Drywall VS CHB
Drywall VS CHB
SUMMARY
QTY UNIT PRICE/unit TOTAL PRICE
CHB 628 pcs 16 10048
CEMENT 47 bags 210 9870
SAND 3 cu.m. 950 2850
GRAVEL 2 cu.m. 1200 2400
10mm dia BARS 33 pcs 155 5115
TIE WIRE #16 2 kilo 100 200
LABOR 1 unit 17942 17942
TOTAL 48425
DRY WALL
40737.5
COST PER SQ. M. = = PHP 890.63 / sq.m.
45.74
CHB ESTIMATES
MORTAR
# of # OF
NAME H L OPENING TOTAL AREA
LAYERS CHB FILLER
CHB REINFORCEMENT
TOTAL ARE CHOSEN COMMERCIAL LEGNTH,m NO. OF PCS SAY
195.75 6 32.62 33
33 PCS 10 mm X6 m
TIEWIRE, MASONRY
WALL AREAFACTOR KILO SAY
45.74 0.024 1.09764 2
2 KILO
TES
MORTAR # OF
SAND
CEMENT GRAVEL
LAYER PLASTER (mᶟ)
BAGS
0.09 0.23 9 0.46 0.38
0.09 0.11 5 0.25 0.18
0.17 0.43 16 0.87 0.72
0.17 0.38 14 0.77 0.62
1.14 44 2.357403 1.90568
CHB LAYING (57
LABOR COSTS
LAYERS
NFORCEMENT FOREMAN
MASON
98.33 LABORER/HELPER
98.33 m long
LABOR COSTS
FOREMAN
MASON
CS 10 mm X6 m LABORER/HELPER
CHB LAYING (574 pcs)
QUANTITY
RATE TOTAL COSTS
MAN POWER # OF DAYS
1 2 707 1414
3 2 450 2700
3 2 400 2400
6514
QUANTITY
RATE TOTAL COSTS
MAN POWER # OF DAYS
1 4 707 2828
3 4 450 5400
2 4 400 3200
11428
CHB ESTIMATES
# OF 8mm
NAME H L OPENING TOTAL AREA CEMENT MORTAR
BOARD
W1 2.65 3.45 0.00 9.14 4.00 0.69
W2 2.65 3.45 4.80 4.34 2.00 0.33
W3 2.65 6.5 0.00 17.22 6.00 1.29
W4 2.65 6.5 2.20 15.02 6.00 1.13
45.74 18.00
TOP &
BOTTOM -- 49.74 18.00
FRAME
133.00
# OF
SAND
MORTAR CEMENT
(mᶟ)
BAGS
0.69 5 0.91
0.33 3 0.43
1.29 9 1.71
1.13 8 1.49
25 4.53 INSTALLATION OF METAL STUDS (133 pcs) &
CEMENT BOARD
QUANTITY
LABOR COSTS
AR IN EVERY 800mm MAN POWER # OF DAYS
EINFORCEMENT FOREMAN 1 3
LEADMAN 1 3
CARPENTER
33.58 CARPENTER 3 3
6.00 pcs of 10mm x 6m Rebars
QUANTITY
LABOR COSTS
MAN POWER # OF DAYS
FOREMAN 1 1
LABORER/HELPER 4 1
AL STUDS (133 pcs) &
BOARD
707 2121
617 1851
400 3600
7572
707 707
400 1600
2307