
Approved by:
Any site-specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
1. All flammable materials in the vicinity (8m) should be removed or protected before starting the task
2. The hoses should be drawn overhead and if it is not possible, towards the edge of the room
3. Fire-fighting equipment should be available nearby (should be in working condition)
4. Cylinders should be secured properly on trolleys to prevent from toppling
5. The operation should not be carried out near energize sources, Eg., Distribution boards and near COSHH
Storage areas
6. Non-combustible or flame proof screens should be used to protect others
7. Adequate mechanical fume extraction methods should be devised when Hotwork is carried out in places other
than in open air
8. In case the cutting is carried out in access areas / slab edges / floor openings, the area above and below
should be barricaded (to prevent fall of materials and sparks). Fire watcher to be appointed for monitoring
PPE to be used
Safety shoes, Safety helmets, Safety Goggles with shade 5, Leather gloves, Reflective jackets, Jeans / aprons
Managerial/Supervisory input:
The supervisor must ensure that all precautions mentioned in the hot work permit are in place.
Constant supervision is a must for the critical activity and deviations from the agreed procedure must be checked.
Defective equipments must be returned to prevent any mishaps. The crew should be aware of using fire-fighting
equipment in case of emergency situations. Fault reporting systems should be encouraged.
Training:
Trained and experienced persons only should be employed for the purpose. Helpers, if any, should be trained on
the hazards and precautions and tool box talk should be recorded. Training on fire fighting is a must.
Approved by:
Any site-specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
Training
All the technicians will be trained on proper work procedure by the concerned supervisor. Any other training may
be arranged based on site requirements.
Approved by
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
Controls to be employed :
1 Fire emergency routes will be established adequately signed and kept free of obstruction.
2 Adequate fire alarm detection and fire-fighting equipment must be available.
3 An emergency action plan must be prepared and published for the awareness of all occupants.
4 Adequate heating, lighting, ventilating and welfare facilities should be available and must be properly maintained
5 Office should be kept clean and floor maintained clean and free from tripping hazards
6 Workstations are to be designed for safety using ergonomic principles and over-crowding should be avoided. Anti-
glare filter may be provided for workstations where employees work for long hours.
7 First-aid facilities should be made available for the site offices.
8 Designated smoking area will be provided if found necessary. Site cabins will be a no smoking area.
9 Proper manual handling and ergonomic principles should be followed.
10 Emergency contact number / procedure must be displayed at prominent places.
PPE to be used
Safety Shoes, Reflective Jackets, Nose Masks, Safety Helmets, Gloves
Managerial / Supervisory input:
Records will be maintained for routine fire inspections and the maintenance and testing of fire-fighting equipment. The
regular inspection has to be carried out by an HSE representative or any other personnel authorized by the Project In-
charge and inspections should be carried out on fire-fighting equipment. Fire exits which should not be obstructed.
COSHH assessments will be carried out for hazardous substances and the findings and precautions required will be
passed on to the employees for compliance. Manual handling techniques will be made known to the concerned
employees.
Training
All office employees will be trained on fire evacuation procedures during induction training. Evacuation drills will be
practiced. Nominated Fire Marshalls and first aiders will be adequately trained
Approved by
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-charge of his
representative shall sign it before carrying out the activity on site
PPE to be used
Safety Helmet with chin strap, Safety boots, Reflective Jacket, double lanyard full body harness.
Managerial / Supervisory input:
Managers and supervisors must ensure strict compliance to the correct measures and that the technicians are
competent and aware of the risks involved. While selecting chain pulley block and lifting gears, ensure valid load test
certificates are available with it. The lifting gears used for the activity must be stored as per manufacturer’s
instructions.
Training
All the operators involved in the task should be adequately trained and experienced in the operation. Toolbox talk will
be carried out by the supervisor on site before carrying out the operation. If necessary, check with the manufacturer
for any additional training seasons.
Approved by
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-charge
or his representative shall sign it before carrying out the activity on site
Supervisors should make sure that the workmen handling chemicals are trained in proper handling storage
and usage of chemicals.
Proper storage area should be provided on site and arrangements to clear the empty containers should be
made.
Measures to prevent accumulation of fumes in the workplace should be addressed.
Training
Training on hazards of chemicals and protective measures will be conducted to all those who handle
chemicals.
Refresher sessions will be conducted as and when needed
Toolbox talk should be conducted by the supervisors on chemicals.
Approved by
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project €In-
charge or his representative shall sign it before carrying out the activity on site
PPE to be used
Certification of drivers must be checked. Drivers must be above 18 years of age. Valid load certificate of the forklift
must be obtained. Management must enforce speed restrictions on site and monitor this. Special instructions must
be given when working on slopes and near excavations.
Training
The forklift operator should hold a valid Indian Heavy Vehicle Driving license. This applies to sub-contractors also.
Specific training about the restriction shall be given by the Supervisor/Safety professional before carrying out the
operation.
Approved by
Any site specific arrangement shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
PPE to be used
Safety shoes; Reflective Jacket, Safety Helmet, Safety goggles, Hand gloves, Coverall
Managerial / Supervisory input:
Management will monitor hand tools that can deteriorate with use to ensure they are sharpened or replaced as
necessary. Specific Checks will be made as follows
a) Chisels for mushroom heads
b) Hammer and file handles for deterioration and exposed parts
c) Double end spanners for splayed jaws
Training
Operators will be trained in safe use of hand tools during safety induction training. Toolbox talks have to be carried
out by the respective supervisors on the subject.
Approved by
Any site specific arrangement shall be incorporated in writing on the reverse of this sheet and the Project In-charge
or his representative shall sign it before carrying out the activity on site.
Machines should be positioned so as to allow clear access and avoid causing obstructions
Manufacturer’s instructions on usage on machine will be followed
COSHH assessments should be made available for any lubricating or cutting oils used
Scraps produced during activity must be disposed safely
Controls to be employed :
1 Guards are to be provided for any rotating or moving parts to prevent entanglement of body parts / clothing
2 Operators should not wear loose clothing or gloves or ornaments that can cause entanglement
3 The supply wires are to be placed safely – not on the walkway – to prevent trip hazard
4 Machine should not be left running while unattended
5 Spillage of oil on the floor should be controlled and any spillage should be wiped off immediately
6 Proper industrial sockets should be used after checking the operating voltage
7 Manual handling techniques should be used to load/unload work pieces
8 Emergency stop controls to be known to the operator
PPE to be used
Safety shoes; Reflective Jacket, safety helmet, coverall
Managerial / Supervisory input:
Control measures mentioned in COSHH assessment of the chemicals (lubricating/cutting oil) must be communicated
to the workmen. Only trained persons should be allowed to work on the machines. Machine should be stored
securely after use. Power connection to be removed after use.
Training
Operators will be trained to use the machine according to the manufacturer’s instructions
They will be made aware of health hazards present, if any, and to the concerned supervisor.
Approved by
Any site specific arrangement shall be incorporated in writing on the reverse of this sheet and the Project In-charge
or his representative shall sign it before carrying out the activity on site.
Controls to be employed:
1 The area below the lifting operation should be cleared of people and barricaded
2 Certified banksman with proper communication facility must be employed for assisting the lifting operation
3 The tower crane operator and the crew should be briefed about the activity
4 Permissible load limit should be never be exceeded
5 Operators should not wear loose clothing or gloves or ornaments that can cause entanglement
6 The supply wires are to be placed safely – not on the walkway – to prevent trip hazard
7 Machine should not be left running while unattended
8 Spillage of oil on the floor should be controlled and any spillage should be wiped off immediately
9 Proper industrial sockets should be used after checking the operating voltage
10 Manual handling techniques should be used to load/unload work pieces
PPE to be used
Safety shoes; Reflective Jacket, Safety helmet, Hand gloves
Managerial / Supervisory input:
Control measures mentioned in COSHH assessment of the chemicals (lubricating/cutting oil) must be
communicated to the workman. Only trained persons should be allowed to work on the machines. Machine
should be stored securely after use. Power connection to be removed after use.
Training
Operators will be trained to use the machine according to the manufacturer’s instructions
They will be made aware of health hazards present, if any, and to the concerned supervisor.
Approved by
Any site specific arrangement shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
Managerial/Supervisory input:
Safe systems of work are to be established and implemented before the work begins. All operations are to be
monitored and permit to work must be obtained from the authorized person by the supervisor. Any difficulty in
complying with the requirements mentioned therein must be referred to the HSE representative or Construction
Manager. Caution signs and barricade must be ensured at required locations and the supervisor must check the
work platform to ensure its stability.
Training:
Person erecting scaffold must be adequately trained and this must be recorded. Person who is working on mobile
towers must be trained about this use. Persons who inspect the scaffold must be trained and authorized to do so
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-charge
or his representative shall sign it before carrying out the activity on site.
Managerial/Supervisory input:
The management has to ensure proper machine tools and connections are provided and must monitor the
workmen for correct procedure No operator should work on machine which he is not trained to do so.
Arrangements should be done to repair damaged machines immediately once the defected is noticed/notified
Training:
Employees will be made aware of the procedures during the time of safely induction Experienced persons should
be employed for the task. The task in-charge must brief the activity and requirement to the crew.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project
Manager or his representative shall sign it before carrying out the activity on site.
Managerial/Supervisory input:
Work must be closely monitoring by the supervisor. The Operator should not work on machine which he is
not trained to do so. Arrangements should be done to repair damaged machines immediately once the
defect is noticed/notified Regular inspections should be done to ensure the interlock and other safety
devices are not bypassed/tampered with. Periodic maintenance schedule should be made for SWL
Training:
Operations, crane drivers will be trained on proper use the machine tool by the concerned supervisor. They
will also be trained on guarding earthing and by the Safety Representative. Any other training may be the
programming prior to lift
Approved by:
Any site-specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project
In-charge or his representative shall sign it before carrying out the activity on site.
PPE to be used
Safety shoes, Reflective jacket, Safety Helmet (Other PPE that are to be used depends on the activity
undertaken)
Managerial/Supervisory input:
Work must be closely monitored by the supervisor. Operator should not work on machine which he is not
trained to do so. Area must be barricaded. The area should be monitored by the respective in-charge
Training:
Workmen will be made aware of the hazards. Workers on scaffolds must be adequately trained and this
must be recorded. Person who is working on mobile towers must be trained about its use. Persons who
inspect the scaffold must be trained time to time by the concerned supervisor.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
Managerial/Supervisory input:
Measures to schedule activity that require hard labour to the cooler hours of the day must be taken.
Supervisors should ensure the above mentioned control measures are in place and are sufficient to protect
them. Instructions from client on working hours during summer should be strictly adhered to.
Training:
All the employees will be informed about heat related illnesses and the necessary precautionary measures.
Posters, notices, etc., will be posted in conspicuous locations for improving awareness on the subject
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project
In-charge or his representative shall sign it before carrying out the activity on site.
Fit-for-purpose should be arranged and all accessories and guards should be in place. The machine should be
placed in such a way not to disturb other activities. Proper grounding should be ensured before employing
workman on the machine. Training on the job should be given to all those are involved with it. Arrangements
should be done to place the machine in an area which is least affected by noise.
Controls to be employed:
1 The electrical connections should be made by a competent electrician. All the cables / plugs / sockets are
to be free of defects.
2 Dust suction machines should be provided and must be operational while operating the machine.
3 All the guards should be in place and workman should be instructed not to remove it
4 Blades should be checked for its wear and tear and worn out blades should be discarded.
5 Cutting speed should be set properly to prevent breaking of blade.
6 The work should be properly clamed to prevent any dislodgement and injury.
7 The gap between the machine blade and the lower side of the blade guide should be set to a minimum so
that finger will not be fed inside.
8 Interlocks and other safety devices should not be bypassed or modified
9 Hand gloves should not be used while feeding by hand. Use push sticks instead
10 Proper housekeeping should be ensured and finished wood and scrap wood shall be properly stacked and
kept in an allotted place.
11 Compressed air should not be used to clean floors or body/clothing
PPE to be used
Safety shoes, reflective jackets, safety helmets, dust masks
Managerial / Supervisory input:
The management has to ensure proper machine tools and connections are provided and must monitor the
workman for correct procedure. No operator should work on a machine on which he is not trained to do so.
Arrangements should be done to repair damaged machine immediately, once noticed /noticed. Regular
inspections should be done to ensure the interlocks and other safety devices are not bypassed / tampered with.
Maintenance schedules should be made for this.
Training:
All the technicians will be trained on proper use of the machine tool by the concerned supervisor. They will also
be trained on guarding, earthing and PPE by the safety representative. Any other training may be arranged
based on site requirements.
Approved by
Any side specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site
Ladders must be checked to ensure correct length, type and condition before it use. Proper selection of ladder is
must for the activity to be performed. Site made wooden ladders are prohibited from use. Ladder work should be
planned and restricted to those which can be performed with one hand only. Ladders should not be used for
heavy jobs and for works of long duration. Ladders should be stored in a safe position when not in use.
Controls to be employed:
1 The ground base for ladders must be firm and level.
2 The ladder must extend at least 1.05m above the step off point when used as a means to access scaffold or
Platform.
3 Base to height ratio of 1:4 must be maintained while placing the ladder.
4 Ladders must be secured against fall all the time (by tying at the top or bottom).
5 Over-reaching from ladders must be avoided.
6 Hand tools should only be used by tying at its end to prevent accidental fall & tools should never be left over
the top rung
7 A 3-point contact must be ensured while working with ladders.
8 Locks should be in good condition. Ensure ladders are locked before its use.
PPE to be used
Safety shoes, Reflective jacket, Safety Helmets, Double lanyard Full body harness (if 3-point contact cannot be
established with hands and legs).
Managerial/Supervisory input:
Supervisors must ensure ladders of proper length are provided for work and no over-reaching takes place.
Damaged ladders should be removed from site immediately
Section in-charges must check the method statement provided by sub-contractors is correct to ensure proper
usage of ladder. Fault reporting system should be encouraged.
Training:
All employees will be given training on safe use of ladders during induction. They should be additionally trained
through regular toolbox talks and on-site training by the supervisory staff.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project In-
charge or his representative shall sign it before carrying out the activity on site.
The activity should be properly planned and wherever possible, entry in to the tank should be avoided. Suitable
and sufficient access methods (ladders / Scaffolds) must be planned and placed. Entry if required will be
controlled by permit-to-work system. Other measures include emptying the tank of its contents before carrying
out work inside and identifying the level of oxygen inside the tank. Presence of toxic and flammable gases at
the bottom of the tank must be checked. Fire fighting measures and emergency procedures should be planned
and implemented.
Controls to be employed:
1. Oxygen level should be checked before allowing workmen inside the tank.
2. The tank may be purged with fresh air 30 minutes before entry or additional forced ventilation should be
provided depending on the depth of the tank and its configuration. The assessment should be made on
site by a competent person.
3. Presence of flammable and toxic gases should be checked.
4. Proper scaffold or ladders should be in place before inside the tank.
5. Illumination must be sufficient and halogen and incandescent lamps should not be used inside the tank.
6. The tank must be emptied before entering into it.
7. Access (like ladders) to the tank should be secured and proper.
8. Accidental release of any materials should be avoided (Tank inlet valve must be closed and kept in locked
position).
9. Activity must be serviced by an appointed watcher from outside the tank. He should be trained enough to
handle the emergency situation.
10. Personal fall arrestors should be used if found necessary.
PPE to be used
Safety shoes, Reflective Jacket, Safety Helmets, Self contained breathing apparatus if oxygen level is below
19.5% in the atmosphere.
Managerial/Supervisory input:
Managers and supervisors must ensure strict compliance to the control measures and the technicians are
competent and aware of the risks involved. They must make sure the oxygen level is within the range of 19.5%
and 22.5% inside the tank.
Training:
All the operators involved in the task should be adequately trained and experienced in the operation. Toolbox
talk will be carried out by the supervisor on site before carrying out the operation.
Approved by:
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project
Manager or his representative shall sign it before carrying out the activity on site.
1. Only authorized & trained person should operate clean or repair the machine.
2. Visual and mechanical inspecting of the machine should be carried out by the operator during start of
every shift.
3. Body of the machine to be grounded (earthed).
4. Power supply to the machine to be cut-off during the end of the shift or whenever-operator leaves the
machine unattended.
5. Sharp corners of the sheets to be blunted wherever possible.
6. Good Communication and co-ordination to be established between the operator and helper.
7. Foot pedal to be operated ONLY after positioning hands and other body parts away from the moving
platens.
8. Loose clothing to be avoided and coverall to be used to prevent dragging in the machine.
9. Chains and bracelets should be removed while working on machines.
10. Other materials and tools should not be kept / stored on machine.
11. During the folding operation the sheet has to be arrested in its position by mechanical means and NOT
by hands near to the moving parts.
PPE to be used
Supervisors should make sure that sufficiently trained personnel are employed for the task. He also should
check the condition of the machines and adherence to the accepted safe working procedure from time to
time.
Training
In addition to the safety induction training, the workmen should be trained on the machine by the concerned
supervisor.
Approved by
Any site specific arrangements shall be incorporated in writing on the reverse of this sheet and the Project
Manager of his representative shall sign it before carrying out the activity on site.