Professional Documents
Culture Documents
Week 5 PP
Week 5 PP
Week 5 PP
Define each term in your own words, calculate these values for the above project, and show
your work:
A budgeted bost baseline is the planned and approved total cost for completing all project activities
Budget at completion (BAC) is the total planned budgeted cost for completing an entire project.
Planned Value as of May 1 is the amount of cost required to complete the targeted tasks till May1
4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete.
Earned value is the value of work actually completed and approved at a specific point in time.
EV= $140,000
5. SV as of May 1.
6. The actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May1
Cost Variance = Difference between the Earned value and Actual cost at any point in the project.
CV= -$20,000
Scheduled Performance is the ratio of Earned value per date to the planned value to date.
SPI=EV/PV
3
SPI= 140,000/190,000
SPI= 0.737
CPI is the ratio of Earned value to the Actual cost at any point in the project.
CPI= EV/AC
9. Estimate to complete (ETC), if the previous cost variances will not affect future costs.
ETC is the amount of cost required to complete the unfinished activities of the project.
ETC = (BAC-EV)/CPI
=(720000-140000)
ETC= 580,000
EAC=AC+ETC
EAC= 160,000+580,000
EAC= 740,000
4
References:
Watts, A. (2014). Project Management. Victoria, B.C.: BCcampus. Retrieved from https://open-
textbc.ca/projectmanagement/.